Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Panai Link Road Work Completed
Project: UDRP-RB UID: 1261 Sanction Cost: 54.05  lakh Length: 1.000 KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 88        Package Name:  UDRP/PWD/02/08/RD/077        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 23-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/077      Contractor Name: Dream Real Infra
Start Date:  30-12-2015      Intended Completion Date:  31-10-2018      Original End Date:  29-03-2017
Total Bond Cost: 55686855.62 (556.87 lakh)        Variation Cost: -905472.35 (-9.05 lakh)    Hence Total Bond Cost is   54781383.27 (547.81 lakh) 
Sub Project Cost: 48.52  lakh        Variation Cost of Sub Project: 7078825.58  (70.79 lakh)       Total Sub Project Cost:   119.31 lakh
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.00 KM0.0010-06-201615-03-20170.00 KM0.00 KM00.00
2.R/Wall, B/ Wall Type Protection works345.00 m11.5216-05-201620-03-2017345.00 m345.00 m30.7811.52
3.G-30.50 KM3.7312-03-201712-09-20170.50 KM0.50 KM9.963.73
4.PC/CC i/c Prime Coat, Tack Coat1.00 KM12.0820-09-201715-12-20171.00 KM1.00 KM32.2912.08
5.Cause Way0.00 No0.0002-03-201720-03-20170.00 No0.00 No00.00
6.longitudinal Drain930.00 m7.1420-04-201630-09-2017930.00 m930.00 m19.087.14
7.Crash Barrier0.00 m0.0001-03-201730-09-20170.00 m0.00 m00.00
8.Parapet75.00 No2.3310-01-201730-11-201775.00 No75.00 No6.242.33
9.Road Furniture26.00 No0.6221-10-201602-10-201826.00 No26.00 No1.650.62
Total Amount: 37.42 100   37.42
Remarks: No Remarks       Work Program Made On: 06-02-2016        Updation of work program on: 14-01-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-May-20165.07  lakh
2.30-June-20162.03  lakh
3.24-March-201710.45  lakh
4.30-November-20170.84  lakh
5.31-March-201887.36  lakh
6.06-June-20185.54  lakh
7.13-July-20184.59  lakh
Total 115.88  lakh
% Payment97.13 %
Advance Amount:  79.00  lakh        Recovered Amount:  86.50  lakh        Balance to be Recovered  -7.50  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 276   No. of Test Done : 255    No. of Test Passed : 243   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.10
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 36
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-11-20170+730Pc thickness checkingAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
2.16-11-20170+530Laying premix carpetAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
3.15-11-20170.380OGPC Work in progress work is satisfactoryAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.01-11-20170.750Cement pavement work in progress instruction given to contractor to complete use of PPEAshwani KumarREDSC4 R&B WB Chamoli See Pic
5.06-10-20160.500Cement mortar rejected due to quality of sandAshwani KumarREDSC4 R&B WB Chamoli See Pic
6.03-10-20160.490RW banded work in progressPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
7.06-08-20160.800RW work in progressPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
8.06-08-20160.917Rw work in progressPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
9.25-07-20160.380Pucca drainPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
10.11-07-20160.870Site visit by EE sirPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
11.17-06-20160.510Pucca drainPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
12.12-05-20160.000Information boardPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
13.10-05-20160.570pucca drain progress work.Vinod Singh ChauhanJEUDRP R&B Gopeshwar See Pic
14.10-05-20160.570Pucca drain in progressPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
15.10-05-20160.730Pucca drainPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
16.10-05-20160.730pucca drainVinod Singh ChauhanJEUDRP R&B Gopeshwar See Pic
17.07-05-2016O.720Cube casting M15Pankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
18.07-05-20160.750Mixing concrete for kc drain M20Pankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
19.06-05-20160.750Cube casting M10 drain PccPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic
20.05-05-2016Ch 0.590Thickness checking of drainKirti Vardhan NegiAEDEA WB Gopeshwar See Pic