Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Katpudiya Chhina Seraghat MR (Ch-0 to 13 Km) Agreement signed
Project: UDRP-RB UID: 1143 Sanction Cost: 1095.89  lakh Length: 13.000 KM.
District: Bageshwar Block: 0074 Constituency: 46 Circle:
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 143        Package Name:  UDRP/PWD/08/RD/127        Tender Date: 07-04-2017        Current Status: Agreement signed        Achieved on Date: 14-11-2017

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/RD/127      Contractor Name: Tomar Construction Company
Start Date:  21-11-2017      Intended Completion Date:  20-02-2019     
Total Bond Cost: 87931448.3 (879.31 lakh)       
LD Analysis for Milestone1: calculated LD is Rs 3956940 for 90 days        LD Analysis for Milestone2: 62 days remained       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence9.93 KM117.9321-11-201730-08-20189.93 KM6.75 KM9.1280.16
2.R/Wall, B/ Wall Type Protection works219.00 m46.6521-11-201730-12-2018219.00 m152.00 m3.6832.38
3.G-23.80 KM53.8001-06-201830-08-20183.80 KM1.15 KM1.8516.28
4.G-33.80 KM33.2910-06-201815-10-20183.80 KM0.00 KM00.00
5.PC/CC i/c Prime Coat, Tack Coat15.46 KM170.9915-09-201830-11-201815.46 KM0.00 KM00.00
6.Cause Way4.00 No18.9720-05-201820-12-20184.00 No2.00 No1.089.48
7.Culverts/Scupper 68.00 No151.8920-05-201820-08-201868.00 No21.00 No5.3346.90
8.longitudinal Drain15455.00 m149.8420-06-201820-02-201915455.00 m600.00 m0.665.81
9.Crash Barrier1160.00 m29.0001-10-201830-01-20191160.00 m0.00 m00.00
10.Parapet780.00 No39.4101-07-201830-01-2019780.00 No0.00 No00.00
11.Road Furniture613.00 No8.9801-11-201820-02-2019613.00 No1.00 No00.01
12.Env. Man & Moni Plan1.00 Job6.8021-11-201720-02-20191.00 Job0.00 Job00.00
13.Other Allied Works & Finishing Work 1.00 Job51.7801-05-201820-02-20191.00 Job0.00 Job00.00
Total Amount: 879.33 21.73   191.02
Remarks: No Remarks       Work Program Made On: 01-05-2018        Updation of work program on: 18-05-2018       
Work Program Status:Work Programme workable.
Financial Progress
SNo. Date Payment
1.08-March-201867.85  lakh
2.28-April-201836.44  lakh
Total 104.29  lakh
% Payment 11.86 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill should be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 154   No. of Test Done : 162    No. of Test Passed : 158   No. of Test Failed : 4   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.25
Number of Notice(s) issued: 12

Mobile Pic Upload

Number of Pics Available on Web Repository: 80
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.19-07-2018Ch 5.650EE sir nainital and EE Sir bageshwar inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
2.19-07-2018Ch 5.900Discussion for 3 mtr span culvertJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
3.19-07-2018Ch 5.900EE sir nainital and EE sir bageshwar inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
4.19-07-2018Ch 9.550EE sir nainital and EE Sir bageshwar inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
5.19-07-2018Ch 3.625SE sir inspectionJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
6.19-07-2018Ch 0.375Slab reinforcementJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
7.19-07-2018Ch 2.350Steel Reinforcement for 1 mtr span culvertJagdish Narayan MeenaAEUDRP R&B Bageshwar See Pic
8.07-06-20180.375Before casrting steel in slabHarish ChandraJEUDRP R&B Bageshwar See Pic
9.07-06-20180/12Casting slabHarish ChandraJEUDRP R&B Bageshwar See Pic
10.07-06-20181/2Ecv. Of causewayHarish ChandraJEUDRP R&B Bageshwar See Pic
11.07-06-201813.675Hill cuttingHarish ChandraJEUDRP R&B Bageshwar See Pic
12.07-06-20187/5Scupper Slab castingHarish ChandraJEUDRP R&B Bageshwar See Pic
13.25-05-20185.900Discuss about 3mt. Span culvert with contractorHarish ChandraJEUDRP R&B Bageshwar See Pic
14.25-05-201815.500Lowring workHarish ChandraJEUDRP R&B Bageshwar See Pic
15.25-05-20180.000Starting pointHarish ChandraJEUDRP R&B Bageshwar See Pic
16.25-05-201814.900Cutting/lowring and filling workHarish ChandraJEUDRP R&B Bageshwar See Pic
17.25-05-201814/14Cutting / lowring workHarish ChandraJEUDRP R&B Bageshwar See Pic
18.25-05-2018Health checkup of construction team pkg 127Harish ChandraJEUDRP R&B Bageshwar See Pic
19.25-05-20183.625Dry stone kharanjaHarish ChandraJEUDRP R&B Bageshwar See Pic
20.25-05-20180.475Scupper abutment masonryHarish ChandraJEUDRP R&B Bageshwar See Pic