Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Sonla - Kandara - Maikhura Silangi MR Work Completed
Project: UDRP-RB UID: 1219 Sanction Cost: 1625.43  lakh Length: 36.000 KM.
District: Chamoli Block: Karnaprayag Constituency: Karanprayag Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 9        Package Name:  UDRP/PWD/02/38/RD/009        Tender Date: 01-02-2014        Current Status: Agreement signed        Achieved on Date: 26-04-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/02/38/RD/009      Contractor Name: Ramnarayan.
Start Date:  26-04-2014      Intended Completion Date:  28-05-2017      Original End Date:  26-07-2015
Total Bond Cost: 123395603.92 (1233.96 lakh)        Variation Cost: 35350130.57 (353.5 lakh)    Hence Total Bond Cost is   158745734.49 (1587.46 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 3455088 for 56 days        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence7.00 KM135.1420-04-201531-12-20167.00 KM7.00 KM9.16135.14
2.R/Wall, B/ Wall Type Protection works5588.00 m460.6326-04-201415-01-20175588.00 m5588.00 m31.21460.63
3.GSB/RBI/G-17.39 KM33.1701-06-201425-01-20177.39 KM7.39 KM2.2533.17
4.G-211.00 KM36.9630-10-201525-05-201711.00 KM11.00 KM2.536.96
5.G-311.00 KM41.7220-10-201525-05-201711.00 KM11.00 KM2.8341.72
6.PC/CC i/c Prime Coat, Tack Coat32.50 KM361.2815-05-201528-05-201732.50 KM32.50 KM24.48361.28
7.Cause Way8.00 No17.4801-10-201428-05-20178.00 No8.00 No1.1817.48
8.Culverts/Scupper 68.00 No124.1301-08-201428-05-201768.00 No68.00 No8.41124.13
9.longitudinal Drain32500.00 m98.6401-05-201524-05-201732500.00 m32500.00 m6.6898.64
10.Crash Barrier602.00 m70.7812-09-201610-05-2017602.00 m602.00 m4.870.78
11.Parapet1976.00 No88.2701-09-201528-05-20171976.00 No1976.00 No5.9888.27
12.Road Furniture410.00 No7.9201-02-201628-05-2017410.00 No410.00 No0.547.92
Total Amount: 1476.12 100   1476.12
Remarks: Lab Establised       Work Program Made On: 19-06-2014        Updation of work program on: 23-09-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-September-201463.27  lakh
2.06-December-201452.73  lakh
3.31-December-201436.70  lakh
4.12-February-201538.22  lakh
5.02-March-201518.17  lakh
6.18-March-201518.95  lakh
7.28-March-20155.72  lakh
8.21-April-201514.98  lakh
9.03-June-201534.59  lakh
10.11-September-201548.19  lakh
11.28-September-2015115.04  lakh
12.19-October-201527.87  lakh
13.31-October-201589.28  lakh
14.30-November-201560.95  lakh
15.15-January-201612.33  lakh
16.23-January-201651.14  lakh
17.28-February-201629.51  lakh
18.30-March-201652.62  lakh
19.02-May-201640.39  lakh
20.11-May-2016137.15  lakh
21.30-June-2016101.48  lakh
22.21-July-201652.43  lakh
23.24-August-201624.28  lakh
24.30-August-20160.78  lakh
25.26-October-201645.33  lakh
26.30-December-201656.82  lakh
27.25-January-201732.89  lakh
28.10-February-201718.92  lakh
29.23-March-201713.13  lakh
30.20-May-201755.39  lakh
31.17-July-201737.33  lakh
32.18-December-201763.07  lakh
33.24-April-201852.00  lakh
34.28-August-201811.22  lakh
Total 1512.87  lakh
% Payment 95.3 %
Advance Amount:  195.66  lakh        Recovered Amount:  195.66  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 613   No. of Test Done : 633    No. of Test Passed : 544   No. of Test Failed : 89   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.00
Number of Notice(s) issued: 109

Mobile Pic Upload

Number of Pics Available on Web Repository: 675
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.03-08-201720.125Site inspection SEAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.17-07-201714.300Ashwani KumarREDSC4 R&B WB Chamoli See Pic
3.02-12-201619.010Road edge damaged due to cutting of road by Airtel instead of hillsideAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.02-12-201611.425Road edge cutting by Airtel instead of hillsideAshwani KumarREDSC4 R&B WB Chamoli See Pic
5.02-12-2016Ch. 19.025Pc edge cutting + drain damageAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
6.30-11-2016Ch. 5.850Slip clearanceAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
7.30-11-2016Ch. 6.300Slip clearanceAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
8.30-11-2016Ch. 7.150Slip clearanceAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
9.30-11-2016Ch. 9.925Way for templeAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
10.21-11-2016CH 10.100Causeway damage due to laying of ducts by AirtelJayendra PundirSite SupervisorDSC1 R&B WB Chamoli See Pic
11.18-11-201612.500Kc drain dismentlingPiyush MishraJEUDRP R&B Gopeshwar See Pic
12.17-11-2016Ch. 12. 550Pc + KC drain damageAnkur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
13.15-11-2016Ch. 28. 285Plum work is going...Ankur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
14.09-11-201628.200P.c work at ch 28.200Piyush MishraJEUDRP R&B Gopeshwar See Pic
15.09-11-201611.300Diffuct cuttingPiyush MishraJEUDRP R&B Gopeshwar See Pic
16.09-11-2016550Parapet white washingPiyush MishraJEUDRP R&B Gopeshwar See Pic
17.09-11-2016Ch.11. 350Patch work is going on.....Ankur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
18.08-11-2016Ch.9. 950Profile correction for patch work.......Ankur VishwasContractor Site EngineerDSC1 R&B WB Chamoli See Pic
19.07-11-201611,800DeefatDeepak RawatContractor Site SupervisorDSC1 R&B WB Chamoli See Pic
20.07-11-2016Ch.3,525Birecha.ropanDeepak RawatContractor Site SupervisorDSC1 R&B WB Chamoli See Pic