Nanprayag Devkhal to Gurshal Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1257 |
Sanction Cost: |
188.78 lakh |
Length:
|
2.250 KM. |
District: |
Chamoli |
Block: |
Dasholi |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 59
Package Name: 
UDRP/PWD/02/03/RD/030b
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/03/RD/030b
Contractor Name: R. B. Construction
|
Start Date: 14-07-2015
Intended Completion Date: 25-04-2017
Original End Date: 13-10-2016 |
Total Bond Cost: 31427309.65 (314.27 lakh)
Variation Cost: 371761.57 (3.72 lakh) Hence Total Bond Cost is 31799071.22 (317.99 lakh)
|
Sub Project Cost: 126.10 lakh
Variation Cost of Sub Project: 2690281.28 (26.9 lakh)
Total Sub Project Cost:
153 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 722844 for 46 days
LD Analysis for Milestone2: calculated LD is Rs 5028480 for 320 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.00 KM | 2.14 | 25-08-2015 | 01-12-2016 | 1.00 KM | 1.00 KM | 2.16 | 2.14 | 2. | R/Wall, B/ Wall Type Protection works | 266.00 m | 31.32 | 05-09-2015 | 25-12-2016 | 266.00 m | 266.00 m | 31.47 | 31.32 | 3. | GSB/RBI/G-1 | 2.00 KM | 12.20 | 05-12-2015 | 15-12-2016 | 2.00 KM | 2.00 KM | 12.26 | 12.20 | 4. | G-2 | 2.15 KM | 9.68 | 01-02-2016 | 25-01-2017 | 2.15 KM | 2.15 KM | 9.72 | 9.68 | 5. | G-3 | 2.15 KM | 13.36 | 30-12-2016 | 20-02-2017 | 2.15 KM | 2.15 KM | 13.42 | 13.36 | 6. | PC/CC i/c Prime Coat, Tack Coat | 2.15 KM | 24.87 | 01-03-2017 | 28-03-2017 | 2.05 KM | 2.05 KM | 24.99 | 24.87 | 7. | Culverts/Scupper | 4.00 No | 5.95 | 02-10-2015 | 16-12-2017 | 4.00 No | 4.00 No | 5.98 | 5.95 |
Total Amount: |
99.52 |
|
100 |
99.52 |
|
Remarks:
No Remarks
Work Program Made On:
14-08-2015 } ?>
Updation of work program on:
19-11-2016
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-January-2016 | 16.44 lakh | 2. | 30-March-2016 | 21.45 lakh | 3. | 23-March-2017 | 42.44 lakh | 4. | 31-March-2017 | 9.76 lakh | 5. | 28-July-2017 | 25.34 lakh | 6. | 19-December-2017 | 40.65 lakh | 7. | 30-May-2018 | 9.06 lakh |
Total |
165.14 lakh |
% Payment | 107.93 % |
|
Advance Amount: 36.53 lakh
Recovered Amount: 6.53 lakh
Balance to be Recovered 30.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 127 No. of Test Done : 150 No. of Test Passed : 137 No. of Test Failed : 13 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.70 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 79 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-09-2017 | Km 1 | Checking of road width. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
2. | 13-05-2017 | Chainage 1+435 | Thickness checking of pc and seal coat by JE and AE WB PWD | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
3. | 10-05-2017 | Ch. 1+075 | Seal coat work compete | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
4. | 10-05-2017 | Ch.1+025 | Tack coat work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
5. | 09-05-2017 | Ch.0+325 | PC work rolling in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
6. | 08-05-2017 | 0.400 | PC Work is in progress thickness found 22 mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
7. | 08-05-2017 | 0.350 | Seal coat work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
8. | 04-05-2017 | Ch.0+925 | PC Rolling Work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
9. | 28-03-2017 | Ch. 0+900 | KC type drain work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
10. | 08-03-2017 | Ch-1.475 | Thickness checking G1 G2 G3 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
11. | 14-02-2017 | ch.1+600 | Superelevation checked found 8.5% | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
12. | 07-02-2017 | Ch-1.375 | Thickness checking of G1,G2, & G3 found 255 mm | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
13. | 02-02-2017 | Ch-1.900 | Gradation for G1 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 02-02-2017 | Ch-1.200 | Rolling for G1 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
15. | 01-02-2017 | Ch-1.300 | G3Material stocking | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 01-02-2017 | Ch-1.800 | Thickness checking for G2 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
17. | 15-10-2016 | Ch-1.250 | Rcc work | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
18. | 08-10-2016 | 1.250 | Slab casting 5.00 M span culvert | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
19. | 07-10-2016 | Ch 1.200 | Casting of slab | Pradeep Kumar Negi | JE | UDRP R&B Gopeshwar | See Pic |
20. | 28-09-2016 | Ch-1.260 | R/w | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|