Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Ghat Baanjbagar Telan Motor Road Work Completed
Project: UDRP-RB UID: 1239 Sanction Cost: 474.31  lakh Length: 7.800 KM.
District: Chamoli Block: Ghat Constituency: Tharali Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 100        Package Name:  UDRP/PWD/02/36/RD/089        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/089      Contractor Name: Surat Singh & Sons
Start Date:  11-06-2015      Intended Completion Date:  03-06-2017      Original End Date:  10-09-2016
Total Bond Cost: 38580821.75 (385.81 lakh)        Variation Cost: 4096845.07 (40.97 lakh)    Hence Total Bond Cost is   42677666.82 (426.78 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 752310 for 39 days        LD Analysis for Milestone2: calculated LD is Rs 1311720 for 68 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence7.80 KM1.6715-08-201510-03-20177.80 KM7.80 KM0.541.67
2.R/Wall, B/ Wall Type Protection works1110.00 m64.1408-07-201501-03-20171207.00 m1207.00 m20.6864.14
3.G-23.00 KM3.2302-10-201530-09-20163.00 KM3.00 KM1.043.23
4.G-35.00 KM38.2210-02-201625-03-20175.00 KM5.00 KM12.3238.22
5.PC/CC i/c Prime Coat, Tack Coat7.80 KM93.6801-05-201615-05-20177.80 KM7.80 KM30.293.68
6.Culverts/Scupper 25.00 No67.9701-08-201525-03-201725.00 No25.00 No21.9167.97
7.longitudinal Drain7500.00 m38.0006-01-201524-07-20167500.00 m7500.00 m12.2538.00
8.Parapet210.00 No1.0020-06-201605-05-2017300.00 No300.00 No0.321.00
9.Road Furniture125.00 No2.2901-07-201625-05-2017125.00 No125.00 No0.742.29
Total Amount: 310.2 100   310.2
Remarks: No Remarks       Work Program Made On: 13-07-2015        Updation of work program on: 24-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.31-October-201531.71  lakh
2.30-November-201528.82  lakh
3.26-December-201522.80  lakh
4.29-February-201639.84  lakh
5.02-May-201642.55  lakh
6.30-June-201633.86  lakh
7.14-July-201640.64  lakh
8.17-December-201620.95  lakh
9.30-December-201618.29  lakh
10.31-March-201724.98  lakh
11.01-June-201744.98  lakh
12.12-October-201711.94  lakh
13.27-November-201724.19  lakh
14.28-February-201839.93  lakh
Total 425.48  lakh
% Payment 99.7 %
Advance Amount:  34.82  lakh        Recovered Amount:  34.82  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 172   No. of Test Done : 200    No. of Test Passed : 167   No. of Test Failed : 33   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.12
Number of Notice(s) issued: 95

Mobile Pic Upload

Number of Pics Available on Web Repository: 189
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.02-07-20170.135Inter locking work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.08-03-2017Ch-2.525Site visitPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
3.08-03-2017Ch- 2.580Thickness checking for pcPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
4.08-03-2017Ch-3.400Drain ExcavationPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
5.05-03-20173.200Site Visit by C.E. Sir ,S.E. Sir & E.E. SirMuhammad Munazir AnsariJEUDRP R&B Chamoli See Pic
6.02-02-2017Ch-5.825K.C. drain c typePramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
7.02-02-2017Ch-3.100R/W RR.DryPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
8.12-11-2016Ch-5.300Seal coat RectifyPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
9.25-10-2016Chainage-5.850kmPc laying workManish RanaJEUDRP R&B Gopeshwar See Pic
10.25-10-2016Chainage-5.860kmTack coat laying workManish RanaJEUDRP R&B Gopeshwar See Pic
11.25-10-2016Chainage-5.865kmPc laying workManish RanaJEUDRP R&B Gopeshwar See Pic
12.25-10-2016Chainage-5.825KmPc rolling workManish RanaJEUDRP R&B Gopeshwar See Pic
13.25-10-2016Chainage-5.900kmSeal coat rolling workManish RanaJEUDRP R&B Gopeshwar See Pic
14.19-10-2016Chainage-5.320kmParapet construction workManish RanaJEUDRP R&B Gopeshwar See Pic
15.18-10-20165.650Seal coat work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
16.18-10-20165.650Bitumen content testAshwani KumarREDSC4 R&B WB Chamoli See Pic
17.17-10-2016Chainage-4.320Seal coat bitumen extractionManish RanaJEUDRP R&B Gopeshwar See Pic
18.17-10-2016Chainage.4.320Temperature of seal coatManish RanaJEUDRP R&B Gopeshwar See Pic
19.17-10-2016Chainage4.300Seal coat rolling workManish RanaJEUDRP R&B Gopeshwar See Pic
20.17-10-2016Ch.4.040kmSeal coat rolling workManish RanaJEUDRP R&B Gopeshwar See Pic