Kapkot- Tehsil-Poling MR Phase2
Work Completed
|
Project: |
UDRP-RB |
UID: |
1142 |
Sanction Cost: |
428.93 lakh |
Length:
|
5.250 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 111
Package Name: 
UDRP/PWD/08/06/RD/100
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/100
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 01-10-2015
Intended Completion Date: 23-02-2018
Original End Date: 30-12-2016 |
Total Bond Cost: 122411658.74 (1224.12 lakh)
Variation Cost: 12988043.64 (129.88 lakh) Hence Total Bond Cost is 135399702.38 (1354 lakh)
|
Sub Project Cost: 394.13 lakh
Variation Cost of Sub Project: 1139443.75 (11.39 lakh)
Total Sub Project Cost:
405.52 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days
LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.11 KM | 40.18 | 03-10-2015 | 10-05-2017 | 1.11 KM | 1.11 KM | 9.26 | 40.18 | 2. | R/Wall, B/ Wall Type Protection works | 1744.00 m | 159.60 | 01-11-2015 | 25-10-2017 | 1744.00 m | 1744.00 m | 36.76 | 159.60 | 3. | GSB/RBI/G-1 | 3.25 KM | 27.13 | 01-02-2016 | 15-10-2017 | 3.25 KM | 3.25 KM | 6.25 | 27.13 | 4. | G-2 | 2.45 KM | 12.99 | 15-01-2017 | 15-10-2017 | 2.45 KM | 2.45 KM | 2.99 | 12.99 | 5. | G-3 | 2.45 KM | 18.01 | 01-04-2016 | 15-10-2017 | 2.45 KM | 2.45 KM | 4.15 | 18.01 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.25 KM | 71.34 | 01-03-2016 | 15-11-2017 | 3.25 KM | 3.25 KM | 16.43 | 71.34 | 7. | Cause Way | 3.00 No | 0.48 | 01-06-2016 | 15-05-2017 | 3.00 No | 3.00 No | 0.11 | 0.48 | 8. | Culverts/Scupper | 13.00 No | 32.85 | 01-11-2015 | 30-04-2017 | 13.00 No | 13.00 No | 7.57 | 32.85 | 9. | longitudinal Drain | 2773.00 m | 39.08 | 01-01-2016 | 15-11-2017 | 2773.00 m | 2773.00 m | 9 | 39.08 | 10. | Crash Barrier | 273.00 m | 8.63 | 01-01-2017 | 15-11-2017 | 273.00 m | 273.00 m | 1.99 | 8.63 | 11. | Parapet | 65.00 No | 10.31 | 01-10-2016 | 15-11-2017 | 65.00 No | 65.00 No | 2.38 | 10.31 | 12. | Road Furniture | 182.00 No | 2.24 | 01-11-2016 | 15-11-2017 | 182.00 No | 182.00 No | 0.52 | 2.24 | 13. | Other Allied Works & Finishing Work | 11.50 Job | 11.35 | 07-01-2016 | 15-11-2017 | 2.50 Job | 2.50 Job | 2.62 | 11.35 |
Total Amount: |
434.19 |
|
100 |
434.19 |
|
Remarks:
No Remarks
Work Program Made On:
31-10-2015 } ?>
Updation of work program on:
25-10-2018
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-January-2016 | 20.57 lakh | 2. | 27-January-2016 | 31.65 lakh | 3. | 03-March-2016 | 20.44 lakh | 4. | 29-March-2016 | 40.53 lakh | 5. | 31-May-2016 | 37.40 lakh | 6. | 11-July-2016 | 16.12 lakh | 7. | 30-August-2016 | 4.56 lakh | 8. | 24-October-2016 | 0.75 lakh | 9. | 23-December-2016 | 0.28 lakh | 10. | 03-January-2017 | 23.82 lakh | 11. | 08-March-2017 | 54.98 lakh | 12. | 31-March-2017 | 42.98 lakh | 13. | 30-June-2017 | 48.60 lakh | 14. | 16-October-2017 | 27.78 lakh | 15. | 15-December-2017 | 36.57 lakh | 16. | 23-March-2018 | 19.22 lakh | 17. | 18-August-2018 | 14.56 lakh | 18. | 16-November-2018 | 4.98 lakh |
Total |
445.79 lakh |
% Payment | 109.93 % |
|
Advance Amount: 534.52 lakh
Recovered Amount: 534.52 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1850 No. of Test Done : 1877 No. of Test Passed : 1838 No. of Test Failed : 39 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.74 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 100 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-07-2017 | Ch 2.360 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 15-07-2017 | Ch 2.600 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 15-07-2017 | Ch 4.100 | SRMD, slip but road open for traffic. | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 15-07-2017 | Ch 4.150 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 15-07-2017 | Ch 4.200 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 15-07-2017 | Ch 4.300 | SRMD, slip clearance | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 15-07-2017 | Ch 4.300 | SRMD, slip clearance by JCB | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 15-07-2017 | Ch 4.300 | SRMD, slip due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 15-07-2017 | Ch 5.200 | SRMD, sinking due to heavy rain. | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 15-07-2017 | Ch 4.100 | SRMD , slide due to heavy rain | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 08-06-2017 | Ch 2.400 | Instructions given by world bank mission | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 25-05-2017 | HMP | PC work started | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
13. | 19-05-2017 | 5+100 | G3 rectified | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
14. | 19-05-2017 | 0+010 | World bank visit | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
15. | 18-05-2017 | Ch 3+450 | Rejected Emulsion | Sanjay Singh | Site Supervisor | DSC5 R&B WB Bageshwar | See Pic |
16. | 16-05-2017 | 5+100 | Rectification on defected WBM G3 surface | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
17. | 16-05-2017 | 5+100 | Rectification on WBM Gr3 | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
18. | 16-05-2017 | Ch 2.950 | Instructions given by world bank mission | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 16-05-2017 | Ch 2.720 | World bank inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 16-05-2017 | 2.700 | World bank inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|