Dyuni Sukanda MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1140 |
Sanction Cost: |
489.24 lakh |
Length:
|
5.000 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 111
Package Name: 
UDRP/PWD/08/06/RD/100
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/100
Contractor Name: Woodhill Infrastructure Ltd
|
Start Date: 01-10-2015
Intended Completion Date: 23-02-2018
Original End Date: 30-12-2016 |
Total Bond Cost: 122411658.74 (1224.12 lakh)
Variation Cost: 12988043.64 (129.88 lakh) Hence Total Bond Cost is 135399702.38 (1354 lakh)
|
Sub Project Cost: 340.98 lakh
Variation Cost of Sub Project: 10917814.20 (109.18 lakh)
Total Sub Project Cost:
450.16 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days
LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.25 KM | 32.89 | 03-10-2015 | 25-05-2017 | 1.25 KM | 1.25 KM | 7.81 | 32.89 | 2. | R/Wall, B/ Wall Type Protection works | 940.00 m | 108.78 | 01-11-2015 | 15-11-2017 | 1377.00 m | 1377.00 m | 25.83 | 108.78 | 3. | GSB/RBI/G-1 | 2.44 KM | 31.03 | 01-02-2016 | 30-05-2017 | 2.36 KM | 2.36 KM | 7.37 | 31.03 | 4. | G-2 | 4.60 KM | 28.79 | 15-11-2016 | 12-11-2017 | 2.44 KM | 2.44 KM | 6.84 | 28.79 | 5. | G-3 | 4.80 KM | 38.78 | 01-04-2016 | 12-11-2017 | 4.80 KM | 4.80 KM | 9.21 | 38.78 | 6. | PC/CC i/c Prime Coat, Tack Coat | 4.80 KM | 55.21 | 01-06-2017 | 15-11-2017 | 4.80 KM | 4.80 KM | 13.11 | 55.21 | 7. | Cause Way | 6.00 No | 31.15 | 01-01-2016 | 15-11-2017 | 5.00 No | 5.00 No | 7.4 | 31.15 | 8. | Culverts/Scupper | 10.00 No | 41.25 | 01-01-2016 | 20-05-2017 | 7.00 No | 7.00 No | 9.8 | 41.25 | 9. | longitudinal Drain | 4700.00 m | 18.02 | 01-01-2016 | 15-11-2017 | 4700.00 m | 4700.00 m | 4.28 | 18.02 | 10. | Crash Barrier | 296.00 m | 9.12 | 01-06-2017 | 15-11-2017 | 800.00 m | 800.00 m | 2.17 | 9.12 | 11. | Parapet | 200.00 No | 6.08 | 01-01-2017 | 15-11-2017 | 269.00 No | 269.00 No | 1.45 | 6.08 | 12. | Road Furniture | 81.00 No | 1.60 | 10-03-2017 | 15-11-2017 | 450.00 No | 450.00 No | 0.38 | 1.60 | 13. | Other Allied Works & Finishing Work | 6.00 Job | 18.40 | 01-07-2016 | 15-11-2017 | 6.00 Job | 6.00 Job | 4.37 | 18.40 |
Total Amount: |
421.1 |
|
100 |
421.1 |
|
Remarks:
No Remarks
Work Program Made On:
31-10-2015 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 04-January-2016 | 19.04 lakh | 2. | 27-January-2016 | 24.31 lakh | 3. | 03-March-2016 | 32.57 lakh | 4. | 29-March-2016 | 37.62 lakh | 5. | 31-May-2016 | 12.56 lakh | 6. | 11-July-2016 | 55.77 lakh | 7. | 30-August-2016 | 0.60 lakh | 8. | 24-October-2016 | 1.88 lakh | 9. | 08-December-2016 | 0.69 lakh | 10. | 23-December-2016 | 0.63 lakh | 11. | 31-March-2017 | 20.22 lakh | 12. | 30-June-2017 | 43.50 lakh | 13. | 16-October-2017 | 29.62 lakh | 14. | 24-November-2017 | 28.86 lakh | 15. | 15-December-2017 | 64.12 lakh | 16. | 23-March-2018 | 60.22 lakh | 17. | 18-August-2018 | 12.47 lakh | 18. | 16-November-2018 | 6.31 lakh |
Total |
450.99 lakh |
% Payment | 100.18 % |
|
Advance Amount: 534.52 lakh
Recovered Amount: 534.52 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1850 No. of Test Done : 1877 No. of Test Passed : 1838 No. of Test Failed : 39 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.97 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 73 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-05-2017 | Labour camp | Labour camp | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
2. | 05-05-2017 | 0+065 | Social Expert asking views of Road Users during construction. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
3. | 05-05-2017 | 0+070 | Social Experts Discussing to labours about importance of their safety. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
4. | 04-05-2017 | Ch 0+200 | WBM (g-3) laying | Sanjay Singh | Site Supervisor | DSC5 R&B WB Bageshwar | See Pic |
5. | 29-04-2017 | 0+650 | Stone collection for G2 | Sanjay Singh | Site Supervisor | DSC5 R&B WB Bageshwar | See Pic |
6. | 28-04-2017 | Ch 1.000 | Plum protecting work and R/wall at sinking area | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 28-04-2017 | Ch 0.975 | Breaking of Greading no 2 stones | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 28-04-2017 | Ch 0.150 | G 2 surface first layer and stone collection | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 31-03-2017 | Ch 0+500 | Public consultation | Naresh Mittal | TL | DSC5 R&B WB Bageshwar | See Pic |
10. | 27-01-2017 | 0+000 | Environmental Training to site engineers and supervisors by environmental and safety expert | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
11. | 27-01-2017 | 0+000 | Safety and environmental training to supervisor,s and engineers by expert | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
12. | 30-12-2016 | Ch-0+975 | Measurement of R/Wall cheked by RE | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
13. | 19-11-2016 | Pkg 100 lab site | Gradation test of G3 material in presence of CE sir almora | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 19-11-2016 | At lab pkg 100 | Gradation test of G3 material in presence of CE sir PWD almora. | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 21-10-2016 | Ch- 3+300 to 3+700 | WBM GR 3 rejected, because Base course RBI-81 all ready rejected | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
16. | 15-09-2016 | Ch 4.300 | Meeting with villagers for making culvert | Jagdish Narayan Meena | unknown | unknown | See Pic |
17. | 28-07-2016 | Ch 3.550 | RBI grade 81 Greadation test | Jagdish Narayan Meena | unknown | unknown | See Pic |
18. | 28-07-2016 | Ch 3.450 | Greadation test of RBI grade 81 | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 28-07-2016 | Ch 3.450 | Greading test of RBI grade 81 | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 25-07-2016 | Ch 0.975 | Road open for traffic | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|