Panduwakhan Rohilda Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1214 |
Sanction Cost: |
496.87 lakh |
Length:
|
15.680 KM. |
District: |
Chamoli |
Block: |
Gairsain |
Constituency: |
Karanprayag |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Karanprayag |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 146
Package Name: 
UDRP/PWD/02/36/RD/026N
Tender Date: 29-01-2018
Current Status: Agreement signed
Achieved on Date: 02-07-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/36/RD/026N
Contractor Name: R K Gupta Contractor
|
Start Date: 12-07-2018
Intended Completion Date: 15-06-2019
Original End Date: 31-05-2019 |
Total Bond Cost: 46225278.26 (462.25 lakh)
|
Sub Project Cost: 224.55 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 15.68 KM | 5.21 | 15-07-2018 | 30-11-2018 | 15.68 KM | 15.68 KM | 2.32 | 5.21 | 2. | R/Wall, B/ Wall Type Protection works | 858.00 m | 40.35 | 31-07-2018 | 10-06-2019 | 858.00 m | 858.00 m | 17.97 | 40.35 | 3. | GSB/RBI/G-1 | 1.10 KM | 12.06 | 21-07-2018 | 10-04-2019 | 1.10 KM | 1.10 KM | 5.37 | 12.06 | 4. | G-2 | 1.10 KM | 9.66 | 21-12-2018 | 30-05-2019 | 1.10 KM | 1.10 KM | 4.3 | 9.66 | 5. | G-3 | 2.72 KM | 22.46 | 10-01-2019 | 07-06-2019 | 2.72 KM | 2.72 KM | 10 | 22.46 | 6. | PC/CC i/c Prime Coat, Tack Coat | 7.80 KM | 62.38 | 01-03-2019 | 10-06-2019 | 7.80 KM | 7.80 KM | 27.78 | 62.38 | 7. | Culverts/Scupper | 8.00 No | 32.00 | 20-11-2018 | 10-06-2019 | 8.00 No | 8.00 No | 14.25 | 32.00 | 8. | longitudinal Drain | 15000.00 m | 18.07 | 01-09-2018 | 10-06-2019 | 15000.00 m | 15000.00 m | 8.05 | 18.07 | 9. | Crash Barrier | 200.00 m | 8.42 | 01-05-2019 | 24-06-2019 | 200.00 m | 200.00 m | 3.75 | 8.42 | 10. | Parapet | 151.00 No | 4.65 | 20-03-2019 | 16-06-2019 | 151.00 No | 151.00 No | 2.07 | 4.65 | 11. | Road Furniture | 187.00 No | 4.55 | 20-05-2019 | 24-06-2019 | 187.00 No | 187.00 No | 2.03 | 4.55 | 12. | Env. Man & Moni Plan | 1.00 Job | 4.73 | 12-07-2018 | 15-06-2019 | 1.00 Job | 1.00 Job | 2.11 | 4.73 |
Total Amount: |
224.54 |
|
100 |
224.54 |
|
Remarks:
Collection of soling coat in progress
Work Program Made On:
04-09-2018 } ?>
Updation of work program on:
02-08-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-September-2014 | 10.84 lakh | 2. | 06-December-2014 | 12.31 lakh | 3. | 31-January-2015 | 16.96 lakh | 4. | 03-March-2015 | 7.98 lakh | 5. | 27-March-2015 | 6.14 lakh | 6. | 05-May-2015 | 12.38 lakh | 7. | 12-October-2015 | 44.38 lakh | 8. | 03-December-2015 | 0.12 lakh | 9. | 24-December-2015 | 37.14 lakh | 10. | 30-March-2016 | 14.19 lakh | 11. | 30-August-2016 | 40.23 lakh | 12. | 01-September-2016 | 37.16 lakh |
Previous Package Expenditure Total |
239.83 lakh |
SNo. |
Date |
Payment |
1. | 27-September-2018 | 15.74 lakh | 2. | 31-October-2018 | 19.24 lakh | 3. | 29-December-2018 | 16.08 lakh | 4. | 26-February-2019 | 10.04 lakh | 5. | 30-March-2019 | 11.06 lakh | 6. | 16-April-2019 | 8.66 lakh | 7. | 30-April-2019 | 33.12 lakh | 8. | 10-June-2019 | 40.82 lakh | 9. | 19-June-2019 | 30.33 lakh | 10. | 25-June-2019 | 12.51 lakh | 11. | 12-July-2019 | 24.06 lakh | 12. | 15-July-2019 | 2.89 lakh |
Total |
224.55 lakh |
% Payment | 100 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 261 No. of Test Done : 321 No. of Test Passed : 321 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.20 |
Number of Notice(s) issued: 5 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 227 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-06-2019 | Ch. 0.500 | Exen sir visit pandvakhal road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
2. | 19-05-2019 | Ch.11.000 | CME sir & Exen sir visit pc work at rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
3. | 19-05-2019 | Ch.10.900 | CME sir & Exen Sir visit pc work | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
4. | 21-04-2019 | Ch.15.610 | Pc starts pandvakhal rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
5. | 21-04-2019 | Ch.15.630 | Exen sir visit pc work | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
6. | 21-04-2019 | Ch.15.680 | Exen sir visit rohida road as pc work starts today | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
7. | 05-04-2019 | Ch.15.680 | DPM sir visit rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
8. | 05-04-2019 | Ch. 13.050 | DPM sir visit rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
9. | 07-02-2019 | Patch work | Ch 10.975 | Lalit Mohan Benjwal | AE | UDRP R&B Karnprayag | See Pic |
10. | 21-01-2019 | Ch 11.400 | Plum protection on slipzone area | Naveen Kumar Sharma | AE | UDRP R&B Karanprayag | See Pic |
11. | 08-01-2019 | Ch.11.400 | Plum concrete in critical zone rohida road | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
12. | 14-12-2018 | Ch.11.325 | Plum concrete in critical zone pkg 26 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
13. | 14-12-2018 | Ch. 12.300 | Laying of G3 coat pkg 26 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
14. | 14-12-2018 | Ch. 15.460 | Kc drain pcc starts today pkg 26 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
15. | 30-11-2018 | Ch. 13.900 | G 2 coat laying pkg 26 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
16. | 15-10-2018 | Ch. 14.800 | Exen sir visit pkg 26 new | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
17. | 09-08-2018 | Ch. 5.100 pandvakhal dharapani road | R/wall in peogress | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
18. | 03-08-2018 | Ch. 5.100 pandvakhal dharapani road r/ wall in progress | Rwall under progress | Gaurav Bhardwaj | JE | UDRP R&B Karnprayag | See Pic |
19. | 11-05-2016 | Ch9.650 | OGPC work | Gaurav Bhandari | JE | UDRP R&B Gopeshwar | See Pic |
20. | 11-05-2016 | 9.640 | OGPC work | Gaurav Bhandari | JE | UDRP R&B Gopeshwar | See Pic |
|
|