Aso Bedapakhar Okhaldhar MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1141 |
Sanction Cost: |
482.56 lakh |
Length:
|
6.300 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 111
Package Name: 
UDRP/PWD/08/06/RD/100
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/100
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 01-10-2015
Intended Completion Date: 23-02-2018
Original End Date: 30-12-2016 |
Total Bond Cost: 122411658.74 (1224.12 lakh)
Variation Cost: 12988043.64 (129.88 lakh) Hence Total Bond Cost is 135399702.38 (1354 lakh)
|
Sub Project Cost: 448.92 lakh
Variation Cost of Sub Project: 930785.69 (9.31 lakh)
Total Sub Project Cost:
458.23 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days
LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.20 KM | 41.59 | 03-10-2015 | 30-04-2017 | 1.28 KM | 1.28 KM | 9.45 | 41.59 | 2. | R/Wall, B/ Wall Type Protection works | 790.00 m | 101.33 | 01-11-2015 | 30-08-2017 | 1419.00 m | 1419.00 m | 23.04 | 101.33 | 3. | GSB/RBI/G-1 | 4.22 KM | 48.19 | 01-02-2016 | 30-05-2017 | 4.22 KM | 4.22 KM | 10.95 | 48.19 | 4. | G-2 | 2.50 KM | 16.20 | 01-05-2017 | 30-07-2017 | 2.50 KM | 2.50 KM | 3.68 | 16.20 | 5. | G-3 | 6.28 KM | 49.60 | 01-04-2016 | 25-09-2017 | 5.28 KM | 5.28 KM | 11.28 | 49.60 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.28 KM | 71.72 | 08-05-2017 | 15-11-2017 | 6.28 KM | 6.28 KM | 16.31 | 71.72 | 7. | Cause Way | 6.00 No | 17.39 | 01-06-2016 | 30-04-2017 | 6.00 No | 6.00 No | 3.95 | 17.39 | 8. | Culverts/Scupper | 15.00 No | 37.05 | 01-01-2016 | 15-05-2017 | 8.00 No | 8.00 No | 8.42 | 37.05 | 9. | longitudinal Drain | 5800.00 m | 19.16 | 01-01-2016 | 15-11-2017 | 5800.00 m | 5800.00 m | 4.36 | 19.16 | 10. | Crash Barrier | 400.00 m | 12.34 | 04-01-2017 | 30-10-2017 | 470.00 m | 470.00 m | 2.81 | 12.34 | 11. | Parapet | 120.00 No | 3.65 | 12-10-2016 | 30-10-2017 | 100.00 No | 100.00 No | 0.83 | 3.65 | 12. | Road Furniture | 536.00 No | 5.04 | 01-11-2016 | 15-11-2017 | 225.00 No | 225.00 No | 1.15 | 5.04 | 13. | Other Allied Works & Finishing Work | 5.00 Job | 16.62 | 01-07-2016 | 15-11-2017 | 5.00 Job | 5.00 Job | 3.78 | 16.62 |
Total Amount: |
439.88 |
|
100 |
439.88 |
|
Remarks:
No Remarks
Work Program Made On:
31-10-2015 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-January-2016 | 4.11 lakh | 2. | 27-January-2016 | 45.66 lakh | 3. | 03-March-2016 | 26.22 lakh | 4. | 29-March-2016 | 36.76 lakh | 5. | 31-May-2016 | 34.47 lakh | 6. | 11-July-2016 | 22.88 lakh | 7. | 30-August-2016 | 10.84 lakh | 8. | 24-October-2016 | 0.93 lakh | 9. | 23-December-2016 | 1.13 lakh | 10. | 03-January-2017 | 57.15 lakh | 11. | 08-March-2017 | 41.20 lakh | 12. | 31-March-2017 | 17.11 lakh | 13. | 30-June-2017 | 43.61 lakh | 14. | 16-October-2017 | 54.23 lakh | 15. | 15-December-2017 | 20.20 lakh | 16. | 23-March-2018 | 20.79 lakh | 17. | 18-August-2018 | 31.95 lakh | 18. | 16-November-2018 | 4.19 lakh |
Total |
473.43 lakh |
% Payment | 103.32 % |
|
Advance Amount: 534.52 lakh
Recovered Amount: 534.52 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1850 No. of Test Done : 1877 No. of Test Passed : 1838 No. of Test Failed : 39 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.18 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 77 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 16-06-2017 | 6+280 | Caution tape and safety sign board during the work | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
2. | 16-06-2017 | 3+525 | WBM Grading-3 in Progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
3. | 07-06-2017 | 6+260 | PC stoped due to rain | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
4. | 04-05-2017 | Ch 0+050 | Perapit white wash | Sanjay Singh | Site Supervisor | DSC5 R&B WB Bageshwar | See Pic |
5. | 28-04-2017 | Ch 4.200 | Wire creates for protection | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 28-04-2017 | Ch 4.200 | Cleaning of G3 surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 28-04-2017 | Ch 4.450 | Culvert with wing wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 28-04-2017 | Ch 4.900 | After cleaning Surface , required more compaction. | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 28-04-2017 | Ch 6.270 | Coolie wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 28-04-2017 | Ch 6.250 | Surface ready for PC | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 31-03-2017 | Ch 3+900 | Surface prepared for pc work | Naresh Mittal | TL | DSC5 R&B WB Bageshwar | See Pic |
12. | 02-12-2016 | Ch 3.300 | Water sprinkling | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 02-12-2016 | Ch 1.000 | Dismantling of parapet due to poor quality and no vibrator use. | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 02-12-2016 | Ch 1.000 | Parapet reject and dismantling due to poor quality and no vibrator use. | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 13-11-2016 | Ch 1.980 | B/wall complete | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 13-11-2016 | Ch 4.450 | 1 m span Slab culvert reinforcement. | Jagdish Narayan Meena | unknown | unknown | See Pic |
17. | 21-10-2016 | Ch 6.250 | Inspection by EE sir and TL DSC 05 | Jagdish Narayan Meena | unknown | unknown | See Pic |
18. | 21-10-2016 | Ch 0.500 | Site inspection by EE sir and TL sir | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 21-10-2016 | 5+475 | Discussion with contactor for construction of Culvert one or two m span | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 21-10-2016 | 1+350 | Toe Wall constructed seen quality satisfactory | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|