Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Lolti - Kasbinagar Motor Road Work Completed
Project: UDRP-RB UID: 1252 Sanction Cost: 197.54  lakh Length: 3.520 KM.
District: Chamoli Block: Tharali Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 108        Package Name:  UDRP/PWD/02/RD/097        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 11-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/RD/097      Contractor Name: Sansun Contractors Pvt. Ltd.
Start Date:  18-09-2015      Intended Completion Date:  25-06-2017      Original End Date:  17-12-2016
Total Bond Cost: 74543585.76 (745.44 lakh)        Variation Cost: 18843460.57 (188.43 lakh)    Hence Total Bond Cost is   93387046.33 (933.87 lakh) 
Sub Project Cost: 171.33  lakh        Variation Cost of Sub Project: 534793.61  (5.35 lakh)       Total Sub Project Cost:   176.68 lakh
LD Analysis for Milestone1: calculated LD is Rs 2459952 for 66 days        LD Analysis for Milestone2: calculated LD is Rs 3689928 for 99 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence3.00 KM9.8105-10-201515-03-20173.00 KM3.00 KM6.949.81
2.R/Wall, B/ Wall Type Protection works847.00 m37.7815-10-201510-04-2017847.00 m847.00 m26.7237.78
3.G-21.00 KM5.3901-01-201715-04-20170.50 KM0.50 KM3.815.39
4.G-31.00 KM7.8012-01-201715-05-20170.70 KM0.70 KM5.527.80
5.PC/CC i/c Prime Coat, Tack Coat3.50 KM44.7501-10-201625-05-20173.50 KM3.50 KM31.6544.75
6.Culverts/Scupper 19.00 No18.3920-01-201615-03-201719.00 No19.00 No13.0118.39
7.longitudinal Drain3500.00 m15.8510-02-201612-05-20173500.00 m3500.00 m11.2115.85
8.Parapet0.00 No0.0002-07-201624-05-201750.00 No50.00 No00.00
9.Road Furniture150.00 No1.6203-09-201630-05-2017150.00 No150.00 No1.141.62
Total Amount: 141.39 100   141.39
Remarks: No Remarks       Work Program Made On: 25-09-2015        Updation of work program on: 24-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.25-January-20161.93  lakh
2.04-March-20162.78  lakh
3.31-March-201618.56  lakh
4.03-May-20168.93  lakh
5.30-June-201627.56  lakh
6.18-October-201611.63  lakh
7.26-October-201623.75  lakh
8.17-December-201616.24  lakh
9.23-March-201710.14  lakh
10.13-October-201731.19  lakh
11.27-November-20174.45  lakh
12.17-February-201818.47  lakh
13.13-September-20181.28  lakh
Total 176.91  lakh
% Payment100.13 %
Advance Amount:  25.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  25.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 300   No. of Test Done : 301    No. of Test Passed : 255   No. of Test Failed : 46   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 37
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-12-20162.525old.p.cSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
2.30-12-20162.525old p.cSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
3.14-12-20161.840p.c.work.chekingAjay Narayan PandeyREDSC1 R&B WB Chamoli See Pic
4.14-12-20162.340Checking measurement of pc workAjay Narayan PandeyREDSC1 R&B WB Chamoli See Pic
5.24-10-20162.250Laying of type c seal coatVikash SinghJEUDRP R&B Gopeshwar See Pic
6.24-10-20162.300Rolling of seal coatVikash SinghJEUDRP R&B Gopeshwar See Pic
7.10-10-20163.000Tempreture checking in seal coat materialVikash SinghJEUDRP R&B Gopeshwar See Pic
8.10-10-20163.025Rolling of type c seal coat at lolti kasbinagarVikash SinghJEUDRP R&B Gopeshwar See Pic
9.02-10-20163.575Rolling of type c seal coatVikash SinghJEUDRP R&B Gopeshwar See Pic
10.27-09-20163.400G3 Wbm in patch workVikash SinghJEUDRP R&B Gopeshwar See Pic
11.28-08-20161.900B/W Rejected due to quality of mortarAshwani KumarREDSC4 R&B WB Chamoli See Pic
12.18-07-20161520Lolti KashminagarManish VikalContractor Site EngineerUDRP R&B Chamoli See Pic
13.18-07-20161500Lolti KashminagarManish VikalContractor Site EngineerUDRP R&B Chamoli See Pic
14.04-06-20160.160p.c.peachSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
15.03-06-20160.110p.c.workSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
16.02-06-20161.360deran workSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
17.26-05-20160.720p.c.Sudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
18.18-05-20162570Pc PatchVikash SinghJEUDRP R&B Gopeshwar See Pic
19.05-04-20162500Dismentaling of scuper due to poor work menship in visit of E.E A.E R.E and contractor representativeVikash SinghJEUDRP R&B Gopeshwar See Pic
20.05-04-20161450Instruction given to contracter repersentive for cress barier steel by E.E sir at ch 1450Vikash SinghJEUDRP R&B Gopeshwar See Pic