Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kapkot- Tehsil-Poling MR Phase2 Work Completed
Project: UDRP-RB UID: 1142 Sanction Cost: 428.93  lakh Length: 5.250 KM.
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 111        Package Name:  UDRP/PWD/08/06/RD/100        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/100      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  01-10-2015      Intended Completion Date:  23-02-2018      Original End Date:  30-12-2016
Total Bond Cost: 122411658.74 (1224.12 lakh)        Variation Cost: 12988043.64 (129.88 lakh)    Hence Total Bond Cost is   135399702.38 (1354 lakh) 
Sub Project Cost: 394.13  lakh        Variation Cost of Sub Project: 1139443.75  (11.39 lakh)       Total Sub Project Cost:   405.52 lakh
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days        LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.11 KM40.1803-10-201510-05-20171.11 KM1.11 KM9.2640.18
2.R/Wall, B/ Wall Type Protection works1744.00 m159.6001-11-201525-10-20171744.00 m1744.00 m36.76159.60
3.GSB/RBI/G-13.25 KM27.1301-02-201615-10-20173.25 KM3.25 KM6.2527.13
4.G-22.45 KM12.9915-01-201715-10-20172.45 KM2.45 KM2.9912.99
5.G-32.45 KM18.0101-04-201615-10-20172.45 KM2.45 KM4.1518.01
6.PC/CC i/c Prime Coat, Tack Coat3.25 KM71.3401-03-201615-11-20173.25 KM3.25 KM16.4371.34
7.Cause Way3.00 No0.4801-06-201615-05-20173.00 No3.00 No0.110.48
8.Culverts/Scupper 13.00 No32.8501-11-201530-04-201713.00 No13.00 No7.5732.85
9.longitudinal Drain2773.00 m39.0801-01-201615-11-20172773.00 m2773.00 m939.08
10.Crash Barrier273.00 m8.6301-01-201715-11-2017273.00 m273.00 m1.998.63
11.Parapet65.00 No10.3101-10-201615-11-201765.00 No65.00 No2.3810.31
12.Road Furniture182.00 No2.2401-11-201615-11-2017182.00 No182.00 No0.522.24
13.Other Allied Works & Finishing Work 11.50 Job11.3507-01-201615-11-20172.50 Job2.50 Job2.6211.35
Total Amount: 434.19 100   434.19
Remarks: No Remarks       Work Program Made On: 31-10-2015        Updation of work program on: 25-10-2018       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-January-201620.57  lakh
2.27-January-201631.65  lakh
3.03-March-201620.44  lakh
4.29-March-201640.53  lakh
5.31-May-201637.40  lakh
6.11-July-201616.12  lakh
7.30-August-20164.56  lakh
8.24-October-20160.75  lakh
9.23-December-20160.28  lakh
10.03-January-201723.82  lakh
11.08-March-201754.98  lakh
12.31-March-201742.98  lakh
13.30-June-201748.60  lakh
14.16-October-201727.78  lakh
15.15-December-201736.57  lakh
16.23-March-201819.22  lakh
17.18-August-201814.56  lakh
18.16-November-20184.98  lakh
Total 445.79  lakh
% Payment109.93 %
Advance Amount:  534.52  lakh        Recovered Amount:  534.52  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1850   No. of Test Done : 1877    No. of Test Passed : 1838   No. of Test Failed : 39   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.74
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 100
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-07-2017Ch 2.360SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
2.15-07-2017Ch 2.600SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
3.15-07-2017Ch 4.100SRMD, slip but road open for traffic.Jagdish Narayan Meenaunknownunknown See Pic
4.15-07-2017Ch 4.150SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
5.15-07-2017Ch 4.200SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
6.15-07-2017Ch 4.300SRMD, slip clearanceJagdish Narayan Meenaunknownunknown See Pic
7.15-07-2017Ch 4.300SRMD, slip clearance by JCBJagdish Narayan Meenaunknownunknown See Pic
8.15-07-2017Ch 4.300SRMD, slip due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
9.15-07-2017Ch 5.200SRMD, sinking due to heavy rain.Jagdish Narayan Meenaunknownunknown See Pic
10.15-07-2017Ch 4.100SRMD , slide due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
11.08-06-2017Ch 2.400Instructions given by world bank missionJagdish Narayan Meenaunknownunknown See Pic
12.25-05-2017HMPPC work startedManoj BhattREDSC2 R&B WB Pauri See Pic
13.19-05-20175+100G3 rectifiedMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
14.19-05-20170+010World bank visitMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
15.18-05-2017Ch 3+450Rejected EmulsionSanjay SinghSite SupervisorDSC5 R&B WB Bageshwar See Pic
16.16-05-20175+100Rectification on defected WBM G3 surfaceManoj BhattREDSC2 R&B WB Pauri See Pic
17.16-05-20175+100Rectification on WBM Gr3Manoj BhattREDSC2 R&B WB Pauri See Pic
18.16-05-2017Ch 2.950Instructions given by world bank missionJagdish Narayan Meenaunknownunknown See Pic
19.16-05-2017Ch 2.720World bank inspectionJagdish Narayan Meenaunknownunknown See Pic
20.16-05-20172.700World bank inspectionJagdish Narayan Meenaunknownunknown See Pic