Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Gauchar Shail Dua MR Work Completed
Project: UDRP-RB UID: 1238 Sanction Cost: 889.84  lakh Length: 10.000 KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 119        Package Name:  UDRP/PWD/02/38/RD/108        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/108      Contractor Name: Sharda Associates
Start Date:  09-12-2015      Intended Completion Date:  31-12-2017      Original End Date:  08-03-2017
Total Bond Cost: 67153711.16 (671.54 lakh)        Variation Cost: 20538013.00 (205.38 lakh)    Hence Total Bond Cost is   87691724.16 (876.92 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: calculated LD is Rs 2048197 for 61 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence10.00 KM62.3121-12-201520-11-201710.00 KM10.00 KM8.4362.31
2.R/Wall, B/ Wall Type Protection works1430.00 m158.1911-01-201615-12-20171480.00 m1480.00 m21.41158.19
3.GSB/RBI/G-110.00 KM82.2515-03-201626-11-201610.00 KM10.00 KM11.1482.25
4.G-210.00 KM59.8025-03-201609-01-201710.00 KM10.00 KM8.159.80
5.G-310.00 KM82.4422-08-201605-10-201610.00 KM10.00 KM11.1682.44
6.PC/CC i/c Prime Coat, Tack Coat10.00 KM117.6515-03-201701-05-201710.00 KM10.00 KM15.93117.65
7.Cause Way3.00 No6.8201-12-201618-09-20171.00 No1.00 No0.926.82
8.Culverts/Scupper 23.00 No85.8208-02-201615-12-201622.00 No22.00 No11.6285.82
9.longitudinal Drain10000.00 m41.2723-03-201623-04-201710000.00 m10000.00 m5.5941.27
10.Crash Barrier950.00 m25.5212-12-201612-01-2017950.00 m950.00 m3.4525.52
11.Parapet400.00 No12.1721-11-201620-09-2017400.00 No400.00 No1.6512.17
12.Road Furniture153.00 No4.4806-12-201615-12-2017153.00 No153.00 No0.614.48
Total Amount: 738.72 100   738.72
Remarks: No Remarks       Work Program Made On: 23-12-2015        Updation of work program on: 23-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.23-January-201651.69  lakh
2.29-February-201642.66  lakh
3.30-April-201667.33  lakh
4.30-June-201644.80  lakh
5.30-August-201635.78  lakh
6.30-September-201647.75  lakh
7.08-December-201645.89  lakh
8.03-February-201765.46  lakh
9.28-February-201729.03  lakh
10.22-March-201758.86  lakh
11.31-March-201729.46  lakh
12.25-May-201798.29  lakh
13.14-July-201740.35  lakh
14.13-October-2017106.21  lakh
15.19-December-201778.37  lakh
16.30-May-201820.98  lakh
17.12-September-201814.03  lakh
Total 876.94  lakh
% Payment 99.99 %
Advance Amount:  147.71  lakh        Recovered Amount:  127.81  lakh        Balance to be Recovered  19.90  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 155   No. of Test Done : 171    No. of Test Passed : 151   No. of Test Failed : 20   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.45
Number of Notice(s) issued: 73

Mobile Pic Upload

Number of Pics Available on Web Repository: 182
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.20-11-20170.840Consultation with local people Mr pulsar Lal and hagfish lalAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.20-11-20170.870Checking slope of Retaining wall found 1:3Ashwani KumarREDSC4 R&B WB Chamoli See Pic
3.20-11-20170.470Work of Retaining wall in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.23-07-2017Ch. 7+050Road damage due to heavy RainSohanbir SinghJEUDRP R&B Chamoli See Pic
5.23-07-2017Ch.0+880Consultation with local peopleSohanbir SinghJEUDRP R&B Chamoli See Pic
6.22-07-2017Ch. 6+450Slip clearanceSohanbir SinghJEUDRP R&B Chamoli See Pic
7.22-07-2017Ch.0+390Old R/W damage due to Heavy RainSohanbir SinghJEUDRP R&B Chamoli See Pic
8.14-04-2017LabAIV test of G3 material found 24percentKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
9.14-04-2017Checking 8.060Thicknesses checking of pc by EE sir found 20mmKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
10.14-04-2017Ch 8.040Laying of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
11.14-04-2017Ch 8.040Rolling of seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
12.25-03-2017Ch 9.150Bitumen extraction testKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
13.25-03-2017Ch9.190Thickness checking of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
14.25-03-2017Ch 9.190Seal coat layingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
15.25-03-2017Ch 6.950Plum wall for hp band protectionKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
16.25-03-2017Ch 1.650Top of wall in1:5 cement mortarKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
17.25-03-2017Ch 1.650Checking of road widthKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
18.27-01-2017Ch 0 160Checking of G2 by chief sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
19.27-01-2017Ch 0.440Checking of slope of Rwall by EE sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
20.22-12-20161.050WC work in progressPankaj Singh RawatSite SupervisorDSC1 R&B WB Chamoli See Pic