Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Batadhar Dhunarghat Motor Road Work Completed
Project: UDRP-RB UID: 1228 Sanction Cost: 899.53  lakh Length: 20.000 KM.
District: Chamoli Block: Gairsain Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Karanprayag DSC: Sheladia Associates DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 128        Package Name:  UDRP/PWD/09/01/RD/025/New        Tender Date: 05-11-2015        Current Status: Agreement signed        Achieved on Date: 29-02-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/01/RD/025/New      Contractor Name: B. M. Construction Co.
Start Date:  07-03-2016      Intended Completion Date:  15-08-2018      Original End Date:  06-06-2017
Total Bond Cost: 65082970.36 (650.83 lakh)        Variation Cost: 19775795.63 (197.76 lakh)    Hence Total Bond Cost is   84858765.99 (848.59 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence7.00 KM89.8820-03-201715-04-20187.00 KM7.00 KM9.9989.88
2.R/Wall, B/ Wall Type Protection works400.00 m29.6801-05-201731-07-2018400.00 m400.00 m3.329.68
3.GSB/RBI/G-110.50 KM70.2601-03-201710-04-201810.50 KM10.50 KM7.8170.26
4.G-215.00 KM78.8315-03-201715-04-201815.00 KM15.00 KM8.7678.83
5.G-319.30 KM99.7830-03-201710-05-201819.30 KM19.30 KM11.0999.78
6.PC/CC i/c Prime Coat, Tack Coat19.30 KM215.4701-04-201730-06-201819.30 KM19.30 KM23.94215.47
7.Cause Way14.00 No78.0001-03-201831-03-201814.00 No14.00 No8.6778.00
8.Culverts/Scupper 60.00 No176.9101-03-201725-04-201860.00 No60.00 No19.66176.91
9.longitudinal Drain19300.00 m22.6101-03-201710-08-201819300.00 m19300.00 m2.5122.61
10.Parapet200.00 No28.6201-01-201815-08-2018200.00 No200.00 No3.1828.62
11.Road Furniture102.00 No2.5201-01-201815-08-2018102.00 No102.00 No0.282.52
12.Env. Man & Moni Plan1.00 Job7.3501-08-201815-08-20181.00 Job1.00 Job0.827.35
Total Amount: 899.91 100   899.91
Remarks: No Remarks       Work Program Made On: 22-07-2016        Updation of work program on: 02-08-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201412.09  lakh
2.23-January-201521.28  lakh
3.03-March-201542.20  lakh
4.27-March-20154.60  lakh
5.05-May-201522.46  lakh
6.12-June-201550.42  lakh
7.29-February-2016166.91  lakh
Previous Package Expenditure Total 319.96  lakh
SNo. Date Payment
1.12-January-20177.00  lakh
2.07-March-201721.85  lakh
3.25-May-201724.17  lakh
4.13-October-201771.43  lakh
5.25-November-201759.77  lakh
6.04-January-201843.70  lakh
7.31-January-201883.84  lakh
8.28-February-201838.03  lakh
9.27-March-2018101.92  lakh
10.24-April-2018103.01  lakh
11.31-May-2018100.92  lakh
12.25-July-201853.01  lakh
13.07-September-201881.92  lakh
14.16-October-201837.64  lakh
15.28-November-201820.27  lakh
16.27-December-201841.13  lakh
17.27-February-201910.29  lakh
Total 899.9  lakh
% Payment 106.04 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 742   No. of Test Done : 835    No. of Test Passed : 823   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 95.00
Number of Notice(s) issued: 70

Mobile Pic Upload

Number of Pics Available on Web Repository: 137
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-10-2018Ch 4.150Crash barrier pkg 25 new as per guidline world bank team visit 29.5.2018Gaurav BhardwajJEUDRP R&B Karnprayag See Pic
2.18-08-2018Ch. 7.600Myck disposal pkg 25 newGaurav BhardwajJEUDRP R&B Karnprayag See Pic
3.11-07-2018Ch. 18.800Seal coat repair pkg 25newGaurav BhardwajJEUDRP R&B Karnprayag See Pic
4.21-06-2018Ch. 15.300Chief sir pc thickness checkingGaurav BhardwajJEUDRP R&B Karnprayag See Pic
5.21-06-2018Ch. 8.010Chief sir visit pkg 25 newGaurav BhardwajJEUDRP R&B Karnprayag See Pic
6.19-06-2018Ch. 17.675 mathkotPlum concrete protectionGaurav BhardwajJEUDRP R&B Karnprayag See Pic
7.19-06-2018Ch. 16.800Wire crates in progress ch.16.800Gaurav BhardwajJEUDRP R&B Karnprayag See Pic
8.23-12-2017Start pointInspection of road with DSC.Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
9.22-12-2017End pointKm 17Lalit Mohan BenjwalAEUDRP R&B Karnprayag See Pic
10.20-07-2017At Ch 1+450Site visit with Gopeshwar division JE and AE for taken over work for DEA KaranprayagRajan NautiyalJEUDRP R&B Chakrata See Pic
11.06-06-20170.010OGPC work in progress quality of work is SatisfactoryAshwani KumarREDSC4 R&B WB Chamoli See Pic
12.12-04-2017At site laboratoryG3 gradation testManish RanaJEUDRP R&B Gopeshwar See Pic
13.12-04-2017At laboratoryG2 gradation testManish RanaJEUDRP R&B Gopeshwar See Pic
14.12-04-20174/5G2 gradation testManish RanaJEUDRP R&B Gopeshwar See Pic
15.12-01-20170.015Wing wall work in progressAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
16.20-09-201517.950R.R dry wallAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
17.25-08-20151+075Drain workAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
18.04-08-2015Site labLabSudhir KumarSite EngineerDSC1 R&B WB Chamoli See Pic
19.29-06-201511+400G1 layingMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
20.23-06-201510.700Spreading of G1Alok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic