Mitiyala - Kirsal MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1255 |
Sanction Cost: |
202.24 lakh |
Length:
|
2.000 KM. |
District: |
Chamoli |
Block: |
Gairsain |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 116
Package Name: 
UDRP/PWD/02/36/RD/105
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 05-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/105
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 12-01-2016
Intended Completion Date: 10-06-2019
Original End Date: 11-04-2017 |
Total Bond Cost: 103646807.66 (1036.47 lakh)
Variation Cost: 25046778.29 (250.47 lakh) Hence Total Bond Cost is 128693585.95 (1286.94 lakh)
|
Sub Project Cost: 166.56 lakh
Variation Cost of Sub Project: 2603309.67 (26.03 lakh)
Total Sub Project Cost:
192.59 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 9120848 for 176 days
LD Analysis for Milestone2: calculated LD is Rs 24615925 for 475 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.75 KM | 28.22 | 15-11-2016 | 20-04-2018 | 1.75 KM | 1.75 KM | 13.88 | 28.22 | 2. | R/Wall, B/ Wall Type Protection works | 740.00 m | 68.66 | 25-11-2016 | 30-11-2018 | 740.00 m | 740.00 m | 33.77 | 68.66 | 3. | G-2 | 4.00 KM | 23.71 | 20-01-2017 | 05-04-2018 | 4.00 KM | 4.00 KM | 11.67 | 23.71 | 4. | G-3 | 2.00 KM | 16.98 | 10-02-2017 | 10-04-2018 | 2.00 KM | 2.00 KM | 8.35 | 16.98 | 5. | PC/CC i/c Prime Coat, Tack Coat | 2.00 KM | 23.44 | 01-04-2018 | 15-06-2018 | 2.00 KM | 2.00 KM | 11.53 | 23.44 | 6. | Cause Way | 1.00 No | 3.22 | 01-12-2016 | 25-11-2018 | 1.00 No | 1.00 No | 1.59 | 3.22 | 7. | Culverts/Scupper | 4.00 No | 29.03 | 01-12-2016 | 10-04-2018 | 4.00 No | 4.00 No | 14.28 | 29.03 | 8. | longitudinal Drain | 2000.00 m | 4.10 | 15-02-2017 | 30-10-2018 | 2000.00 m | 2000.00 m | 2.02 | 4.10 | 9. | Crash Barrier | 1.00 m | 0.00 | 25-05-2018 | 12-12-2018 | 1.00 m | 1.00 m | 0 | 0.00 | 10. | Parapet | 40.00 No | 1.77 | 01-06-2018 | 26-12-2018 | 40.00 No | 40.00 No | 0.87 | 1.77 | 11. | Road Furniture | 73.00 No | 0.60 | 01-03-2017 | 31-12-2018 | 73.00 No | 73.00 No | 0.3 | 0.60 | 12. | Env. Man & Moni Plan | 1.00 Job | 3.55 | 01-12-2018 | 31-12-2018 | 1.00 Job | 1.00 Job | 1.75 | 3.55 |
Total Amount: |
203.28 |
|
100 |
203.28 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 10-February-2017 | 25.01 lakh | 2. | 13-October-2017 | 23.51 lakh | 3. | 25-November-2017 | 17.85 lakh | 4. | 04-January-2018 | 11.42 lakh | 5. | 28-February-2018 | 20.51 lakh | 6. | 28-March-2018 | 9.84 lakh | 7. | 31-May-2018 | 37.53 lakh | 8. | 23-August-2018 | 1.15 lakh | 9. | 29-November-2018 | 7.48 lakh | 10. | 16-February-2019 | 17.60 lakh | 11. | 27-February-2019 | 3.14 lakh | 12. | 30-March-2019 | 4.62 lakh | 13. | 22-May-2019 | 2.48 lakh | 14. | 19-June-2019 | 0.20 lakh | 15. | 12-July-2019 | 18.74 lakh | 16. | 15-July-2019 | 2.22 lakh |
Total |
203.3 lakh |
% Payment | 105.56 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1005 No. of Test Done : 1305 No. of Test Passed : 1258 No. of Test Failed : 47 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.09 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 16 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 01-02-2018 | Ch-1.670 km | Extra hill side cutting | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
2. | 21-12-2017 | Ch-1.160 km | Checking heights of retaining wall | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
3. | 27-11-2017 | Ch 1.240 | Checking of R/Wall foundation found ok. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
4. | 21-11-2017 | 0.000 km | Information board at starting point | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
5. | 21-11-2017 | 1.050 km | Making superelevation | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
6. | 03-11-2017 | 1+050 km | Protection work | Shivam Kumar | JE | UDRP R&B Karnprayag | See Pic |
7. | 25-08-2017 | At ch 1/0-1 | Road U bend curve width checking by AE sir | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
8. | 25-08-2017 | At ch 0/27-28 | Heavy Slip at road | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
9. | 24-07-2017 | Ch.1+700 | SRMD, Road close due to heavy Rain | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
10. | 12-04-2017 | Ch.1.850 | Rejected wbm g2 due to under size | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
11. | 12-04-2017 | Ch.1.375 | Scupper construction work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
12. | 12-04-2017 | 0.350 | G2 stock | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
13. | 25-02-2016 | 1.610 | transit visit | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 25-02-2016 | 0.030 | Transit visit | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
15. | 23-08-2015 | CH_0.100 | Taking GPS for Matai Kirshal road | Jayendra Pundir | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
16. | 22-08-2015 | Ch 1.150 | Gps location | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|