Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Aagerchatti Jingod Motor Road Work Completed
Project: UDRP-RB UID: 1222 Sanction Cost: 629.57  lakh Length: 7.000 KM.
District: Chamoli Block: Gairsain Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 117        Package Name:  UDRP/PWD/02/36/RD/106        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 06-08-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/36/RD/106      Contractor Name: Singla Construction Limited
Start Date:  13-08-2015      Intended Completion Date:  14-05-2017      Original End Date:  12-11-2016
Total Bond Cost: 103206509.48 (1032.07 lakh)        Variation Cost: 13196287.93 (131.96 lakh)    Hence Total Bond Cost is   116402797.41 (1164.03 lakh) 
Sub Project Cost: 584.30  lakh        Variation Cost of Sub Project: -2463265.03  (-24.63 lakh)       Total Sub Project Cost:   559.67 lakh
LD Analysis for Milestone1: calculated LD is Rs 2941371 for 57 days        LD Analysis for Milestone2: calculated LD is Rs 4025034 for 78 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence7.00 KM22.5402-09-201512-02-20177.00 KM7.00 KM5.2222.54
2.R/Wall, B/ Wall Type Protection works2184.00 m193.6315-09-201525-02-20172184.00 m2184.00 m44.88193.63
3.G-214.00 KM74.8615-01-201625-02-201714.00 KM14.00 KM17.3574.86
4.G-37.00 KM49.9315-02-201608-03-20177.00 KM7.00 KM11.5749.93
5.PC/CC i/c Prime Coat, Tack Coat7.00 KM31.6404-04-201625-04-20177.00 KM7.00 KM7.3331.64
6.Cause Way4.00 No5.8109-05-201601-03-20174.00 No4.00 No1.355.81
7.Culverts/Scupper 38.00 No32.0320-10-201510-02-201738.00 No38.00 No7.4232.03
8.longitudinal Drain7000.00 m6.5818-02-201630-05-20177000.00 m7000.00 m1.526.58
9.Crash Barrier0.00 m0.0009-12-201630-05-20170.00 m0.00 m00.00
10.Parapet0.00 No0.0001-04-201730-05-20170.00 No0.00 No00.00
11.Road Furniture59.00 No14.4625-09-201630-05-201759.00 No59.00 No3.3514.46
Total Amount: 431.48 100   431.48
Remarks: No Remarks       Work Program Made On: 25-09-2015        Updation of work program on: 26-05-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-October-201540.56  lakh
2.30-November-201530.94  lakh
3.04-March-201673.95  lakh
4.21-July-2016110.37  lakh
5.31-August-201653.05  lakh
6.27-October-201683.41  lakh
7.30-December-20165.02  lakh
8.28-February-201719.28  lakh
9.24-March-20171.95  lakh
10.20-May-201773.86  lakh
11.25-November-201719.66  lakh
12.28-February-201818.04  lakh
13.28-April-201857.13  lakh
Total 587.22  lakh
% Payment104.92 %
Advance Amount:  140.00  lakh        Recovered Amount:  140.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 191   No. of Test Done : 198    No. of Test Passed : 162   No. of Test Failed : 36   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 94.67
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 152
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-04-20171.475SealManish RanaJEUDRP R&B Gopeshwar See Pic
2.12-04-20171.460Seal coat workManish RanaJEUDRP R&B Gopeshwar See Pic
3.12-04-2017Chainage-3.780Damage R/wall reconstruction workManish RanaJEUDRP R&B Gopeshwar See Pic
4.12-01-20170.530Construction of toe wall in RR 1:5. Without using safety measuresAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
5.02-12-2016Ch 3.800kmR/wall rejected due to bad masonry workManish RanaJEUDRP R&B Gopeshwar See Pic
6.01-12-2016Chainage-4.225kmThickness checking of pc G2 1st & 2nd layer & G3 by pwd ce sirManish RanaJEUDRP R&B Gopeshwar See Pic
7.01-12-2016Chainage-6.950kmThickness checking by pwd chief engineer sirManish RanaJEUDRP R&B Gopeshwar See Pic
8.01-12-2016Ch.6.950kmPwd chief engineer sir visitManish RanaJEUDRP R&B Gopeshwar See Pic
9.28-10-20165.190Taking Joint Measurement of PC WorkAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
10.28-10-20162.700Jointly checking of thickness of PC WorkAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
11.28-10-20162.950Gradiation test of WBM G3by RE SirAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
12.28-10-20162.800Bitumin Extraction test in siteAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
13.28-10-20162.625Thickness checking by RE SirAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
14.26-10-20164.740PC WORK IN PROGRESSAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
15.17-10-20165.250Bitumin Extraction test in site labAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
16.17-10-20165.075Seal Coat work in progressAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
17.17-10-20165.380Thickness checking of PC Work by RE SirAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
18.17-10-20165.125Rolling of seal coat surfaceAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
19.15-10-20165.725Tack Coat & PC Work in progressAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic
20.11-10-20165.375Seal Coat Work in ProgressAlok Chandra JoshiSite SupervisorDSC1 R&B WB Chamoli See Pic