Project: UDRP-RB UID: 1225 Sanction Cost: 622.60  lakh Length: 11.200 KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 94        Package Name:  UDRP/PWD/02/36/RD/083        Tender Date: 18-02-2015        Current Status: Agreement signed        Achieved on Date: 04-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/083      Contractor Name: Universal Associates
Start Date:  11-06-2015      Intended Completion Date:  08-11-2016      Original End Date:  10-09-2016
Total Bond Cost: 55011028.02 (550.11 lakh)        Variation Cost: 7233682.16 (72.34 lakh)    Hence Total Bond Cost is   62244710.18 (622.45 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence11.20 KM31.4720-06-201520-11-201611.20 KM11.20 KM6.9231.47
2.R/Wall, B/ Wall Type Protection works2575.00 m120.0801-07-201520-11-20162575.00 m2575.00 m26.4120.08
3.G-20.30 KM3.2113-10-201520-11-20160.30 KM0.30 KM0.713.21
4.G-32.45 KM18.2301-12-201520-11-20162.45 KM2.45 KM4.0118.23
5.PC/CC i/c Prime Coat, Tack Coat11.20 KM124.1001-03-201620-11-201611.20 KM11.20 KM27.29124.10
6.Cause Way7.00 No21.5001-10-201520-11-20167.00 No7.00 No4.7321.50
7.Culverts/Scupper 32.00 No72.0401-08-201520-11-201632.00 No32.00 No15.8472.04
8.longitudinal Drain10510.00 m48.2210-09-201520-11-201610510.00 m10510.00 m10.648.22
9.Crash Barrier0.00 m0.0002-02-201620-11-20160.00 m0.00 m00.00
10.Parapet500.00 No13.2713-01-201620-11-2016500.00 No500.00 No2.9213.27
11.Road Furniture249.00 No2.6601-01-201620-11-2016249.00 No249.00 No0.582.66
Total Amount: 454.78 100   454.78
Remarks: No Remarks       Work Program Made On: 13-07-2015        Updation of work program on: 06-06-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.24-September-201552.71  lakh
2.30-October-201575.34  lakh
3.30-January-201686.93  lakh
4.29-February-201645.02  lakh
5.28-March-201626.84  lakh
6.02-May-201682.83  lakh
7.29-June-201624.53  lakh
8.30-June-201651.44  lakh
9.31-August-201627.27  lakh
10.18-October-201644.48  lakh
11.26-October-201656.84  lakh
12.31-March-201748.20  lakh
Total 622.43  lakh
% Payment 99.99 %
Advance Amount:  132.83  lakh        Recovered Amount:  132.83  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 371   No. of Test Done : 399    No. of Test Passed : 364   No. of Test Failed : 35   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.47
Number of Notice(s) issued: 74

Mobile Pic Upload

Number of Pics Available on Web Repository: 289
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-01-2017Ch 8.585Measurement checking by EE sirKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
2.27-01-2017Ch 9.900Sign boardKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.12-01-20170.015Scupper abutment work in progressAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
4.12-01-20170.015Rejected scupper abutmentAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
5.30-11-20166.025Delinator and edge stone fixedAshwani KumarREDSC4 R&B WB Chamoli See Pic
6.25-11-2016Ch 0.100Path way for movement of villagers connection road to griddle pathKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
7.25-11-2016Ch 7.330Patch workKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
8.17-11-20164+420Painting on parapetMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
9.17-11-20160+100Parapet white wash completeMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
10.16-11-20163+825Extension joint seeling of causewayAjay Narayan PandeyREDSC1 R&B WB Chamoli See Pic
11.16-11-20160+119Parapete penting.Ajay Narayan PandeyREDSC1 R&B WB Chamoli See Pic
12.27-10-20168+300Protection work at sinckage area..check by E.E sirMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
13.27-10-20164+225Thickness checking by E.E sirMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
14.27-10-20160+050Seal coat work and E.E sahab site visitMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
15.26-10-2016Ch 2.950Temperature checking of seal coatKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
16.26-10-2016Ch 2.950Thickness checking of pcKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
17.23-10-20164+200Rolling after seal coat workMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
18.23-10-20164+050P. M. C work progressMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
19.21-10-20163+900Tack coatMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic
20.21-10-20163+900PMC work progressMukesh Kumar YadavSite SupervisorDSC1 R&B WB Chamoli See Pic