Hapla Gudam Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1242 |
Sanction Cost: |
131.21 lakh |
Length:
|
1.500 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 59
Package Name: 
UDRP/PWD/02/03/RD/030b
Tender Date: 28-01-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/03/RD/030b
Contractor Name: R. B. Construction
|
Start Date: 14-07-2015
Intended Completion Date: 25-04-2017
Original End Date: 13-10-2016 |
Total Bond Cost: 31427309.65 (314.27 lakh)
Variation Cost: 371761.57 (3.72 lakh) Hence Total Bond Cost is 31799071.22 (317.99 lakh)
|
Sub Project Cost: 121.14 lakh
Variation Cost of Sub Project: -2318519.71 (-23.19 lakh)
Total Sub Project Cost:
97.95 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 722844 for 46 days
LD Analysis for Milestone2: calculated LD is Rs 5028480 for 320 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.50 KM | 2.78 | 05-01-2016 | 24-03-2017 | 1.50 KM | 1.50 KM | 2.46 | 2.78 | 2. | R/Wall, B/ Wall Type Protection works | 323.00 m | 16.49 | 11-01-2016 | 28-03-2017 | 323.00 m | 323.00 m | 14.61 | 16.49 | 3. | GSB/RBI/G-1 | 1.50 KM | 9.15 | 02-12-2016 | 20-04-2017 | 1.50 KM | 1.50 KM | 8.11 | 9.15 | 4. | G-2 | 1.50 KM | 13.51 | 08-01-2017 | 10-05-2017 | 1.50 KM | 1.50 KM | 11.97 | 13.51 | 5. | G-3 | 1.50 KM | 9.33 | 12-02-2017 | 25-05-2017 | 1.50 KM | 1.50 KM | 8.27 | 9.33 | 6. | PC/CC i/c Prime Coat, Tack Coat | 1.50 KM | 17.38 | 25-05-2017 | 15-06-2017 | 1.50 KM | 1.50 KM | 15.4 | 17.38 | 7. | Cause Way | 0.00 No | 0.00 | 30-05-2016 | 01-07-2016 | 0.00 No | 0.00 No | 0 | 0.00 | 8. | Culverts/Scupper | 7.00 No | 23.22 | 06-04-2016 | 20-04-2017 | 7.00 No | 7.00 No | 20.57 | 23.22 | 9. | longitudinal Drain | 1500.00 m | 9.95 | 01-11-2016 | 29-05-2017 | 1500.00 m | 1500.00 m | 8.82 | 9.95 | 10. | Crash Barrier | 0.00 m | 0.00 | 26-05-2017 | 15-06-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 50.00 No | 10.44 | 25-05-2017 | 11-06-2017 | 50.00 No | 50.00 No | 9.25 | 10.44 | 12. | Road Furniture | 26.00 No | 0.62 | 01-10-2016 | 11-06-2017 | 26.00 No | 26.00 No | 0.55 | 0.62 |
Total Amount: |
112.87 |
|
100 |
112.87 |
|
Remarks:
No Remarks
Work Program Made On:
11-08-2015 } ?>
Updation of work program on:
23-09-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 20-October-2015 | 31.72 lakh | 2. | 28-January-2016 | 14.59 lakh | 3. | 30-March-2016 | 6.39 lakh | 4. | 23-March-2017 | 19.00 lakh | 5. | 31-March-2017 | 0.67 lakh | 6. | 28-July-2017 | 39.05 lakh | 7. | 19-December-2017 | 22.86 lakh | 8. | 30-May-2018 | 18.56 lakh |
Total |
152.84 lakh |
% Payment | 156.04 % |
|
Advance Amount: 36.53 lakh
Recovered Amount: 6.53 lakh
Balance to be Recovered 30.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 127 No. of Test Done : 150 No. of Test Passed : 137 No. of Test Failed : 13 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.95 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 39 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-06-2017 | ch.1+325 | PC thickness checking found 22 mm | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
2. | 03-06-2017 | Ch. 1+375 | PC work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
3. | 26-05-2017 | 0+600 | Rectification of catch water drain | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
4. | 23-05-2017 | Ch.0+725 | G-1 Rolling work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
5. | 23-05-2017 | Ch. 0+700 | G-1 Laying work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
6. | 12-05-2017 | Ch. 1+350 | WBM G-3 Laying work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
7. | 12-05-2017 | Ch. 1+400 | WBM G-3 Layer | Abhishek Kumar | Site Supervisor | DSC4 R&B WB Chamoli | See Pic |
8. | 04-05-2017 | Ch.1+475 | WBM G-2 Laying work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
9. | 12-04-2017 | Ch.1.650 | Meeting with vilagers | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
10. | 08-03-2017 | Ch- 0.400 | Site visit | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
11. | 21-12-2016 | ch. 0+575 | scupper BBS. checking | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
12. | 13-12-2016 | Ch-1.075 | Scupper satring | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
13. | 21-10-2016 | Ch-1.350 | Stock for g2 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 06-09-2016 | Ch. 0+025 | Branded R/W | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
15. | 13-08-2016 | Ch-0.150 | Slip clearance | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 06-08-2016 | Ch-0.025 | Site visit | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
17. | 30-07-2016 | Chanage 0+550 | Site visit | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
18. | 30-07-2016 | Chanage 0+025 | Road open for traffic | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
19. | 27-07-2016 | Ch 0.575 | Condition of road in rainy season | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
20. | 25-07-2016 | Chanage 0+025 | Hapla Gudam motor marg | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
|
|