Aagerchatti Jingod Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1222 |
Sanction Cost: |
629.57 lakh |
Length:
|
7.000 KM. |
District: |
Chamoli |
Block: |
Gairsain |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 117
Package Name: 
UDRP/PWD/02/36/RD/106
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 06-08-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/106
Contractor Name: Singla Construction Limited
|
Start Date: 13-08-2015
Intended Completion Date: 14-05-2017
Original End Date: 12-11-2016 |
Total Bond Cost: 103206509.48 (1032.07 lakh)
Variation Cost: 13196287.93 (131.96 lakh) Hence Total Bond Cost is 116402797.41 (1164.03 lakh)
|
Sub Project Cost: 584.30 lakh
Variation Cost of Sub Project: -2463265.03 (-24.63 lakh)
Total Sub Project Cost:
559.67 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2941371 for 57 days
LD Analysis for Milestone2: calculated LD is Rs 4025034 for 78 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 7.00 KM | 22.54 | 02-09-2015 | 12-02-2017 | 7.00 KM | 7.00 KM | 5.22 | 22.54 | 2. | R/Wall, B/ Wall Type Protection works | 2184.00 m | 193.63 | 15-09-2015 | 25-02-2017 | 2184.00 m | 2184.00 m | 44.88 | 193.63 | 3. | G-2 | 14.00 KM | 74.86 | 15-01-2016 | 25-02-2017 | 14.00 KM | 14.00 KM | 17.35 | 74.86 | 4. | G-3 | 7.00 KM | 49.93 | 15-02-2016 | 08-03-2017 | 7.00 KM | 7.00 KM | 11.57 | 49.93 | 5. | PC/CC i/c Prime Coat, Tack Coat | 7.00 KM | 31.64 | 04-04-2016 | 25-04-2017 | 7.00 KM | 7.00 KM | 7.33 | 31.64 | 6. | Cause Way | 4.00 No | 5.81 | 09-05-2016 | 01-03-2017 | 4.00 No | 4.00 No | 1.35 | 5.81 | 7. | Culverts/Scupper | 38.00 No | 32.03 | 20-10-2015 | 10-02-2017 | 38.00 No | 38.00 No | 7.42 | 32.03 | 8. | longitudinal Drain | 7000.00 m | 6.58 | 18-02-2016 | 30-05-2017 | 7000.00 m | 7000.00 m | 1.52 | 6.58 | 9. | Crash Barrier | 0.00 m | 0.00 | 09-12-2016 | 30-05-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 10. | Parapet | 0.00 No | 0.00 | 01-04-2017 | 30-05-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 11. | Road Furniture | 59.00 No | 14.46 | 25-09-2016 | 30-05-2017 | 59.00 No | 59.00 No | 3.35 | 14.46 |
Total Amount: |
431.48 |
|
100 |
431.48 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
26-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-October-2015 | 40.56 lakh | 2. | 30-November-2015 | 30.94 lakh | 3. | 04-March-2016 | 73.95 lakh | 4. | 21-July-2016 | 110.37 lakh | 5. | 31-August-2016 | 53.05 lakh | 6. | 27-October-2016 | 83.41 lakh | 7. | 30-December-2016 | 5.02 lakh | 8. | 28-February-2017 | 19.28 lakh | 9. | 24-March-2017 | 1.95 lakh | 10. | 20-May-2017 | 73.86 lakh | 11. | 25-November-2017 | 19.66 lakh | 12. | 28-February-2018 | 18.04 lakh | 13. | 28-April-2018 | 57.13 lakh |
Total |
587.22 lakh |
% Payment | 104.92 % |
|
Advance Amount: 140.00 lakh
Recovered Amount: 140.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 191 No. of Test Done : 198 No. of Test Passed : 162 No. of Test Failed : 36 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 94.67 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 152 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-04-2017 | 1.475 | Seal | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
2. | 12-04-2017 | 1.460 | Seal coat work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
3. | 12-04-2017 | Chainage-3.780 | Damage R/wall reconstruction work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
4. | 12-01-2017 | 0.530 | Construction of toe wall in RR 1:5.
Without using safety measures | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
5. | 02-12-2016 | Ch 3.800km | R/wall rejected due to bad masonry work | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
6. | 01-12-2016 | Chainage-4.225km | Thickness checking of pc G2 1st & 2nd layer & G3 by pwd ce sir | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
7. | 01-12-2016 | Chainage-6.950km | Thickness checking by pwd chief engineer sir | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
8. | 01-12-2016 | Ch.6.950km | Pwd chief engineer sir visit | Manish Rana | JE | UDRP R&B Gopeshwar | See Pic |
9. | 28-10-2016 | 5.190 | Taking Joint Measurement of PC Work | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
10. | 28-10-2016 | 2.700 | Jointly checking of thickness of PC Work | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
11. | 28-10-2016 | 2.950 | Gradiation test of WBM G3by RE Sir | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
12. | 28-10-2016 | 2.800 | Bitumin Extraction test in site | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
13. | 28-10-2016 | 2.625 | Thickness checking by RE Sir | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
14. | 26-10-2016 | 4.740 | PC WORK IN PROGRESS | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
15. | 17-10-2016 | 5.250 | Bitumin Extraction test in site lab | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
16. | 17-10-2016 | 5.075 | Seal Coat work in progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
17. | 17-10-2016 | 5.380 | Thickness checking of PC Work by RE Sir | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
18. | 17-10-2016 | 5.125 | Rolling of seal coat surface | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
19. | 15-10-2016 | 5.725 | Tack Coat & PC Work in progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
20. | 11-10-2016 | 5.375 | Seal Coat Work in Progress | Alok Chandra Joshi | Site Supervisor | DSC1 R&B WB Chamoli | See Pic |
|
|