Bamnath - Nail - Sankri MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1226 |
Sanction Cost: |
178.75 lakh |
Length:
|
2.350 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 88
Package Name: 
UDRP/PWD/02/08/RD/077
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 23-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/077
Contractor Name: Dream Real Infra
|
Start Date: 30-12-2015
Intended Completion Date: 31-10-2018
Original End Date: 29-03-2017 |
Total Bond Cost: 55686855.62 (556.87 lakh)
Variation Cost: -905472.35 (-9.05 lakh) Hence Total Bond Cost is 54781383.27 (547.81 lakh)
|
Sub Project Cost: 148.93 lakh
Variation Cost of Sub Project: -10132264.74 (-101.32 lakh)
Total Sub Project Cost:
47.61 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.00 KM | 0.00 | 08-09-2016 | 20-03-2017 | 0.90 KM | 0.90 KM | 0 | 0.00 | 2. | R/Wall, B/ Wall Type Protection works | 450.00 m | 59.60 | 10-02-2016 | 15-03-2017 | 450.00 m | 450.00 m | 40.13 | 59.60 | 3. | G-2 | 0.50 KM | 5.37 | 20-09-2016 | 10-03-2017 | 0.50 KM | 0.50 KM | 3.62 | 5.37 | 4. | G-3 | 0.95 KM | 9.84 | 15-10-2016 | 25-03-2017 | 0.95 KM | 0.95 KM | 6.63 | 9.84 | 5. | PC/CC i/c Prime Coat, Tack Coat | 0.95 KM | 27.65 | 01-04-2017 | 15-11-2017 | 0.95 KM | 0.95 KM | 18.62 | 27.65 | 6. | Culverts/Scupper | 3.00 No | 34.62 | 02-09-2016 | 31-05-2017 | 3.00 No | 3.00 No | 23.31 | 34.62 | 7. | longitudinal Drain | 950.00 m | 10.29 | 10-09-2016 | 15-06-2017 | 950.00 m | 950.00 m | 6.93 | 10.29 | 8. | Parapet | 20.00 No | 0.00 | 25-05-2017 | 20-01-2018 | 20.00 No | 20.00 No | 0 | 0.00 | 9. | Road Furniture | 46.00 No | 1.14 | 25-05-2017 | 21-03-2018 | 46.00 No | 46.00 No | 0.77 | 1.14 |
Total Amount: |
148.51 |
|
100 |
148.51 |
|
Remarks:
No Remarks
Work Program Made On:
06-02-2016 } ?>
Updation of work program on:
21-03-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-June-2016 | 6.02 lakh | 2. | 09-September-2016 | 3.76 lakh | 3. | 27-October-2016 | 1.99 lakh | 4. | 12-January-2017 | 2.61 lakh | 5. | 24-March-2017 | 3.30 lakh | 6. | 30-November-2017 | 14.66 lakh | 7. | 06-June-2018 | 8.31 lakh | 8. | 20-February-2019 | 1.73 lakh |
Total |
42.38 lakh |
% Payment | 89.01 % |
|
Advance Amount: 79.00 lakh
Recovered Amount: 86.50 lakh
Balance to be Recovered -7.50 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 276 No. of Test Done : 255 No. of Test Passed : 243 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.02 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 25 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-11-2017 | 0.775 | OGPC Work complete | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 20-06-2017 | 0.200 | OGPC work rejected due to not proper clearing and undulation | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
3. | 23-05-2017 | Ch.0+875 | G-3 Laying work completed | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
4. | 25-03-2017 | Chainage 0+320 | G-3 stacking | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
5. | 23-09-2016 | Ch 0.100 | Abutment of scupper | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
6. | 21-09-2016 | 0.100 | Scupper abutment work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
7. | 16-09-2016 | At 0.120 | Breast wall | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
8. | 16-09-2016 | At 0.610 | Site visit | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
9. | 25-06-2016 | Ch- 0.350 | B/w | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
10. | 17-06-2016 | Chanage 0+875 | RR Dry Retaining walls | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
11. | 17-06-2016 | Chanage 0+850 | Dry Retaining wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
12. | 06-04-2016 | Ch-0.375 | B/w | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
13. | 29-03-2016 | Chanage 0+375 | Breast wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
14. | 29-03-2016 | Chanage 0+400 | Breast wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
15. | 04-03-2016 | Ch-0.825 | R/w | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 03-03-2016 | Chanage 0+800 | Construction of dry Retaining wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
17. | 03-03-2016 | Chanage 0+825 | Dry Retaining wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
18. | 03-03-2016 | Chanage 0+825 | Retaining wall Curring | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
19. | 29-02-2016 | Chanage 0+850 | Dry Retaining wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 17-02-2016 | Ch-0.600 | B/w | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|