Batadhar Dhunarghat Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1228 |
Sanction Cost: |
899.53 lakh |
Length:
|
20.000 KM. |
District: |
Chamoli |
Block: |
Gairsain |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Sheladia Associates |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 128
Package Name: 
UDRP/PWD/09/01/RD/025/New
Tender Date: 05-11-2015
Current Status: Agreement signed
Achieved on Date: 29-02-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/01/RD/025/New
Contractor Name: B. M. Construction Co.
|
Start Date: 07-03-2016
Intended Completion Date: 15-08-2018
Original End Date: 06-06-2017 |
Total Bond Cost: 65082970.36 (650.83 lakh)
Variation Cost: 19775795.63 (197.76 lakh) Hence Total Bond Cost is 84858765.99 (848.59 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 7.00 KM | 89.88 | 20-03-2017 | 15-04-2018 | 7.00 KM | 7.00 KM | 9.99 | 89.88 | 2. | R/Wall, B/ Wall Type Protection works | 400.00 m | 29.68 | 01-05-2017 | 31-07-2018 | 400.00 m | 400.00 m | 3.3 | 29.68 | 3. | GSB/RBI/G-1 | 10.50 KM | 70.26 | 01-03-2017 | 10-04-2018 | 10.50 KM | 10.50 KM | 7.81 | 70.26 | 4. | G-2 | 15.00 KM | 78.83 | 15-03-2017 | 15-04-2018 | 15.00 KM | 15.00 KM | 8.76 | 78.83 | 5. | G-3 | 19.30 KM | 99.78 | 30-03-2017 | 10-05-2018 | 19.30 KM | 19.30 KM | 11.09 | 99.78 | 6. | PC/CC i/c Prime Coat, Tack Coat | 19.30 KM | 215.47 | 01-04-2017 | 30-06-2018 | 19.30 KM | 19.30 KM | 23.94 | 215.47 | 7. | Cause Way | 14.00 No | 78.00 | 01-03-2018 | 31-03-2018 | 14.00 No | 14.00 No | 8.67 | 78.00 | 8. | Culverts/Scupper | 60.00 No | 176.91 | 01-03-2017 | 25-04-2018 | 60.00 No | 60.00 No | 19.66 | 176.91 | 9. | longitudinal Drain | 19300.00 m | 22.61 | 01-03-2017 | 10-08-2018 | 19300.00 m | 19300.00 m | 2.51 | 22.61 | 10. | Parapet | 200.00 No | 28.62 | 01-01-2018 | 15-08-2018 | 200.00 No | 200.00 No | 3.18 | 28.62 | 11. | Road Furniture | 102.00 No | 2.52 | 01-01-2018 | 15-08-2018 | 102.00 No | 102.00 No | 0.28 | 2.52 | 12. | Env. Man & Moni Plan | 1.00 Job | 7.35 | 01-08-2018 | 15-08-2018 | 1.00 Job | 1.00 Job | 0.82 | 7.35 |
Total Amount: |
899.91 |
|
100 |
899.91 |
|
Remarks:
No Remarks
Work Program Made On:
22-07-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2014 | 12.09 lakh | 2. | 23-January-2015 | 21.28 lakh | 3. | 03-March-2015 | 42.20 lakh | 4. | 27-March-2015 | 4.60 lakh | 5. | 05-May-2015 | 22.46 lakh | 6. | 12-June-2015 | 50.42 lakh | 7. | 29-February-2016 | 166.91 lakh |
Previous Package Expenditure Total |
319.96 lakh |
SNo. |
Date |
Payment |
1. | 12-January-2017 | 7.00 lakh | 2. | 07-March-2017 | 21.85 lakh | 3. | 25-May-2017 | 24.17 lakh | 4. | 13-October-2017 | 71.43 lakh | 5. | 25-November-2017 | 59.77 lakh | 6. | 04-January-2018 | 43.70 lakh | 7. | 31-January-2018 | 83.84 lakh | 8. | 28-February-2018 | 38.03 lakh | 9. | 27-March-2018 | 101.92 lakh | 10. | 24-April-2018 | 103.01 lakh | 11. | 31-May-2018 | 100.92 lakh | 12. | 25-July-2018 | 53.01 lakh | 13. | 07-September-2018 | 81.92 lakh | 14. | 16-October-2018 | 37.64 lakh | 15. | 28-November-2018 | 20.27 lakh | 16. | 27-December-2018 | 41.13 lakh | 17. | 27-February-2019 | 10.29 lakh |
Total |
899.9 lakh |
% Payment |
106.04 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 742 No. of Test Done : 835 No. of Test Passed : 823 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 95.00 |
Number of Notice(s) issued: 70 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 137 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-10-2018 | Ch 4.150 | Crash barrier pkg 25 new as per guidline world bank team visit 29.5.2018 | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
2. | 18-08-2018 | Ch. 7.600 | Myck disposal pkg 25 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
3. | 11-07-2018 | Ch. 18.800 | Seal coat repair pkg 25new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
4. | 21-06-2018 | Ch. 15.300 | Chief sir pc thickness checking | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
5. | 21-06-2018 | Ch. 8.010 | Chief sir visit pkg 25 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
6. | 19-06-2018 | Ch. 17.675 mathkot | Plum concrete protection | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
7. | 19-06-2018 | Ch. 16.800 | Wire crates in progress ch.16.800 | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
8. | 23-12-2017 | Start point | Inspection of road with DSC. | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
9. | 22-12-2017 | End point | Km 17 | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 20-07-2017 | At Ch 1+450 | Site visit with Gopeshwar division JE and AE for taken over work for DEA Karanprayag | Rajan Nautiyal | JE | UDRP R&B Chakrata | See Pic |
11. | 06-06-2017 | 0.010 | OGPC work in progress quality of work is Satisfactory | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
12. | 12-04-2017 | At site laboratory | G3 gradation test | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
13. | 12-04-2017 | At laboratory | G2 gradation test | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
14. | 12-04-2017 | 4/5 | G2 gradation test | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
15. | 12-01-2017 | 0.015 | Wing wall work in progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
16. | 20-09-2015 | 17.950 | R.R dry wall | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
17. | 25-08-2015 | 1+075 | Drain work | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
18. | 04-08-2015 | Site lab | Lab | Sudhir Kumar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
19. | 29-06-2015 | 11+400 | G1 laying | Mukesh Kumar Yadav | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
20. | 23-06-2015 | 10.700 | Spreading of G1 | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
|
|