Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Hapla Gudam Motor Road Work Completed
Project: UDRP-RB UID: 1242 Sanction Cost: 131.21  lakh Length: 1.500 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 59        Package Name:  UDRP/PWD/02/03/RD/030b        Tender Date: 28-01-2015        Current Status: Agreement signed        Achieved on Date: 07-07-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/03/RD/030b      Contractor Name: R. B. Construction
Start Date:  14-07-2015      Intended Completion Date:  25-04-2017      Original End Date:  13-10-2016
Total Bond Cost: 31427309.65 (314.27 lakh)        Variation Cost: 371761.57 (3.72 lakh)    Hence Total Bond Cost is   31799071.22 (317.99 lakh) 
Sub Project Cost: 121.14  lakh        Variation Cost of Sub Project: -2318519.71  (-23.19 lakh)       Total Sub Project Cost:   97.95 lakh
LD Analysis for Milestone1: calculated LD is Rs 722844 for 46 days        LD Analysis for Milestone2: calculated LD is Rs 5028480 for 320 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.50 KM2.7805-01-201624-03-20171.50 KM1.50 KM2.462.78
2.R/Wall, B/ Wall Type Protection works323.00 m16.4911-01-201628-03-2017323.00 m323.00 m14.6116.49
3.GSB/RBI/G-11.50 KM9.1502-12-201620-04-20171.50 KM1.50 KM8.119.15
4.G-21.50 KM13.5108-01-201710-05-20171.50 KM1.50 KM11.9713.51
5.G-31.50 KM9.3312-02-201725-05-20171.50 KM1.50 KM8.279.33
6.PC/CC i/c Prime Coat, Tack Coat1.50 KM17.3825-05-201715-06-20171.50 KM1.50 KM15.417.38
7.Cause Way0.00 No0.0030-05-201601-07-20160.00 No0.00 No00.00
8.Culverts/Scupper 7.00 No23.2206-04-201620-04-20177.00 No7.00 No20.5723.22
9.longitudinal Drain1500.00 m9.9501-11-201629-05-20171500.00 m1500.00 m8.829.95
10.Crash Barrier0.00 m0.0026-05-201715-06-20170.00 m0.00 m00.00
11.Parapet50.00 No10.4425-05-201711-06-201750.00 No50.00 No9.2510.44
12.Road Furniture26.00 No0.6201-10-201611-06-201726.00 No26.00 No0.550.62
Total Amount: 112.87 100   112.87
Remarks: No Remarks       Work Program Made On: 11-08-2015        Updation of work program on: 23-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.20-October-201531.72  lakh
2.28-January-201614.59  lakh
3.30-March-20166.39  lakh
4.23-March-201719.00  lakh
5.31-March-20170.67  lakh
6.28-July-201739.05  lakh
7.19-December-201722.86  lakh
8.30-May-201818.56  lakh
Total 152.84  lakh
% Payment156.04 %
Advance Amount:  36.53  lakh        Recovered Amount:  6.53  lakh        Balance to be Recovered  30.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 127   No. of Test Done : 150    No. of Test Passed : 137   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.95
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 39
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-06-2017ch.1+325PC thickness checking found 22 mmSohanbir SinghJEUDRP R&B Chamoli See Pic
2.03-06-2017Ch. 1+375PC work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
3.26-05-20170+600Rectification of catch water drainAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
4.23-05-2017Ch.0+725G-1 Rolling work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
5.23-05-2017Ch. 0+700G-1 Laying work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
6.12-05-2017Ch. 1+350WBM G-3 Laying workSohanbir SinghJEUDRP R&B Chamoli See Pic
7.12-05-2017Ch. 1+400WBM G-3 LayerAbhishek KumarSite SupervisorDSC4 R&B WB Chamoli See Pic
8.04-05-2017Ch.1+475WBM G-2 Laying work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
9.12-04-2017Ch.1.650Meeting with vilagersManish RanaJEUDRP R&B Gopeshwar See Pic
10.08-03-2017Ch- 0.400Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
11.21-12-2016ch. 0+575scupper BBS. checkingSohanbir SinghJEUDRP R&B Chamoli See Pic
12.13-12-2016Ch-1.075Scupper satringPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
13.21-10-2016Ch-1.350Stock for g2Pramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
14.06-09-2016Ch. 0+025Branded R/WSohanbir SinghJEUDRP R&B Chamoli See Pic
15.13-08-2016Ch-0.150Slip clearancePramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.06-08-2016Ch-0.025Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.30-07-2016Chanage 0+550Site visitSohanbir SinghJEUDRP R&B Gopeshwar See Pic
18.30-07-2016Chanage 0+025Road open for trafficSohanbir SinghJEUDRP R&B Gopeshwar See Pic
19.27-07-2016Ch 0.575Condition of road in rainy seasonKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
20.25-07-2016Chanage 0+025Hapla Gudam motor margSohanbir SinghJEUDRP R&B Gopeshwar See Pic