Salor - Dungra MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1217 |
Sanction Cost: |
293.34 lakh |
Length:
|
6.000 KM. |
District: |
Chamoli |
Block: |
Joshimath |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 92
Package Name: 
UDRP/PWD/02/08/RD/081
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 31-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/081
Contractor Name: Raina Construction
|
Start Date: 07-08-2015
Intended Completion Date: 31-03-2018
Original End Date: 06-11-2016 |
Total Bond Cost: 31526435.26 (315.26 lakh)
Variation Cost: 2442431.62 (24.42 lakh) Hence Total Bond Cost is 33968866.88 (339.69 lakh)
|
Sub Project Cost: 252.66 lakh
Variation Cost of Sub Project: 2365885.88 (23.66 lakh)
Total Sub Project Cost:
276.32 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2616658 for 166 days
LD Analysis for Milestone2: calculated LD is Rs 4902293 for 311 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 6.00 KM | 10.40 | 25-08-2015 | 05-11-2017 | 6.00 KM | 6.00 KM | 4.38 | 10.40 | 2. | R/Wall, B/ Wall Type Protection works | 506.00 m | 48.31 | 01-10-2015 | 25-03-2017 | 506.00 m | 506.00 m | 20.33 | 48.31 | 3. | G-2 | 2.50 KM | 13.50 | 11-03-2016 | 05-11-2017 | 2.50 KM | 2.50 KM | 5.68 | 13.50 | 4. | G-3 | 5.70 KM | 34.76 | 20-03-2016 | 24-07-2016 | 5.70 KM | 5.70 KM | 14.63 | 34.76 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.00 KM | 77.73 | 25-09-2016 | 30-11-2017 | 6.00 KM | 6.00 KM | 32.71 | 77.73 | 6. | Culverts/Scupper | 4.00 No | 36.83 | 11-02-2016 | 22-08-2017 | 4.00 No | 4.00 No | 15.5 | 36.83 | 7. | longitudinal Drain | 6000.00 m | 11.99 | 22-03-2016 | 12-06-2017 | 6000.00 m | 6000.00 m | 5.04 | 11.99 | 8. | Parapet | 105.00 No | 1.84 | 07-02-2016 | 25-03-2018 | 105.00 No | 105.00 No | 0.77 | 1.84 | 9. | Road Furniture | 140.00 No | 2.27 | 30-09-2016 | 31-03-2018 | 140.00 No | 140.00 No | 0.96 | 2.27 |
Total Amount: |
237.63 |
|
100 |
237.63 |
|
Remarks:
No Remarks
Work Program Made On:
28-09-2015 } ?>
Updation of work program on:
17-04-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 05-December-2015 | 15.85 lakh | 2. | 29-February-2016 | 13.08 lakh | 3. | 11-May-2016 | 0.06 lakh | 4. | 30-June-2016 | 35.74 lakh | 5. | 30-September-2016 | 40.45 lakh | 6. | 26-October-2016 | 13.54 lakh | 7. | 31-December-2016 | 6.91 lakh | 8. | 08-March-2017 | 6.62 lakh | 9. | 25-May-2017 | 26.47 lakh | 10. | 28-July-2017 | 19.47 lakh | 11. | 16-October-2017 | 0.67 lakh | 12. | 17-October-2017 | 0.43 lakh | 13. | 18-December-2017 | 46.73 lakh | 14. | 17-February-2018 | 8.74 lakh | 15. | 15-May-2018 | 10.44 lakh | 16. | 07-June-2018 | 20.85 lakh | 17. | 13-September-2018 | 17.81 lakh |
Total |
283.86 lakh |
% Payment | 102.73 % |
|
Advance Amount: 12.00 lakh
Recovered Amount: 12.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 78 No. of Test Done : 85 No. of Test Passed : 75 No. of Test Failed : 10 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.00 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 95 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 23-11-2017 | 3.300 | Consultation with local people Mr kuldip Chuhan regarding metal crash barriers | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 23-11-2017 | 3.400 | Rolling on seal coat | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
3. | 23-11-2017 | 3.400 | Laying of seal coat | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 23-11-2017 | 3.280 | OGPC thickness checking by EE Gopeshwar thickness found 25mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
5. | 18-11-2017 | 4.260 | Checking of road width found 4.100 | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
6. | 01-11-2017 | 3.300 | Checking of road width 6.0m | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
7. | 03-10-2017 | 3.400 | WBM G3 layer work in progress but thickness or layer is only 50 mm. So, instruction given to contractor to rectify WBMG3 layer | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
8. | 17-07-2017 | 4.300 | Road closed due to heavy land slide | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
9. | 15-05-2017 | 1.600 | Undulation checking found 10mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
10. | 27-01-2017 | Site Lab | Testing for AIV passed | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
11. | 05-01-2017 | 1.050 | Thickness checking of G2 &G3 Layer found 150mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
12. | 27-12-2016 | 1.675 | C type drain | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
13. | 13-12-2016 | Ch-3.150 | Road width checking after Hill cutting | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
14. | 13-12-2016 | Ch-3.280 | Gradation for g2 | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
15. | 27-10-2016 | Ch-1.300 | Prime coat | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
16. | 26-10-2016 | Ch 5.800 | Insulation checking | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
17. | 26-10-2016 | Ch6.150 | Laying of seal coat | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
18. | 26-10-2016 | Ch 6.000 | Temperature checking of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
19. | 26-10-2016 | Ch 6.000 | Undulation checking | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
20. | 26-10-2016 | Ch 6.00 | Rolling of pc | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
|
|