Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Narayanbagar-Kaub Motor Road Work Completed
Project: UDRP-RB UID: 1259 Sanction Cost: 622.19  lakh Length: 6.350 KM.
District: Chamoli Block: Narain Bagar Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 93        Package Name:  UDRP/PWD/02/37/RD/082        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/37/RD/082      Contractor Name: Universal Associates
Start Date:  11-06-2015      Intended Completion Date:  31-05-2017      Original End Date:  10-09-2016
Total Bond Cost: 53596905.6 (535.97 lakh)        Variation Cost: 8005875.11 (80.06 lakh)    Hence Total Bond Cost is   61602780.71 (616.03 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 348374 for 13 days        LD Analysis for Milestone2: calculated LD is Rs 1795466 for 67 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence6.35 KM14.4225-07-201501-03-20176.35 KM6.35 KM3.1914.42
2.R/Wall, B/ Wall Type Protection works1760.00 m130.8809-07-201502-03-20171760.00 m1760.00 m28.96130.88
3.G-26.35 KM68.2017-02-201612-02-201712.70 KM12.70 KM15.0968.20
4.G-36.35 KM48.7302-04-201611-04-20176.35 KM6.35 KM10.7848.73
5.PC/CC i/c Prime Coat, Tack Coat6.35 KM79.3825-03-201724-05-20176.35 KM6.35 KM17.5779.38
6.Cause Way9.00 No10.0106-10-201517-02-20179.00 No9.00 No2.2210.01
7.Culverts/Scupper 34.00 No64.8401-08-201525-02-201634.00 No34.00 No14.3564.84
8.longitudinal Drain6350.00 m26.9215-01-201617-05-20176350.00 m6350.00 m5.9626.92
9.Crash Barrier0.00 m0.0009-04-201701-05-20170.00 m0.00 m00.00
10.Parapet600.00 No6.2911-04-201714-05-2017600.00 No600.00 No1.396.29
11.Road Furniture182.00 No2.2202-09-201618-05-2017182.00 No182.00 No0.492.22
Total Amount: 451.89 100   451.89
Remarks: No Remarks       Work Program Made On: 13-07-2015        Updation of work program on: 23-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-September-201545.43  lakh
2.01-October-201517.05  lakh
3.31-January-2016103.11  lakh
4.04-March-201649.24  lakh
5.28-March-201613.24  lakh
6.02-May-201630.33  lakh
7.29-June-201612.20  lakh
8.30-June-201616.56  lakh
9.30-August-201617.97  lakh
10.30-September-201651.73  lakh
11.25-January-201722.41  lakh
12.22-March-201743.94  lakh
13.31-March-201727.96  lakh
14.25-May-201766.95  lakh
15.14-July-201764.14  lakh
16.27-February-201833.78  lakh
Total 616.04  lakh
% Payment 100 %
Advance Amount:  86.20  lakh        Recovered Amount:  86.20  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 279   No. of Test Done : 297    No. of Test Passed : 276   No. of Test Failed : 21   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.11
Number of Notice(s) issued: 68

Mobile Pic Upload

Number of Pics Available on Web Repository: 74
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-03-2017Ch 0.950Emulsion for primer of hincolKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.31-03-2017Ch 5.915Thickness checking of G2 G3 layer found 25 cmKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.25-03-2017Ch 6.180Bitumen extraction test of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
4.25-03-2017Ch 6.180Laying of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
5.25-03-2017Ch 6.212Rolling of seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.18-03-2017chainage 0+640Road width checking found 6.10 mSohanbir SinghJEUDRP R&B Chamoli See Pic
7.07-02-2017Xh 5.250Screening material over G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.30-01-2017Ch 5.250Rolling of G3Kirti Vardhan NegiAEDEA WB Gopeshwar See Pic
9.30-01-2017Ch 3.675Checking of measurements by Ee sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.23-09-20160.225Checking of G2 layer by CE sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.25-06-2016C.h. 2.250Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
12.25-06-2016Ch2.250Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
13.14-06-20164+000G2 lst layerMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
14.11-06-2016Ch 0.825AIV test FOR G2 materialKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
15.11-06-2016C.h. 5 775Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
16.11-06-2016Ch 5.750Hume pipeKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
17.11-06-2016Ch 3.2005 m span culvertKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
18.09-03-20165.625G2Sudhir KumarREDSC1 R&B WB Chamoli See Pic
19.09-03-20160.140Checking of superelevationSudhir KumarREDSC1 R&B WB Chamoli See Pic
20.09-03-20165.825scupperVinod Singh ChauhanJEUDRP R&B Gopeshwar See Pic