Nagnath Link MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1210 |
Sanction Cost: |
124.46 lakh |
Length:
|
1.650 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 107
Package Name: 
UDPR/PWD/03/RD/096
Tender Date: 23-05-2015
Current Status: Agreement signed
Achieved on Date: 03-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDPR/PWD/03/RD/096
Contractor Name: Hindustan Construction
|
Start Date: 10-09-2015
Intended Completion Date: 15-05-2017
Original End Date: 09-12-2016 |
Total Bond Cost: 38802100 (388.02 lakh)
Variation Cost: 2853664.64 (28.54 lakh) Hence Total Bond Cost is 41655764.64 (416.56 lakh)
|
Sub Project Cost: 121.29 lakh
Variation Cost of Sub Project: -2003309.02 (-20.03 lakh)
Total Sub Project Cost:
101.26 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.65 KM | 3.65 | 06-10-2015 | 30-03-2017 | 1.65 KM | 1.65 KM | 4.08 | 3.65 | 2. | R/Wall, B/ Wall Type Protection works | 625.00 m | 11.52 | 12-10-2015 | 30-03-2017 | 625.00 m | 625.00 m | 12.88 | 11.52 | 3. | G-2 | 1.65 KM | 12.89 | 10-02-2016 | 30-03-2017 | 1.65 KM | 1.65 KM | 14.42 | 12.89 | 4. | G-3 | 1.65 KM | 9.08 | 25-03-2016 | 30-04-2017 | 1.65 KM | 1.65 KM | 10.16 | 9.08 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.65 KM | 20.28 | 20-05-2016 | 30-12-2016 | 1.65 KM | 1.65 KM | 22.69 | 20.28 | 6. | Culverts/Scupper | 5.00 No | 24.57 | 10-10-2015 | 30-12-2016 | 5.00 No | 5.00 No | 27.48 | 24.57 | 7. | longitudinal Drain | 1650.00 m | 5.63 | 01-02-2016 | 30-12-2016 | 1650.00 m | 1650.00 m | 6.3 | 5.63 | 8. | Parapet | 40.00 No | 1.05 | 02-06-2016 | 30-12-2016 | 40.00 No | 40.00 No | 1.18 | 1.05 | 9. | Road Furniture | 70.00 No | 0.73 | 28-03-2016 | 30-12-2016 | 70.00 No | 70.00 No | 0.81 | 0.73 |
Total Amount: |
89.4 |
|
100 |
89.4 |
|
Remarks:
No Remarks
Work Program Made On:
25-09-2015 } ?>
Updation of work program on:
06-06-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 26-December-2015 | 7.69 lakh | 2. | 21-March-2016 | 5.04 lakh | 3. | 03-April-2016 | 0.84 lakh | 4. | 11-May-2016 | 13.97 lakh | 5. | 30-June-2016 | 35.32 lakh | 6. | 31-August-2016 | 12.94 lakh | 7. | 27-October-2016 | 14.68 lakh | 8. | 28-November-2016 | 0.09 lakh | 9. | 31-March-2017 | 10.84 lakh |
Total |
101.41 lakh |
% Payment | 100.15 % |
|
Advance Amount: 38.00 lakh
Recovered Amount: 5.70 lakh
Balance to be Recovered 32.30 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 209 No. of Test Done : 233 No. of Test Passed : 213 No. of Test Failed : 20 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 90.49 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 80 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 27-09-2016 | 0.650 | Old scupper damage | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 23-09-2016 | Ch 0.275 | Causeway | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
3. | 21-09-2016 | 0.275 | Causeway work in progress | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
4. | 12-09-2016 | At semi bend to siwai lab | Cube testing of M-15 grade | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
5. | 07-09-2016 | At 1.430 | Casting of pucca drain | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
6. | 07-09-2016 | At 1.630 | Parapet | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
7. | 06-09-2016 | Ch. 1+630 | Perafit PCC work in progress | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
8. | 06-09-2016 | At 1.630 | PCC for parapet | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
9. | 06-09-2016 | At 1.630 | Exacavation for parapet. | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
10. | 06-09-2016 | At 1.430 | Drain casting | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
11. | 05-09-2016 | At 1.450 | Drain casting | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
12. | 05-09-2016 | At 1.400 | Thickness checking of concrete | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
13. | 05-08-2016 | At 0.725 | Concrete for drain. | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
14. | 02-08-2016 | At ch.0.875 | Coolie wall work in progress | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
15. | 21-07-2016 | 1.550 | Road damaged due to filling of rain water. | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
16. | 18-07-2016 | Ch -0.550 | Slip clerans work in progress | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
17. | 27-06-2016 | At 0.125 | Coolie wall work | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
18. | 26-06-2016 | At ch 0.570 | Pc measurement | Manish Rathi | JE | UDRP R&B Gopeshwar | See Pic |
19. | 25-06-2016 | Ch 0.200 | Super elevation checking | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
20. | 21-06-2016 | Ch -0.040 | Undulasan checking | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
|
|