Panai Link Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1261 |
Sanction Cost: |
54.05 lakh |
Length:
|
1.000 KM. |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 88
Package Name: 
UDRP/PWD/02/08/RD/077
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 23-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/077
Contractor Name: Dream Real Infra
|
Start Date: 30-12-2015
Intended Completion Date: 31-10-2018
Original End Date: 29-03-2017 |
Total Bond Cost: 55686855.62 (556.87 lakh)
Variation Cost: -905472.35 (-9.05 lakh) Hence Total Bond Cost is 54781383.27 (547.81 lakh)
|
Sub Project Cost: 48.52 lakh
Variation Cost of Sub Project: 7078825.58 (70.79 lakh)
Total Sub Project Cost:
119.31 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.00 KM | 0.00 | 10-06-2016 | 15-03-2017 | 0.00 KM | 0.00 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 345.00 m | 11.52 | 16-05-2016 | 20-03-2017 | 345.00 m | 345.00 m | 30.78 | 11.52 | 3. | G-3 | 0.50 KM | 3.73 | 12-03-2017 | 12-09-2017 | 0.50 KM | 0.50 KM | 9.96 | 3.73 | 4. | PC/CC i/c Prime Coat, Tack Coat | 1.00 KM | 12.08 | 20-09-2017 | 15-12-2017 | 1.00 KM | 1.00 KM | 32.29 | 12.08 | 5. | Cause Way | 0.00 No | 0.00 | 02-03-2017 | 20-03-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 6. | longitudinal Drain | 930.00 m | 7.14 | 20-04-2016 | 30-09-2017 | 930.00 m | 930.00 m | 19.08 | 7.14 | 7. | Crash Barrier | 0.00 m | 0.00 | 01-03-2017 | 30-09-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 8. | Parapet | 75.00 No | 2.33 | 10-01-2017 | 30-11-2017 | 75.00 No | 75.00 No | 6.24 | 2.33 | 9. | Road Furniture | 26.00 No | 0.62 | 21-10-2016 | 02-10-2018 | 26.00 No | 26.00 No | 1.65 | 0.62 |
Total Amount: |
37.42 |
|
100 |
37.42 |
|
Remarks:
No Remarks
Work Program Made On:
06-02-2016 } ?>
Updation of work program on:
14-01-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-May-2016 | 5.07 lakh | 2. | 30-June-2016 | 2.03 lakh | 3. | 24-March-2017 | 10.45 lakh | 4. | 30-November-2017 | 0.84 lakh | 5. | 31-March-2018 | 87.36 lakh | 6. | 06-June-2018 | 5.54 lakh | 7. | 13-July-2018 | 4.59 lakh |
Total |
115.88 lakh |
% Payment | 97.13 % |
|
Advance Amount: 79.00 lakh
Recovered Amount: 86.50 lakh
Balance to be Recovered -7.50 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 276 No. of Test Done : 255 No. of Test Passed : 243 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.10 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 36 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-11-2017 | 0+730 | Pc thickness checking | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
2. | 16-11-2017 | 0+530 | Laying premix carpet | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
3. | 15-11-2017 | 0.380 | OGPC Work in progress work is satisfactory | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 01-11-2017 | 0.750 | Cement pavement work in progress instruction given to contractor to complete use of PPE | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
5. | 06-10-2016 | 0.500 | Cement mortar rejected due to quality of sand | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
6. | 03-10-2016 | 0.490 | RW banded work in progress | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
7. | 06-08-2016 | 0.800 | RW work in progress | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
8. | 06-08-2016 | 0.917 | Rw work in progress | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
9. | 25-07-2016 | 0.380 | Pucca drain | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
10. | 11-07-2016 | 0.870 | Site visit by EE sir | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
11. | 17-06-2016 | 0.510 | Pucca drain | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
12. | 12-05-2016 | 0.000 | Information board | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
13. | 10-05-2016 | 0.570 | pucca drain progress work. | Vinod Singh Chauhan | JE | UDRP R&B Gopeshwar | See Pic |
14. | 10-05-2016 | 0.570 | Pucca drain in progress | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
15. | 10-05-2016 | 0.730 | Pucca drain | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
16. | 10-05-2016 | 0.730 | pucca drain | Vinod Singh Chauhan | JE | UDRP R&B Gopeshwar | See Pic |
17. | 07-05-2016 | O.720 | Cube casting M15 | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
18. | 07-05-2016 | 0.750 | Mixing concrete for kc drain M20 | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
19. | 06-05-2016 | 0.750 | Cube casting M10 drain Pcc | Pankaj Singh Rawat | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
20. | 05-05-2016 | Ch 0.590 | Thickness checking of drain | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
|
|