Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Nagnath Link MR Work Completed
Project: UDRP-RB UID: 1210 Sanction Cost: 124.46  lakh Length: 1.650 KM.
District: Chamoli Block: Pokhari Constituency: Badrinath Circle: Rudraprayag WB Circle
DEA: DEA Gopeshwar DSC: Yongma Engineering Co. Ltd. DSC Scope: Design and Supervision Type: ODR
Procurement:
Package No.: 107        Package Name:  UDPR/PWD/03/RD/096        Tender Date: 23-05-2015        Current Status: Agreement signed        Achieved on Date: 03-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDPR/PWD/03/RD/096      Contractor Name: Hindustan Construction
Start Date:  10-09-2015      Intended Completion Date:  15-05-2017      Original End Date:  09-12-2016
Total Bond Cost: 38802100 (388.02 lakh)        Variation Cost: 2853664.64 (28.54 lakh)    Hence Total Bond Cost is   41655764.64 (416.56 lakh) 
Sub Project Cost: 121.29  lakh        Variation Cost of Sub Project: -2003309.02  (-20.03 lakh)       Total Sub Project Cost:   101.26 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.65 KM3.6506-10-201530-03-20171.65 KM1.65 KM4.083.65
2.R/Wall, B/ Wall Type Protection works625.00 m11.5212-10-201530-03-2017625.00 m625.00 m12.8811.52
3.G-21.65 KM12.8910-02-201630-03-20171.65 KM1.65 KM14.4212.89
4.G-31.65 KM9.0825-03-201630-04-20171.65 KM1.65 KM10.169.08
5.PC/CC i/c Prime Coat, Tack Coat1.65 KM20.2820-05-201630-12-20161.65 KM1.65 KM22.6920.28
6.Culverts/Scupper 5.00 No24.5710-10-201530-12-20165.00 No5.00 No27.4824.57
7.longitudinal Drain1650.00 m5.6301-02-201630-12-20161650.00 m1650.00 m6.35.63
8.Parapet40.00 No1.0502-06-201630-12-201640.00 No40.00 No1.181.05
9.Road Furniture70.00 No0.7328-03-201630-12-201670.00 No70.00 No0.810.73
Total Amount: 89.4 100   89.4
Remarks: No Remarks       Work Program Made On: 25-09-2015        Updation of work program on: 06-06-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.26-December-20157.69  lakh
2.21-March-20165.04  lakh
3.03-April-20160.84  lakh
4.11-May-201613.97  lakh
5.30-June-201635.32  lakh
6.31-August-201612.94  lakh
7.27-October-201614.68  lakh
8.28-November-20160.09  lakh
9.31-March-201710.84  lakh
Total 101.41  lakh
% Payment100.15 %
Advance Amount:  38.00  lakh        Recovered Amount:  5.70  lakh        Balance to be Recovered  32.30  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 209   No. of Test Done : 233    No. of Test Passed : 213   No. of Test Failed : 20   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.49
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 80
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.27-09-20160.650Old scupper damageAshwani KumarREDSC4 R&B WB Chamoli See Pic
2.23-09-2016Ch 0.275CausewayKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
3.21-09-20160.275Causeway work in progressAshwani KumarREDSC4 R&B WB Chamoli See Pic
4.12-09-2016At semi bend to siwai labCube testing of M-15 gradeManish RathiJEUDRP R&B Gopeshwar See Pic
5.07-09-2016At 1.430Casting of pucca drainManish RathiJEUDRP R&B Gopeshwar See Pic
6.07-09-2016At 1.630ParapetManish RathiJEUDRP R&B Gopeshwar See Pic
7.06-09-2016Ch. 1+630Perafit PCC work in progressSohanbir SinghJEUDRP R&B Chamoli See Pic
8.06-09-2016At 1.630PCC for parapetManish RathiJEUDRP R&B Gopeshwar See Pic
9.06-09-2016At 1.630Exacavation for parapet.Manish RathiJEUDRP R&B Gopeshwar See Pic
10.06-09-2016At 1.430Drain castingManish RathiJEUDRP R&B Gopeshwar See Pic
11.05-09-2016At 1.450Drain castingManish RathiJEUDRP R&B Gopeshwar See Pic
12.05-09-2016At 1.400Thickness checking of concreteManish RathiJEUDRP R&B Gopeshwar See Pic
13.05-08-2016At 0.725Concrete for drain.Manish RathiJEUDRP R&B Gopeshwar See Pic
14.02-08-2016At ch.0.875Coolie wall work in progressManish RathiJEUDRP R&B Gopeshwar See Pic
15.21-07-20161.550Road damaged due to filling of rain water.Manish RathiJEUDRP R&B Gopeshwar See Pic
16.18-07-2016Ch -0.550Slip clerans work in progressPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic
17.27-06-2016At 0.125Coolie wall workManish RathiJEUDRP R&B Gopeshwar See Pic
18.26-06-2016At ch 0.570Pc measurementManish RathiJEUDRP R&B Gopeshwar See Pic
19.25-06-2016Ch 0.200Super elevation checkingKirti Vardhan NegiAEDEA WB Gopeshwar See Pic
20.21-06-2016Ch -0.040Undulasan checkingPramod Kumar BhaskarSite EngineerDSC1 R&B WB Chamoli See Pic