Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) Work Completed
Project: UDRP-RB UID: 1144 Sanction Cost: 565.24  lakh Length: 6.000 KM.
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 144        Package Name:  UDRP/PWD/08/RD/128        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/128      Contractor Name: Vinod Kumar Chauhan
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 52572926.3 (525.73 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.99 KM10.9921-11-201731-03-20180.99 KM0.99 KM2.1610.99
2.R/Wall, B/ Wall Type Protection works631.00 m45.2921-11-201730-04-2018631.00 m631.00 m8.9145.29
3.G-25.90 KM81.5115-12-201730-04-20185.90 KM5.90 KM16.0481.51
4.G-35.90 KM47.0601-01-201815-05-20185.90 KM5.90 KM9.2647.06
5.PC/CC i/c Prime Coat, Tack Coat5.90 KM77.1510-05-201830-10-20185.90 KM5.90 KM15.1877.15
6.Cause Way2.00 No4.4421-11-201710-05-20182.00 No2.00 No0.874.44
7.Culverts/Scupper 26.00 No73.3821-11-201731-05-201826.00 No26.00 No14.4473.38
8.longitudinal Drain5.90 m103.0515-12-201731-08-20185.90 m5.90 m20.28103.05
9.Crash Barrier907.00 m43.7001-05-201830-05-2018908.00 m908.00 m8.643.70
10.Parapet400.00 No11.8001-05-201830-05-2018468.00 No468.00 No2.3211.80
11.Road Furniture385.00 No3.7501-11-201815-02-2019354.00 No354.00 No0.743.75
12.Env. Man & Moni Plan1.00 Job5.9921-11-201720-02-20191.00 Job1.00 Job1.185.99
Total Amount: 508.11 100   508.11
Remarks: No Remarks       Work Program Made On: 04-01-2018        Updation of work program on: 18-05-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.19-December-201765.00  lakh
2.16-February-2018143.16  lakh
3.26-March-2018138.03  lakh
4.28-May-201889.18  lakh
5.13-July-201855.27  lakh
6.27-August-20186.24  lakh
Total 496.88  lakh
% Payment 94.5 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 522   No. of Test Done : 541    No. of Test Passed : 528   No. of Test Failed : 13   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.84
Number of Notice(s) issued: 12

Mobile Pic Upload

Number of Pics Available on Web Repository: 175
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.31-07-201811+000SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
2.31-07-201811+350SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
3.31-07-20187+900SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
4.31-07-20187+100SRMD, Slip clearanceMukesh KumarJEUDRP R&B Bageshwar See Pic
5.31-07-20187+100SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
6.31-07-20187+850SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
7.31-07-20188+250Hp bandMukesh KumarJEUDRP R&B Bageshwar See Pic
8.31-07-201810+220SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
9.31-07-201811+000SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
10.31-07-201811+050SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
11.31-07-201811+100SRMD Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
12.31-07-201811+350SRMD,Slip due to heavy rainMukesh KumarJEUDRP R&B Bageshwar See Pic
13.30-07-2018Ch 8.200Road surface after pc and crash barrierJagdish Narayan Meenaunknownunknown See Pic
14.30-07-2018Ch 8.200Road surface after pc and crash barrierJagdish Narayan Meenaunknownunknown See Pic
15.30-07-2018Ch 8.220HP bend with crash barrier and pucca drainJagdish Narayan Meenaunknownunknown See Pic
16.30-07-2018Ch 8.250HP bend with crash barrier and pucca drainJagdish Narayan Meenaunknownunknown See Pic
17.30-07-2018Ch 10.220SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
18.30-07-2018Ch 11.000SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
19.30-07-2018Ch 11.050SRMD, slip due to heavy rain.Jagdish Narayan Meenaunknownunknown See Pic
20.30-07-2018Ch 10.790Surface after PC and parapetJagdish Narayan Meenaunknownunknown See Pic