Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) Agreement signed
Project: UDRP-RB UID: 1143 Sanction Cost: 1095.89  lakh Length: 13.000 KM.
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 143        Package Name:  UDRP/PWD/08/RD/127        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/127      Contractor Name: Tomar Construction Company
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 87931448.3 (879.31 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 4660396 for 106 days        LD Analysis for Milestone2: calculated LD is Rs 1099150 for 25 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence9.93 KM117.9321-11-201730-08-20189.93 KM8.13 KM10.9896.55
2.R/Wall, B/ Wall Type Protection works219.00 m46.6521-11-201730-12-2018219.00 m219.00 m5.3146.65
3.G-23.80 KM53.8001-06-201830-08-20183.10 KM2.60 KM5.1345.12
4.G-33.80 KM33.2910-06-201815-10-20183.10 KM0.05 KM0.060.54
5.PC/CC i/c Prime Coat, Tack Coat15.46 KM170.9915-09-201830-11-201815.46 KM1.00 KM1.2611.06
6.Cause Way4.00 No18.9720-05-201820-12-201818.00 No5.00 No0.65.27
7.Culverts/Scupper 68.00 No151.8920-05-201820-08-201836.00 No26.00 No12.48109.69
8.longitudinal Drain15455.00 m149.8420-06-201820-02-201915455.00 m5000.00 m5.5148.47
9.Crash Barrier1160.00 m29.0001-10-201830-01-20191160.00 m0.00 m00.00
10.Parapet780.00 No39.4101-07-201830-01-2019780.00 No320.00 No1.8416.17
11.Road Furniture613.00 No8.9801-11-201820-02-2019613.00 No1.00 No00.01
12.Env. Man & Moni Plan1.00 Job6.8021-11-201720-02-20191.00 Job0.00 Job00.00
13.Other Allied Works & Finishing Work 1.00 Job51.7801-05-201820-02-20191.00 Job0.00 Job00.00
Total Amount: 879.33 43.16   379.53
Remarks: No Remarks       Work Program Made On: 01-05-2018        Updation of work program on: 18-05-2018       
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.08-March-201867.85  lakh
2.28-April-201836.44  lakh
3.07-August-201872.21  lakh
4.01-September-201839.98  lakh
5.29-September-201850.70  lakh
Total 267.18  lakh
% Payment 30.39 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 234   No. of Test Done : 246    No. of Test Passed : 242   No. of Test Failed : 4   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.80
Number of Notice(s) issued: 12

Mobile Pic Upload

Number of Pics Available on Web Repository: 110
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.11-10-2018Ch 9.475HS cutting in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
2.11-10-2018Ch 3.020Kutcha drain in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
3.09-10-2018Ch 9.450HS cutting in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
4.09-10-2018Ch 10.125Existing road surface cleaning for PCJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
5.09-10-2018Ch 9.475HS cutting in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
6.09-10-2018Ch 3.700Slip clearanceJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
7.07-10-20180.595Parapets castingHarish ChandraJEUDRP R&B Bageshwar See Pic
8.07-10-201813.100Slided zone protection workHarish ChandraJEUDRP R&B Bageshwar See Pic
9.07-10-201815.035G2 rollingHarish ChandraJEUDRP R&B Bageshwar See Pic
10.07-10-20189.575Sleep clearenceHarish ChandraJEUDRP R&B Bageshwar See Pic
11.07-10-20180.290ParapetsHarish ChandraJEUDRP R&B Bageshwar See Pic
12.07-10-20180.380Wire createHarish ChandraJEUDRP R&B Bageshwar See Pic
13.07-10-201815.375Wing wall scHarish ChandraJEUDRP R&B Bageshwar See Pic
14.07-10-20181.025Ex for wire createHarish ChandraJEUDRP R&B Bageshwar See Pic
15.26-09-2018Ch 2.025Parapet constructionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
16.26-09-2018Ch 8.425Defect cutting in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
17.26-09-2018Ch 8.425HS cutting in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
18.26-09-2018Ch 15.375Scupper wind wall in progressJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
19.26-09-2018Ch 1.025CausewayJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
20.26-09-2018Ch 1.025wire create for protection of debris.Jagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic