Jaurasi - Hapla - Dhotidhar MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1205 |
Sanction Cost: |
157.67 lakh |
Length:
|
1.700 KM. |
District: |
Chamoli |
Block: |
Pokhari |
Constituency: |
Badrinath |
Circle: |
Rudraprayag WB Circle |
DEA: |
DEA Gopeshwar |
DSC: |
Yongma Engineering Co. Ltd. |
DSC Scope: |
Design and Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 88
Package Name: 
UDRP/PWD/02/08/RD/077
Tender Date: 04-07-2015
Current Status: Agreement signed
Achieved on Date: 23-12-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/02/08/RD/077
Contractor Name: Dream Real Infra
|
Start Date: 30-12-2015
Intended Completion Date: 31-10-2018
Original End Date: 29-03-2017 |
Total Bond Cost: 55686855.62 (556.87 lakh)
Variation Cost: -905472.35 (-9.05 lakh) Hence Total Bond Cost is 54781383.27 (547.81 lakh)
|
Sub Project Cost: 138.65 lakh
Variation Cost of Sub Project: 522668.67 (5.23 lakh)
Total Sub Project Cost:
143.88 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 4204293 for +151 days
LD Analysis for Milestone2: calculated LD is Rs 13782285 for 495 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.70 KM | 3.48 | 01-05-2016 | 10-05-2018 | 1.70 KM | 1.70 KM | 2.72 | 3.48 | 2. | R/Wall, B/ Wall Type Protection works | 410.00 m | 59.32 | 25-05-2016 | 30-04-2018 | 410.00 m | 410.00 m | 46.36 | 59.32 | 3. | G-2 | 1.30 KM | 13.30 | 15-12-2016 | 11-04-2017 | 1.30 KM | 1.30 KM | 10.39 | 13.30 | 4. | G-3 | 1.70 KM | 9.84 | 26-09-2017 | 15-02-2018 | 1.70 KM | 1.70 KM | 7.69 | 9.84 | 5. | PC/CC i/c Prime Coat, Tack Coat | 1.70 KM | 20.89 | 01-10-2017 | 28-05-2018 | 1.70 KM | 1.70 KM | 16.33 | 20.89 | 6. | Cause Way | 7.00 No | 12.54 | 14-01-2018 | 30-04-2018 | 7.00 No | 7.00 No | 9.8 | 12.54 | 7. | Culverts/Scupper | 0.00 No | 0.00 | 01-09-2017 | 20-12-2017 | 0.00 No | 0.00 No | 0 | 0.00 | 8. | longitudinal Drain | 1700.00 m | 5.67 | 20-01-2017 | 30-05-2018 | 1700.00 m | 1700.00 m | 4.43 | 5.67 | 9. | Parapet | 70.00 No | 1.98 | 01-03-2018 | 26-05-2018 | 70.00 No | 70.00 No | 1.55 | 1.98 | 10. | Road Furniture | 83.00 No | 0.95 | 20-02-2017 | 27-05-2018 | 83.00 No | 83.00 No | 0.74 | 0.95 |
Total Amount: |
127.97 |
|
100 |
127.97 |
|
Remarks:
No Remarks
Work Program Made On:
06-02-2016 } ?>
Updation of work program on:
02-06-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-June-2016 | 12.14 lakh | 2. | 09-September-2016 | 8.55 lakh | 3. | 27-October-2016 | 2.35 lakh | 4. | 12-January-2017 | 5.83 lakh | 5. | 24-March-2017 | 8.24 lakh | 6. | 30-November-2017 | 17.70 lakh | 7. | 19-December-2017 | 13.87 lakh | 8. | 31-March-2018 | 27.74 lakh | 9. | 07-June-2018 | 14.99 lakh | 10. | 20-February-2019 | 1.76 lakh |
Total |
113.17 lakh |
% Payment | 78.66 % |
|
Advance Amount: 79.00 lakh
Recovered Amount: 86.50 lakh
Balance to be Recovered -7.50 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 276 No. of Test Done : 255 No. of Test Passed : 243 No. of Test Failed : 12 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.34 |
Number of Notice(s) issued: 2 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 45 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 03-12-2017 | 0.850 | Checking of road width width found 3.75 mm | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
2. | 21-11-2017 | ch.0+525 | Water sprinkling | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
3. | 21-11-2017 | ch.0+550 | Consultation with local puple | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
4. | 20-11-2017 | chanage 0+575 | WBM G-3Laying work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
5. | 08-03-2017 | Ch-0.125 | Chief Sir site visit | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
6. | 13-12-2016 | Ch -1.200 | G2 stone | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
7. | 23-10-2016 | Ch. 1+700 | Site information board | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
8. | 01-10-2016 | Ch-1.450 | Slip clearance | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
9. | 01-10-2016 | Ch-1.250 | Slip clearance | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
10. | 23-09-2016 | Ch 1.250 | Rwall below cause way | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
11. | 21-09-2016 | 1.250 | Slope checking of retaining wall | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
12. | 21-09-2016 | 1.250 | Retaining wall for causeway | Ashwani Kumar | RE | DSC4 R&B WB Chamoli | See Pic |
13. | 06-09-2016 | Ch. 0+400 | Labour at work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
14. | 06-09-2016 | Ch. 1+300 | Jurasi- Hapla-dhotidhar motor road | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
15. | 06-09-2016 | Chanage 1+275 | Plum concreat work | Sohanbir Singh | JE | UDRP R&B Chamoli | See Pic |
16. | 23-08-2016 | Ch-1.050 | Slip clearance havey Rain | Pramod Kumar Bhaskar | Site Engineer | DSC1 R&B WB Chamoli | See Pic |
17. | 30-07-2016 | Chanage 0+775 | Banded Retaining wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
18. | 27-07-2016 | Ch 0.775 | R wall | Kirti Vardhan Negi | AE | DEA WB Gopeshwar | See Pic |
19. | 25-07-2016 | Chanage 0+675 | Bended R/Wall | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
20. | 25-07-2016 | Chanage 1+300 | Breast Wall work in progress | Sohanbir Singh | JE | UDRP R&B Gopeshwar | See Pic |
|
|