Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Okadi Ana Lohar Chada Gairlekh MR Phase2 (Ch-6 to 12 Km) Agreement signed
Project: UDRP-RB UID: 1144 Sanction Cost: 565.24  lakh Length: 6.000 KM.
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 144        Package Name:  UDRP/PWD/08/RD/128        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/128      Contractor Name: Vinod Kumar Chauhan
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 52572926.3 (525.73 lakh)       
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: 91 days remained       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.99 KM10.9921-11-201731-03-20180.99 KM0.99 KM2.1610.99
2.R/Wall, B/ Wall Type Protection works631.00 m45.2921-11-201730-04-2018631.00 m631.00 m8.9145.29
3.G-25.90 KM81.5115-12-201730-04-20185.90 KM5.90 KM16.0481.51
4.G-35.90 KM47.0601-01-201815-05-20185.90 KM5.90 KM9.2647.06
5.PC/CC i/c Prime Coat, Tack Coat5.90 KM77.1510-05-201830-10-20185.90 KM5.75 KM14.875.19
6.Cause Way2.00 No4.4421-11-201710-05-20182.00 No2.00 No0.874.44
7.Culverts/Scupper 26.00 No73.3821-11-201731-05-201826.00 No26.00 No14.4473.38
8.longitudinal Drain5.90 m103.0515-12-201731-08-20185.90 m5.90 m20.28103.05
9.Crash Barrier907.00 m43.7001-05-201830-05-2018908.00 m908.00 m8.643.70
10.Parapet400.00 No11.8001-05-201830-05-2018468.00 No468.00 No2.3211.80
11.Road Furniture385.00 No3.7501-11-201815-02-2019385.00 No2.00 No00.02
12.Env. Man & Moni Plan1.00 Job5.9921-11-201720-02-20191.00 Job0.00 Job00.00
Total Amount: 508.11 97.7   496.43
Remarks: No Remarks       Work Program Made On: 04-01-2018        Updation of work program on: 18-05-2018       
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.19-December-201765.00  lakh
2.16-February-2018143.16  lakh
3.26-March-2018138.03  lakh
4.28-May-201889.18  lakh
Total 435.37  lakh
% Payment 82.8 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 490   No. of Test Done : 507    No. of Test Passed : 495   No. of Test Failed : 12   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.27
Number of Notice(s) issued: 11

Mobile Pic Upload

Number of Pics Available on Web Repository: 123
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.06-06-20186+230Shuttering for pucca drainMukesh KumarJEUDRP R&B Bageshwar See Pic
2.06-06-20188+180Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
3.06-06-20188+285Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
4.06-06-20188+300Pc laying work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
5.06-06-20188+800Hectometer stone castingMukesh KumarJEUDRP R&B Bageshwar See Pic
6.06-06-20186+250Pucca drain work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
7.06-06-20187+650Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
8.06-06-20187+700Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
9.06-06-20187+785Pc surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
10.06-06-20187+885Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
11.06-06-20187+300Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
12.06-06-20187+265Pc laying & rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
13.06-06-20186+090Pucca drain (M10 ) casting work in progressMukesh KumarJEUDRP R&B Bageshwar See Pic
14.06-06-20187+220Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
15.06-06-20188+890PC surface,pucca drain, parapet, causewayMukesh KumarJEUDRP R&B Bageshwar See Pic
16.06-06-20188+900Seal coat rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
17.06-06-20188+900Seal coat over PC surfaceMukesh KumarJEUDRP R&B Bageshwar See Pic
18.06-06-20189+430Tack coat before pcMukesh KumarJEUDRP R&B Bageshwar See Pic
19.06-06-20189+450Pc surface rollingMukesh KumarJEUDRP R&B Bageshwar See Pic
20.24-05-201811+550Check paper work related to progress by world Bank teamMukesh KumarJEUDRP R&B Bageshwar See Pic