Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Kandhar Reetha Talla Parkoti Sirkot Patharkhani MR Work Completed
Project: UDRP-RB UID: 1139 Sanction Cost: 448.58  lakh Length: 6.000 KM.
District: Bageshwar Block: Garud Constituency: Bageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 110        Package Name:  UDRP/PWD/08/05/RD/099        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/099      Contractor Name: Anil Malik Contractor
Start Date:  01-10-2015      Intended Completion Date:  10-10-2017      Original End Date:  30-12-2016
Total Bond Cost: 152575316.91 (1525.75 lakh)        Variation Cost: 4156629.06 (41.57 lakh)    Hence Total Bond Cost is   156731945.97 (1567.32 lakh) 
Sub Project Cost: 442.99  lakh        Variation Cost of Sub Project: -6618399.32  (-66.18 lakh)       Total Sub Project Cost:   376.81 lakh
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days        LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.16 KM43.7220-10-201530-06-20171.16 KM1.16 KM10.9643.72
2.R/Wall, B/ Wall Type Protection works910.00 m65.5911-10-201530-12-2016910.00 m910.00 m16.4465.59
3.GSB/RBI/G-14.91 KM74.8901-06-201615-10-20164.91 KM4.91 KM18.7774.89
4.G-34.91 KM37.2225-06-201615-11-20164.91 KM4.91 KM9.3337.22
5.PC/CC i/c Prime Coat, Tack Coat4.91 KM68.6615-09-201615-11-20164.91 KM4.91 KM17.2168.66
6.Culverts/Scupper 12.00 No34.3520-11-201510-06-201611.00 No11.00 No8.6134.35
7.longitudinal Drain4754.00 m42.4715-12-201515-11-20164754.00 m4754.00 m10.6542.47
8.Crash Barrier300.00 m7.8316-06-201615-07-2017300.00 m300.00 m1.967.83
9.Parapet400.00 No11.5316-06-201615-07-2017400.00 No400.00 No2.8911.53
10.Road Furniture109.00 No1.3301-10-201615-03-2017111.00 No111.00 No0.331.33
11.Other Allied Works & Finishing Work 1.00 Job11.3325-05-201610-08-20172.00 Job2.00 Job2.8411.33
Total Amount: 398.92 100   398.92
Remarks: No Remarks       Work Program Made On: 21-11-2015        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-February-201655.66  lakh
2.30-April-201644.19  lakh
3.28-June-201636.35  lakh
4.12-August-201619.82  lakh
5.29-September-201657.40  lakh
6.22-October-201683.45  lakh
7.08-December-20160.16  lakh
8.21-December-20160.61  lakh
9.13-January-20179.48  lakh
10.02-February-20170.06  lakh
11.27-April-20177.56  lakh
12.21-June-20177.54  lakh
13.16-October-20178.33  lakh
14.24-November-20179.09  lakh
15.16-November-20180.79  lakh
Total 340.49  lakh
% Payment90.36 %
Advance Amount:  625.98  lakh        Recovered Amount:  625.98  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Bill sh ould be issued
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1601   No. of Test Done : 1519    No. of Test Passed : 1463   No. of Test Failed : 56   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.22
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 71
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-05-20171+500G3 work in progressMohd. Ifran QureshiQCDSC5 R&B WB Bageshwar See Pic
2.06-05-2017End PointOn end point of the road parapet s and warning sign board requiredManoj BhattREDSC2 R&B WB Pauri See Pic
3.06-05-2017End pointEnd point of Road required safety sign and parapet wallManoj BhattREDSC2 R&B WB Pauri See Pic
4.21-01-2017Ch-0+960Curing of parapetsMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
5.29-11-2016Ch- 2+325Reconstruction of R/WMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
6.19-11-2016Ch- 4+910End point of the road, PC complete. Drains and shoulders filling under progress.Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
7.26-10-2016Ch- 0+900Tack coat apply before pMC Laying, check. And found satisfactoryMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
8.26-10-20161+200PC in progressManoj BhattREDSC5 R&B WB Bageshwar See Pic
9.26-10-2016Chainage 1+220PC in ProgressManoj BhattREDSC5 R&B WB Bageshwar See Pic
10.26-10-2016Chainage 1+200Tack coat over primed WBM gr3 surface before PCManoj BhattREDSC5 R&B WB Bageshwar See Pic
11.17-10-2016Ch 0. 00Laying of R.B.I-81Sanjeev BhattAEUDRP R&B Bageshwar See Pic
12.09-10-2016Ch. 3.400Checking thickness of kc drainManoj SharmaJEUDRP R&B Bageshwar See Pic
13.09-10-2016Ch.4.710Wing wall of 3.00 mtr span culvertManoj SharmaJEUDRP R&B Bageshwar See Pic
14.09-10-2016Ch.4.200Road surface after rbi layerManoj SharmaJEUDRP R&B Bageshwar See Pic
15.09-10-2016Ch. O.080Rejected kc drainManoj SharmaJEUDRP R&B Bageshwar See Pic
16.04-09-2016Ch.3.000Road surface after rbi layerManoj SharmaJEUDRP R&B Bageshwar See Pic
17.04-09-2016Ch-2+650Slide during ApdaMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
18.15-08-2016Ch. 3. 150Const of kc drainManoj SharmaJEUDRP R&B Bageshwar See Pic
19.17-06-2016Ch- 0+100Field CBR testingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
20.05-04-2016Ch- 1+070Site inspection by SEMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic