Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km)
Work Completed
|
Project: |
UDRP-RB |
UID: |
1144 |
Sanction Cost: |
565.24 lakh |
Length:
|
6.000 KM. |
District: |
Bageshwar |
Block: |
0074 |
Constituency: |
46 |
Circle: |
|
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 144
Package Name: 
UDRP/PWD/08/RD/128
Tender Date: 07-04-2017
Current Status: Agreement signed
Achieved on Date: 14-11-2017 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/RD/128
Contractor Name: Vinod Kumar Chauhan
|
Start Date: 21-11-2017
Intended Completion Date: 20-02-2019
|
Total Bond Cost: 52572926.3 (525.73 lakh)
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.99 KM | 10.99 | 21-11-2017 | 31-03-2018 | 0.99 KM | 0.99 KM | 2.16 | 10.99 | 2. | R/Wall, B/ Wall Type Protection works | 631.00 m | 45.29 | 21-11-2017 | 30-04-2018 | 631.00 m | 631.00 m | 8.91 | 45.29 | 3. | G-2 | 5.90 KM | 81.51 | 15-12-2017 | 30-04-2018 | 5.90 KM | 5.90 KM | 16.04 | 81.51 | 4. | G-3 | 5.90 KM | 47.06 | 01-01-2018 | 15-05-2018 | 5.90 KM | 5.90 KM | 9.26 | 47.06 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.90 KM | 77.15 | 10-05-2018 | 30-10-2018 | 5.90 KM | 5.90 KM | 15.18 | 77.15 | 6. | Cause Way | 2.00 No | 4.44 | 21-11-2017 | 10-05-2018 | 2.00 No | 2.00 No | 0.87 | 4.44 | 7. | Culverts/Scupper | 26.00 No | 73.38 | 21-11-2017 | 31-05-2018 | 26.00 No | 26.00 No | 14.44 | 73.38 | 8. | longitudinal Drain | 5.90 m | 103.05 | 15-12-2017 | 31-08-2018 | 5.90 m | 5.90 m | 20.28 | 103.05 | 9. | Crash Barrier | 907.00 m | 43.70 | 01-05-2018 | 30-05-2018 | 908.00 m | 908.00 m | 8.6 | 43.70 | 10. | Parapet | 400.00 No | 11.80 | 01-05-2018 | 30-05-2018 | 468.00 No | 468.00 No | 2.32 | 11.80 | 11. | Road Furniture | 385.00 No | 3.75 | 01-11-2018 | 15-02-2019 | 354.00 No | 354.00 No | 0.74 | 3.75 | 12. | Env. Man & Moni Plan | 1.00 Job | 5.99 | 21-11-2017 | 20-02-2019 | 1.00 Job | 1.00 Job | 1.18 | 5.99 |
Total Amount: |
508.11 |
|
100 |
508.11 |
|
Remarks:
No Remarks
Work Program Made On:
04-01-2018 } ?>
Updation of work program on:
18-05-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 19-December-2017 | 65.00 lakh | 2. | 16-February-2018 | 143.16 lakh | 3. | 26-March-2018 | 138.03 lakh | 4. | 28-May-2018 | 89.18 lakh | 5. | 13-July-2018 | 55.27 lakh | 6. | 27-August-2018 | 6.24 lakh |
Total |
496.88 lakh |
% Payment |
94.5 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 522 No. of Test Done : 541 No. of Test Passed : 528 No. of Test Failed : 13 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.84 |
Number of Notice(s) issued: 12 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 175 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 31-07-2018 | 11+000 | SRMD, Slip clearance | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
2. | 31-07-2018 | 11+350 | SRMD, Slip clearance | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
3. | 31-07-2018 | 7+900 | SRMD, Slip clearance | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
4. | 31-07-2018 | 7+100 | SRMD, Slip clearance | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
5. | 31-07-2018 | 7+100 | SRMD,Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
6. | 31-07-2018 | 7+850 | SRMD,Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
7. | 31-07-2018 | 8+250 | Hp band | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
8. | 31-07-2018 | 10+220 | SRMD,Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
9. | 31-07-2018 | 11+000 | SRMD,Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
10. | 31-07-2018 | 11+050 | SRMD,Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
11. | 31-07-2018 | 11+100 | SRMD Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
12. | 31-07-2018 | 11+350 | SRMD,Slip due to heavy rain | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
13. | 30-07-2018 | Ch 8.200 | Road surface after pc and crash barrier | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 30-07-2018 | Ch 8.200 | Road surface after pc and crash barrier | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 30-07-2018 | Ch 8.220 | HP bend with crash barrier and pucca drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 30-07-2018 | Ch 8.250 | HP bend with crash barrier and pucca drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
17. | 30-07-2018 | Ch 10.220 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
18. | 30-07-2018 | Ch 11.000 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 30-07-2018 | Ch 11.050 | SRMD, slip due to heavy rain. | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 30-07-2018 | Ch 10.790 | Surface after PC and parapet | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|