Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bamnath - Nail - Sankri MR Work Completed
Project: UDRP-RB UID: 1226 Sanction Cost: 178.75  lakh Length: 2.350 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 88        Package Name:  UDRP/PWD/02/08/RD/077        Tender Date: 04-07-2015        Current Status: Agreement signed        Achieved on Date: 23-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/08/RD/077      Contractor Name: Dream Real Infra
Start Date:  30-12-2015      Intended Completion Date:  31-10-2018      Original End Date:  29-03-2017
Total Bond Cost: 55686855.62 (556.87 lakh)        Variation Cost: -905472.35 (-9.05 lakh)    Hence Total Bond Cost is   54781383.27 (547.81 lakh) 
Sub Project Cost: 148.93  lakh        Variation Cost of Sub Project: -10132264.74  (-101.32 lakh)       Total Sub Project Cost:   47.61 lakh
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days        LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.00 KM0.0008-09-201620-03-20170.90 KM0.90 KM00.00
2.R/Wall, B/ Wall Type Protection works450.00 m59.6010-02-201615-03-2017450.00 m450.00 m40.1359.60
3.G-20.50 KM5.3720-09-201610-03-20170.50 KM0.50 KM3.625.37
4.G-30.95 KM9.8415-10-201625-03-20170.95 KM0.95 KM6.639.84
5.PC/CC i/c Prime Coat, Tack Coat0.95 KM27.6501-04-201715-11-20170.95 KM0.95 KM18.6227.65
6.Culverts/Scupper 3.00 No34.6202-09-201631-05-20173.00 No3.00 No23.3134.62
7.longitudinal Drain950.00 m10.2910-09-201615-06-2017950.00 m950.00 m6.9310.29
8.Parapet20.00 No0.0025-05-201720-01-201820.00 No20.00 No00.00
9.Road Furniture46.00 No1.1425-05-201721-03-201846.00 No46.00 No0.771.14
Total Amount: 148.51 100   148.51
Remarks: No Remarks       Work Program Made On: 06-02-2016        Updation of work program on: 21-03-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.30-June-20166.02  lakh
2.09-September-20163.76  lakh
3.27-October-20161.99  lakh
4.12-January-20172.61  lakh
5.24-March-20173.30  lakh
6.30-November-201714.66  lakh
7.06-June-20188.31  lakh
8.20-February-20191.73  lakh
Total 42.38  lakh
% Payment89.01 %
Advance Amount:  79.00  lakh        Recovered Amount:  86.50  lakh        Balance to be Recovered  -7.50  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 276   No. of Test Done : 255    No. of Test Passed : 243   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.02
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 25
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.29-11-20170.775OGPC Work completeAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.20-06-20170.200OGPC work rejected due to not proper clearing and undulationAshwani KumarREDSC4 R&B WB Chamoli See Pic
3.23-05-2017Ch.0+875G-3 Laying work completedSohanbir SinghJEUDRP R&B Chamoli See Pic
4.25-03-2017Chainage 0+320G-3 stackingSohanbir SinghJEUDRP R&B Chamoli See Pic
5.23-09-2016Ch 0.100Abutment of scupperKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
6.21-09-20160.100Scupper abutment work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
7.16-09-2016At 0.120Breast wallManish RathiJEUDRP R&B Gopeshwar See Pic
8.16-09-2016At 0.610Site visitManish RathiJEUDRP R&B Gopeshwar See Pic
9.25-06-2016Ch- 0.350B/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
10.17-06-2016Chanage 0+875RR Dry Retaining wallsSohanbir SinghJEUDRP R&B Gopeshwar See Pic
11.17-06-2016Chanage 0+850Dry Retaining wallSohanbir SinghJEUDRP R&B Gopeshwar See Pic
12.06-04-2016Ch-0.375B/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
13.29-03-2016Chanage 0+375Breast wallSohanbir SinghJEUDRP R&B Gopeshwar See Pic
14.29-03-2016Chanage 0+400Breast wallSohanbir SinghJEUDRP R&B Gopeshwar See Pic
15.04-03-2016Ch-0.825R/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
16.03-03-2016Chanage 0+800Construction of dry Retaining wallSohanbir SinghJEUDRP R&B Gopeshwar See Pic
17.03-03-2016Chanage 0+825Dry Retaining wallSohanbir SinghJEUDRP R&B Gopeshwar See Pic
18.03-03-2016Chanage 0+825Retaining wall CurringSohanbir SinghJEUDRP R&B Gopeshwar See Pic
19.29-02-2016Chanage 0+850Dry Retaining wallSohanbir SinghJEUDRP R&B Gopeshwar See Pic
20.17-02-2016Ch-0.600B/wPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic