Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dyuni Sukanda MR Work Completed
Project: UDRP-RB UID: 1140 Sanction Cost: 489.24  lakh Length: 5.000 KM.
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 111        Package Name:  UDRP/PWD/08/06/RD/100        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/100      Contractor Name: Woodhill Infrastructure Ltd
Start Date:  01-10-2015      Intended Completion Date:  23-02-2018      Original End Date:  30-12-2016
Total Bond Cost: 122411658.74 (1224.12 lakh)        Variation Cost: 12988043.64 (129.88 lakh)    Hence Total Bond Cost is   135399702.38 (1354 lakh) 
Sub Project Cost: 340.98  lakh        Variation Cost of Sub Project: 10917814.20  (109.18 lakh)       Total Sub Project Cost:   450.16 lakh
LD Analysis for Milestone1: calculated LD is Rs 306030 for 5 days        LD Analysis for Milestone2: calculated LD is Rs 9303312 for 152 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.25 KM32.8903-10-201525-05-20171.25 KM1.25 KM7.8132.89
2.R/Wall, B/ Wall Type Protection works940.00 m108.7801-11-201515-11-20171377.00 m1377.00 m25.83108.78
3.GSB/RBI/G-12.44 KM31.0301-02-201630-05-20172.36 KM2.36 KM7.3731.03
4.G-24.60 KM28.7915-11-201612-11-20172.44 KM2.44 KM6.8428.79
5.G-34.80 KM38.7801-04-201612-11-20174.80 KM4.80 KM9.2138.78
6.PC/CC i/c Prime Coat, Tack Coat4.80 KM55.2101-06-201715-11-20174.80 KM4.80 KM13.1155.21
7.Cause Way6.00 No31.1501-01-201615-11-20175.00 No5.00 No7.431.15
8.Culverts/Scupper 10.00 No41.2501-01-201620-05-20177.00 No7.00 No9.841.25
9.longitudinal Drain4700.00 m18.0201-01-201615-11-20174700.00 m4700.00 m4.2818.02
10.Crash Barrier296.00 m9.1201-06-201715-11-2017800.00 m800.00 m2.179.12
11.Parapet200.00 No6.0801-01-201715-11-2017269.00 No269.00 No1.456.08
12.Road Furniture81.00 No1.6010-03-201715-11-2017450.00 No450.00 No0.381.60
13.Other Allied Works & Finishing Work 6.00 Job18.4001-07-201615-11-20176.00 Job6.00 Job4.3718.40
Total Amount: 421.1 100   421.1
Remarks: No Remarks       Work Program Made On: 31-10-2015        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-January-201619.04  lakh
2.27-January-201624.31  lakh
3.03-March-201632.57  lakh
4.29-March-201637.62  lakh
5.31-May-201612.56  lakh
6.11-July-201655.77  lakh
7.30-August-20160.60  lakh
8.24-October-20161.88  lakh
9.08-December-20160.69  lakh
10.23-December-20160.63  lakh
11.31-March-201720.22  lakh
12.30-June-201743.50  lakh
13.16-October-201729.62  lakh
14.24-November-201728.86  lakh
15.15-December-201764.12  lakh
16.23-March-201860.22  lakh
17.18-August-201812.47  lakh
18.16-November-20186.31  lakh
Total 450.99  lakh
% Payment100.18 %
Advance Amount:  534.52  lakh        Recovered Amount:  534.52  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1850   No. of Test Done : 1877    No. of Test Passed : 1838   No. of Test Failed : 39   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.97
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 73
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.05-05-2017Labour campLabour campManoj BhattREDSC2 R&B WB Pauri See Pic
2.05-05-20170+065Social Expert asking views of Road Users during construction.Manoj BhattREDSC2 R&B WB Pauri See Pic
3.05-05-20170+070Social Experts Discussing to labours about importance of their safety.Manoj BhattREDSC2 R&B WB Pauri See Pic
4.04-05-2017Ch 0+200WBM (g-3) layingSanjay SinghSite SupervisorDSC5 R&B WB Bageshwar See Pic
5.29-04-20170+650Stone collection for G2Sanjay SinghSite SupervisorDSC5 R&B WB Bageshwar See Pic
6.28-04-2017Ch 1.000Plum protecting work and R/wall at sinking areaJagdish Narayan Meenaunknownunknown See Pic
7.28-04-2017Ch 0.975Breaking of Greading no 2 stonesJagdish Narayan Meenaunknownunknown See Pic
8.28-04-2017Ch 0.150G 2 surface first layer and stone collectionJagdish Narayan Meenaunknownunknown See Pic
9.31-03-2017Ch 0+500Public consultationNaresh MittalTLDSC5 R&B WB Bageshwar See Pic
10.27-01-20170+000Environmental Training to site engineers and supervisors by environmental and safety expertManoj BhattREDSC5 R&B WB Bageshwar See Pic
11.27-01-20170+000Safety and environmental training to supervisor,s and engineers by expertManoj BhattREDSC5 R&B WB Bageshwar See Pic
12.30-12-2016Ch-0+975Measurement of R/Wall cheked by REMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
13.19-11-2016Pkg 100 lab siteGradation test of G3 material in presence of CE sir almoraJagdish Narayan Meenaunknownunknown See Pic
14.19-11-2016At lab pkg 100Gradation test of G3 material in presence of CE sir PWD almora.Jagdish Narayan Meenaunknownunknown See Pic
15.21-10-2016Ch- 3+300 to 3+700WBM GR 3 rejected, because Base course RBI-81 all ready rejectedMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
16.15-09-2016Ch 4.300Meeting with villagers for making culvertJagdish Narayan Meenaunknownunknown See Pic
17.28-07-2016Ch 3.550RBI grade 81 Greadation testJagdish Narayan Meenaunknownunknown See Pic
18.28-07-2016Ch 3.450Greadation test of RBI grade 81Jagdish Narayan Meenaunknownunknown See Pic
19.28-07-2016Ch 3.450Greading test of RBI grade 81Jagdish Narayan Meenaunknownunknown See Pic
20.25-07-2016Ch 0.975Road open for trafficJagdish Narayan Meenaunknownunknown See Pic