Kandhar Reetha Talla Parkoti Sirkot Patharkhani MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1139 |
Sanction Cost: |
448.58 lakh |
Length:
|
6.000 KM. |
District: |
Bageshwar |
Block: |
Garud |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 110
Package Name: 
UDRP/PWD/08/05/RD/099
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/099
Contractor Name: Anil Malik Contractor
|
Start Date: 01-10-2015
Intended Completion Date: 10-10-2017
Original End Date: 30-12-2016 |
Total Bond Cost: 152575316.91 (1525.75 lakh)
Variation Cost: 4156629.06 (41.57 lakh) Hence Total Bond Cost is 156731945.97 (1567.32 lakh)
|
Sub Project Cost: 442.99 lakh
Variation Cost of Sub Project: -6618399.32 (-66.18 lakh)
Total Sub Project Cost:
376.81 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days
LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.16 KM | 43.72 | 20-10-2015 | 30-06-2017 | 1.16 KM | 1.16 KM | 10.96 | 43.72 | 2. | R/Wall, B/ Wall Type Protection works | 910.00 m | 65.59 | 11-10-2015 | 30-12-2016 | 910.00 m | 910.00 m | 16.44 | 65.59 | 3. | GSB/RBI/G-1 | 4.91 KM | 74.89 | 01-06-2016 | 15-10-2016 | 4.91 KM | 4.91 KM | 18.77 | 74.89 | 4. | G-3 | 4.91 KM | 37.22 | 25-06-2016 | 15-11-2016 | 4.91 KM | 4.91 KM | 9.33 | 37.22 | 5. | PC/CC i/c Prime Coat, Tack Coat | 4.91 KM | 68.66 | 15-09-2016 | 15-11-2016 | 4.91 KM | 4.91 KM | 17.21 | 68.66 | 6. | Culverts/Scupper | 12.00 No | 34.35 | 20-11-2015 | 10-06-2016 | 11.00 No | 11.00 No | 8.61 | 34.35 | 7. | longitudinal Drain | 4754.00 m | 42.47 | 15-12-2015 | 15-11-2016 | 4754.00 m | 4754.00 m | 10.65 | 42.47 | 8. | Crash Barrier | 300.00 m | 7.83 | 16-06-2016 | 15-07-2017 | 300.00 m | 300.00 m | 1.96 | 7.83 | 9. | Parapet | 400.00 No | 11.53 | 16-06-2016 | 15-07-2017 | 400.00 No | 400.00 No | 2.89 | 11.53 | 10. | Road Furniture | 109.00 No | 1.33 | 01-10-2016 | 15-03-2017 | 111.00 No | 111.00 No | 0.33 | 1.33 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 11.33 | 25-05-2016 | 10-08-2017 | 2.00 Job | 2.00 Job | 2.84 | 11.33 |
Total Amount: |
398.92 |
|
100 |
398.92 |
|
Remarks:
No Remarks
Work Program Made On:
21-11-2015 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-February-2016 | 55.66 lakh | 2. | 30-April-2016 | 44.19 lakh | 3. | 28-June-2016 | 36.35 lakh | 4. | 12-August-2016 | 19.82 lakh | 5. | 29-September-2016 | 57.40 lakh | 6. | 22-October-2016 | 83.45 lakh | 7. | 08-December-2016 | 0.16 lakh | 8. | 21-December-2016 | 0.61 lakh | 9. | 13-January-2017 | 9.48 lakh | 10. | 02-February-2017 | 0.06 lakh | 11. | 27-April-2017 | 7.56 lakh | 12. | 21-June-2017 | 7.54 lakh | 13. | 16-October-2017 | 8.33 lakh | 14. | 24-November-2017 | 9.09 lakh | 15. | 16-November-2018 | 0.79 lakh |
Total |
340.49 lakh |
% Payment | 90.36 % |
|
Advance Amount: 625.98 lakh
Recovered Amount: 625.98 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1601 No. of Test Done : 1519 No. of Test Passed : 1463 No. of Test Failed : 56 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.22 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 71 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-05-2017 | 1+500 | G3 work in progress | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
2. | 06-05-2017 | End Point | On end point of the road parapet s and warning sign board required | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
3. | 06-05-2017 | End point | End point of Road required safety sign and parapet wall | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
4. | 21-01-2017 | Ch-0+960 | Curing of parapets | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
5. | 29-11-2016 | Ch- 2+325 | Reconstruction of R/W | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
6. | 19-11-2016 | Ch- 4+910 | End point of the road, PC complete. Drains and shoulders filling under progress. | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
7. | 26-10-2016 | Ch- 0+900 | Tack coat apply before pMC Laying, check. And found satisfactory | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
8. | 26-10-2016 | 1+200 | PC in progress | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
9. | 26-10-2016 | Chainage 1+220 | PC in Progress | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
10. | 26-10-2016 | Chainage 1+200 | Tack coat over primed WBM gr3 surface before PC | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
11. | 17-10-2016 | Ch 0. 00 | Laying of R.B.I-81 | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
12. | 09-10-2016 | Ch. 3.400 | Checking thickness of kc drain | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
13. | 09-10-2016 | Ch.4.710 | Wing wall of 3.00 mtr span culvert | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
14. | 09-10-2016 | Ch.4.200 | Road surface after rbi layer | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
15. | 09-10-2016 | Ch. O.080 | Rejected kc drain | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
16. | 04-09-2016 | Ch.3.000 | Road surface after rbi layer | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
17. | 04-09-2016 | Ch-2+650 | Slide during Apda | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 15-08-2016 | Ch. 3. 150 | Const of kc drain | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
19. | 17-06-2016 | Ch- 0+100 | Field CBR testing | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 05-04-2016 | Ch- 1+070 | Site inspection by SE | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|