Sunali - Dasholikhal MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1220 |
Sanction Cost: |
1091.56 lakh |
Length:
|
15.400 KM. |
District: |
Chamoli |
Block: |
Karnaprayag |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 116
Package Name: 
UDRP/PWD/02/36/RD/105
Tender Date: 11-09-2015
Current Status: Agreement signed
Achieved on Date: 05-01-2016 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/105
Contractor Name: N P Buildwell Pvt. Ltd
|
Start Date: 12-01-2016
Intended Completion Date: 10-06-2019
Original End Date: 11-04-2017 |
Total Bond Cost: 103646807.66 (1036.47 lakh)
Variation Cost: 25046778.29 (250.47 lakh) Hence Total Bond Cost is 128693585.95 (1286.94 lakh)
|
Sub Project Cost: 730.05 lakh
Variation Cost of Sub Project: 30666623.73 (306.67 lakh)
Total Sub Project Cost:
1036.72 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 9120848 for 176 days
LD Analysis for Milestone2: calculated LD is Rs 24615925 for 475 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 15.40 KM | 143.18 | 10-02-2016 | 12-11-2018 | 15.40 KM | 15.40 KM | 13.19 | 143.18 | 2. | R/Wall, B/ Wall Type Protection works | 3931.00 m | 336.67 | 15-02-2016 | 15-04-2019 | 3931.00 m | 3931.00 m | 31.02 | 336.67 | 3. | GSB/RBI/G-1 | 2.90 KM | 25.25 | 10-03-2019 | 02-04-2019 | 2.90 KM | 2.90 KM | 2.33 | 25.25 | 4. | G-2 | 9.50 KM | 47.54 | 12-06-2017 | 11-04-2019 | 9.50 KM | 9.50 KM | 4.38 | 47.54 | 5. | G-3 | 13.90 KM | 126.09 | 15-07-2017 | 21-04-2019 | 13.90 KM | 13.90 KM | 11.62 | 126.09 | 6. | PC/CC i/c Prime Coat, Tack Coat | 15.40 KM | 187.78 | 01-04-2018 | 28-04-2019 | 15.40 KM | 15.40 KM | 17.3 | 187.78 | 7. | Cause Way | 20.00 No | 74.98 | 01-06-2018 | 15-04-2019 | 20.00 No | 20.00 No | 6.91 | 74.98 | 8. | Culverts/Scupper | 27.00 No | 73.20 | 20-06-2016 | 20-04-2019 | 27.00 No | 27.00 No | 6.75 | 73.20 | 9. | longitudinal Drain | 15400.00 m | 31.29 | 08-09-2016 | 25-04-2019 | 15400.00 m | 15400.00 m | 2.88 | 31.29 | 10. | Crash Barrier | 0.00 m | 0.00 | 10-11-2017 | 10-11-2017 | 0.00 m | 0.00 m | 0 | 0.00 | 11. | Parapet | 810.00 No | 27.23 | 25-03-2018 | 15-04-2019 | 810.00 No | 810.00 No | 2.51 | 27.23 | 12. | Road Furniture | 319.00 No | 4.10 | 15-03-2017 | 28-04-2019 | 319.00 No | 319.00 No | 0.38 | 4.10 | 13. | Env. Man & Moni Plan | 1.00 Job | 7.89 | 12-01-2019 | 30-04-2019 | 1.00 Job | 1.00 Job | 0.73 | 7.89 |
Total Amount: |
1085.2 |
|
100 |
1085.2 |
|
Remarks:
No Remarks
Work Program Made On:
11-02-2016 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 02-May-2016 | 36.13 lakh | 2. | 30-June-2016 | 22.92 lakh | 3. | 24-August-2016 | 57.16 lakh | 4. | 30-September-2016 | 17.00 lakh | 5. | 26-October-2016 | 26.05 lakh | 6. | 10-February-2017 | 104.73 lakh | 7. | 31-March-2017 | 44.75 lakh | 8. | 13-October-2017 | 28.62 lakh | 9. | 25-November-2017 | 26.56 lakh | 10. | 04-January-2018 | 36.01 lakh | 11. | 28-February-2018 | 9.42 lakh | 12. | 28-March-2018 | 50.95 lakh | 13. | 21-May-2018 | 12.11 lakh | 14. | 31-May-2018 | 57.27 lakh | 15. | 23-August-2018 | 55.55 lakh | 16. | 28-September-2018 | 15.31 lakh | 17. | 16-October-2018 | 26.69 lakh | 18. | 31-October-2018 | 36.57 lakh | 19. | 28-November-2018 | 39.31 lakh | 20. | 29-November-2018 | 24.78 lakh | 21. | 31-December-2018 | 45.72 lakh | 22. | 16-February-2019 | 20.72 lakh | 23. | 27-February-2019 | 12.27 lakh | 24. | 30-March-2019 | 49.38 lakh | 25. | 10-April-2019 | 18.61 lakh | 26. | 30-April-2019 | 21.06 lakh | 27. | 22-May-2019 | 63.51 lakh | 28. | 19-June-2019 | 46.66 lakh | 29. | 12-July-2019 | 62.79 lakh | 30. | 15-July-2019 | 16.58 lakh |
Total |
1085.19 lakh |
% Payment | 104.68 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1005 No. of Test Done : 1305 No. of Test Passed : 1258 No. of Test Failed : 47 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 92.96 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 78 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 21-01-2019 | Ch 11.350 | Excavation for causeway | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
2. | 13-12-2018 | Ch 8.950 | Taking mts of P. C | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
3. | 23-11-2018 | Ch 9.700 | WBM in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
4. | 15-10-2018 | Ch 3+600 to 3+650 | Casting of parapet satisfactorily | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
5. | 15-10-2018 | Ch 3+575 to 3+600 | Construction of R/W under progress, small size of stone is using, it has removed and rebuild with big size of stone. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
6. | 26-09-2018 | Ch. 1.275 | C.C. pavement in progress | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
7. | 21-09-2018 | Lab | Checking of silt content in coarse sand | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
8. | 19-09-2018 | Ch 1+900 to1+950 | Laying of khadenja in causeway under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
9. | 19-09-2018 | Ch 6+500 to 6+525 | Road is settled due heavy rain fall on dated 09-09-3018 | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
10. | 19-09-2018 | Ch 4+825 | Old R/W damaged due to heavy rainfall on Dt 09/09/2018 | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
11. | 19-09-2018 | Ch 3+725 to 3+750 | Construction of R/W is completed satisfactorily which is damaged in rainy season | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
12. | 06-09-2018 | Ch 1.950 | Debris disposal | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
13. | 06-09-2018 | Ch 6.300 | Debris disposal | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
14. | 20-08-2018 | Ch 3+725 | Damage of old R/W due to heavy rainfall | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
15. | 08-08-2018 | Ch 4.800 | Clearance of land slid for opening communication | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
16. | 08-08-2018 | Ch 3.425 | Clearance of land slid | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
17. | 05-07-2018 | Ch 0.900 | Painting on parapet is under progress | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
18. | 05-07-2018 | Ch 1.035 | Laying of Khadenja in causeway satisfactorily. | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
19. | 05-07-2018 | Ch 1.400 to 1.425 | Causeway M30 done satisfactorily | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
20. | 28-05-2018 | Ch 5.00 to 5.050 | Laying of PC satisfactorily | Dhwajvir Singh | JE | UDRP R&B Karnprayag | See Pic |
|
|