Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nanprayag Devkhal to Gurshal Motor Road Work Completed
Project: UDRP-RB UID: 1257 Sanction Cost: 188.78  lakh Length: 2.250 KM.
District: Chamoli Block: Dasholi Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 59        Package Name:  UDRP/PWD/02/03/RD/030b        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 07-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/03/RD/030b      Contractor Name: R. B. Construction
Start Date:  14-07-2015      Intended Completion Date:  25-04-2017      Original End Date:  13-10-2016
Total Bond Cost: 31427309.65 (314.27 lakh)        Variation Cost: 371761.57 (3.72 lakh)    Hence Total Bond Cost is   31799071.22 (317.99 lakh) 
Sub Project Cost: 126.10  lakh        Variation Cost of Sub Project: 2690281.28  (26.9 lakh)       Total Sub Project Cost:   153 lakh
LD Analysis for Milestone1: calculated LD is Rs 722844 for 46 days        LD Analysis for Milestone2: calculated LD is Rs 5028480 for 320 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.00 KM2.1425-08-201501-12-20161.00 KM1.00 KM2.162.14
2.R/Wall, B/ Wall Type Protection works266.00 m31.3205-09-201525-12-2016266.00 m266.00 m31.4731.32
3.GSB/RBI/G-12.00 KM12.2005-12-201515-12-20162.00 KM2.00 KM12.2612.20
4.G-22.15 KM9.6801-02-201625-01-20172.15 KM2.15 KM9.729.68
5.G-32.15 KM13.3630-12-201620-02-20172.15 KM2.15 KM13.4213.36
6.PC/CC i/c Prime Coat, Tack Coat2.15 KM24.8701-03-201728-03-20172.05 KM2.05 KM24.9924.87
7.Culverts/Scupper 4.00 No5.9502-10-201516-12-20174.00 No4.00 No5.985.95
Total Amount: 99.52 100   99.52
Remarks: No Remarks       Work Program Made On: 14-08-2015        Updation of work program on: 19-11-2016       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-January-201616.44  lakh
2.30-March-201621.45  lakh
3.23-March-201742.44  lakh
4.31-March-20179.76  lakh
5.28-July-201725.34  lakh
6.19-December-201740.65  lakh
7.30-May-20189.06  lakh
Total 165.14  lakh
% Payment107.93 %
Advance Amount:  36.53  lakh        Recovered Amount:  6.53  lakh        Balance to be Recovered  30.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 127   No. of Test Done : 150    No. of Test Passed : 137   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.70
Number of Notice(s) issued: 2

Mobile Pic Upload

Number of Pics Available on Web Repository: 79
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-09-2017Km 1Checking of road width.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
2.13-05-2017Chainage 1+435Thickness checking of pc and seal coat by JE and AE WB PWDAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
3.10-05-2017Ch. 1+075Seal coat work competeSohanbir SinghJEUDRP R&B Chamoli See Pic
4.10-05-2017Ch.1+025Tack coat work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
5.09-05-2017Ch.0+325PC work rolling in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
6.08-05-20170.400PC Work is in progress thickness found 22 mmAshwani KumarREDSC4 R&B WB Chamoli See Pic
7.08-05-20170.350Seal coat work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
8.04-05-2017Ch.0+925PC Rolling Work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
9.28-03-2017Ch. 0+900KC type drain workSohanbir SinghJEUDRP R&B Chamoli See Pic
10.08-03-2017Ch-1.475Thickness checking G1 G2 G3Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
11.14-02-2017ch.1+600Superelevation checked found 8.5%Sohanbir SinghJEUDRP R&B Chamoli See Pic
12.07-02-2017Ch-1.375Thickness checking of G1,G2, & G3 found 255 mmPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
13.02-02-2017Ch-1.900Gradation for G1Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
14.02-02-2017Ch-1.200Rolling for G1Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
15.01-02-2017Ch-1.300G3Material stockingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.01-02-2017Ch-1.800Thickness checking for G2Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.15-10-2016Ch-1.250Rcc workPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
18.08-10-20161.250Slab casting 5.00 M span culvertAshwani KumarREDSC4 R&B WB Chamoli See Pic
19.07-10-2016Ch 1.200Casting of slabPradeep Kumar NegiJEUDRP R&B Gopeshwar See Pic
20.28-09-2016Ch-1.260R/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic