Lolti - Kasbinagar Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1252 |
Sanction Cost: |
197.54 lakh |
Length:
|
3.520 KM. |
District: |
Chamoli |
Block: |
Tharali |
Constituency: |
Tharali |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 108
Package Name: 
UDRP/PWD/02/RD/097
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 11-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/RD/097
Contractor Name: Sansun Contractors Pvt. Ltd.
|
Start Date: 18-09-2015
Intended Completion Date: 25-06-2017
Original End Date: 17-12-2016 |
Total Bond Cost: 74543585.76 (745.44 lakh)
Variation Cost: 18843460.57 (188.43 lakh) Hence Total Bond Cost is 93387046.33 (933.87 lakh)
|
Sub Project Cost: 171.33 lakh
Variation Cost of Sub Project: 534793.61 (5.35 lakh)
Total Sub Project Cost:
176.68 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2459952 for 66 days
LD Analysis for Milestone2: calculated LD is Rs 3689928 for 99 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 3.00 KM | 9.81 | 05-10-2015 | 15-03-2017 | 3.00 KM | 3.00 KM | 6.94 | 9.81 | 2. | R/Wall, B/ Wall Type Protection works | 847.00 m | 37.78 | 15-10-2015 | 10-04-2017 | 847.00 m | 847.00 m | 26.72 | 37.78 | 3. | G-2 | 1.00 KM | 5.39 | 01-01-2017 | 15-04-2017 | 0.50 KM | 0.50 KM | 3.81 | 5.39 | 4. | G-3 | 1.00 KM | 7.80 | 12-01-2017 | 15-05-2017 | 0.70 KM | 0.70 KM | 5.52 | 7.80 | 5. | PC/CC i/c Prime Coat, Tack Coat | 3.50 KM | 44.75 | 01-10-2016 | 25-05-2017 | 3.50 KM | 3.50 KM | 31.65 | 44.75 | 6. | Culverts/Scupper | 19.00 No | 18.39 | 20-01-2016 | 15-03-2017 | 19.00 No | 19.00 No | 13.01 | 18.39 | 7. | longitudinal Drain | 3500.00 m | 15.85 | 10-02-2016 | 12-05-2017 | 3500.00 m | 3500.00 m | 11.21 | 15.85 | 8. | Parapet | 0.00 No | 0.00 | 02-07-2016 | 24-05-2017 | 50.00 No | 50.00 No | 0 | 0.00 | 9. | Road Furniture | 150.00 No | 1.62 | 03-09-2016 | 30-05-2017 | 150.00 No | 150.00 No | 1.14 | 1.62 |
Total Amount: |
141.39 |
|
100 |
141.39 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
24-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 25-January-2016 | 1.93 lakh | 2. | 04-March-2016 | 2.78 lakh | 3. | 31-March-2016 | 18.56 lakh | 4. | 03-May-2016 | 8.93 lakh | 5. | 30-June-2016 | 27.56 lakh | 6. | 18-October-2016 | 11.63 lakh | 7. | 26-October-2016 | 23.75 lakh | 8. | 17-December-2016 | 16.24 lakh | 9. | 23-March-2017 | 10.14 lakh | 10. | 13-October-2017 | 31.19 lakh | 11. | 27-November-2017 | 4.45 lakh | 12. | 17-February-2018 | 18.47 lakh | 13. | 13-September-2018 | 1.28 lakh |
Total |
176.91 lakh |
% Payment | 100.13 % |
|
Advance Amount: 25.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 25.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 300 No. of Test Done : 301 No. of Test Passed : 255 No. of Test Failed : 46 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 37 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-12-2016 | 2.525 | old.p.c | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
2. | 30-12-2016 | 2.525 | old p.c | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
3. | 14-12-2016 | 1.840 | p.c.work.cheking | Ajay Narayan Pandey | RE | DSC1 R&B WB Chamoli | See Pic |
4. | 14-12-2016 | 2.340 | Checking measurement of pc work | Ajay Narayan Pandey | RE | DSC1 R&B WB Chamoli | See Pic |
5. | 24-10-2016 | 2.250 | Laying of type c seal coat | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
6. | 24-10-2016 | 2.300 | Rolling of seal coat | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
7. | 10-10-2016 | 3.000 | Tempreture checking in seal coat material | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
8. | 10-10-2016 | 3.025 | Rolling of type c seal coat at lolti kasbinagar | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
9. | 02-10-2016 | 3.575 | Rolling of type c seal coat | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
10. | 27-09-2016 | 3.400 | G3 Wbm in patch work | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
11. | 28-08-2016 | 1.900 | B/W Rejected due to quality of mortar | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
12. | 18-07-2016 | 1520 | Lolti Kashminagar | Manish Vikal | Contractor Site Engineer | UDRP R&B Chamoli | See Pic |
13. | 18-07-2016 | 1500 | Lolti Kashminagar | Manish Vikal | Contractor Site Engineer | UDRP R&B Chamoli | See Pic |
14. | 04-06-2016 | 0.160 | p.c.peach | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
15. | 03-06-2016 | 0.110 | p.c.work | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 02-06-2016 | 1.360 | deran work | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
17. | 26-05-2016 | 0.720 | p.c. | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
18. | 18-05-2016 | 2570 | Pc Patch | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
19. | 05-04-2016 | 2500 | Dismentaling of scuper due to poor work menship in visit of E.E A.E R.E and contractor representative | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 05-04-2016 | 1450 | Instruction given to contracter repersentive for cress barier steel by E.E sir at ch 1450 | Vikash Singh | JE | UDRP R&B Gopeshwar | See Pic |
|
|