Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Okadal Ana Loharchora Gairlaikh Work Completed
Project: UDRP-RB UID: 1138 Sanction Cost: 451.88  lakh Length: 6.000 KM.
District: Bageshwar Block: Garud Constituency: Bageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 110        Package Name:  UDRP/PWD/08/05/RD/099        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/099      Contractor Name: Anil Malik Contractor
Start Date:  01-10-2015      Intended Completion Date:  10-10-2017      Original End Date:  30-12-2016
Total Bond Cost: 152575316.91 (1525.75 lakh)        Variation Cost: 4156629.06 (41.57 lakh)    Hence Total Bond Cost is   156731945.97 (1567.32 lakh) 
Sub Project Cost: 437.22  lakh        Variation Cost of Sub Project: 1937424.32  (19.37 lakh)       Total Sub Project Cost:   456.59 lakh
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days        LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.45 KM46.4610-10-201530-04-20171.33 KM1.33 KM9.8946.46
2.R/Wall, B/ Wall Type Protection works1009.00 m83.8901-11-201530-05-20161009.00 m1009.00 m17.8683.89
3.GSB/RBI/G-15.96 KM90.3401-02-201615-07-20165.96 KM5.96 KM19.2490.34
4.G-35.96 KM44.5901-03-201630-07-20165.96 KM5.96 KM9.544.59
5.PC/CC i/c Prime Coat, Tack Coat5.96 KM81.3715-06-201615-10-20165.96 KM5.96 KM17.3381.37
6.Cause Way1.00 No7.9827-05-201630-06-20161.00 No1.00 No1.77.98
7.Culverts/Scupper 19.00 No55.2325-10-201530-05-201619.00 No19.00 No11.7655.23
8.longitudinal Drain5856.00 m17.2601-12-201530-11-20165856.00 m5856.00 m3.6717.26
9.Crash Barrier696.00 m20.3716-06-201630-12-2016595.00 m595.00 m4.3420.37
10.Parapet186.00 No5.0416-06-201630-09-2016186.00 No186.00 No1.075.04
11.Road Furniture270.00 No2.5901-11-201615-03-2017270.00 No270.00 No0.552.59
12.Other Allied Works & Finishing Work 2.00 Job14.5301-11-201530-08-20175.00 Job5.00 Job3.114.53
Total Amount: 469.65 100   469.65
Remarks: No Remarks       Work Program Made On: 21-11-2015        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-February-201695.76  lakh
2.30-April-201670.75  lakh
3.28-June-201693.90  lakh
4.12-August-201655.00  lakh
5.29-September-201668.70  lakh
6.22-October-201644.35  lakh
7.08-December-20160.44  lakh
8.21-December-20160.93  lakh
9.13-January-201746.92  lakh
10.02-February-20170.06  lakh
11.27-April-20171.19  lakh
12.16-October-20171.10  lakh
13.24-November-20178.57  lakh
14.16-November-20180.45  lakh
Total 488.12  lakh
% Payment106.91 %
Advance Amount:  625.98  lakh        Recovered Amount:  625.98  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1601   No. of Test Done : 1519    No. of Test Passed : 1463   No. of Test Failed : 56   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.03
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 110
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-12-2016Ch_0+700PC thickness checked by SE USRIPMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
2.17-12-2016Ch-0+080SE Sir USRIP Visit with EE & RE sirMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
3.17-10-2016Ch 4. 710Raft for 3.00 mtr span culvertSanjeev BhattAEUDRP R&B Bageshwar See Pic
4.17-10-2016Ch 6.000Inspection by Mission world bankSanjeev BhattAEUDRP R&B Bageshwar See Pic
5.17-10-2016Ch 6.000Site inspection by mission world bankSanjeev BhattAEUDRP R&B Bageshwar See Pic
6.17-10-2016Ch 5. 200Inspection of labour campSanjeev BhattAEUDRP R&B Bageshwar See Pic
7.09-10-2016HmpPc work in progressManoj SharmaJEUDRP R&B Bageshwar See Pic
8.06-10-2016Ch.4 190Checking undolationManoj SharmaJEUDRP R&B Bageshwar See Pic
9.06-10-2016Ch.0.00Pc work completeManoj SharmaJEUDRP R&B Bageshwar See Pic
10.06-10-2016HmpPollution plantManoj SharmaJEUDRP R&B Bageshwar See Pic
11.06-10-2016HmpChecking temp of mix of pcManoj SharmaJEUDRP R&B Bageshwar See Pic
12.23-09-2016Ch.4.800Metal crash barrier workManoj SharmaJEUDRP R&B Bageshwar See Pic
13.23-09-2016Ch.4.750Preparation the surface for pc work.Manoj SharmaJEUDRP R&B Bageshwar See Pic
14.18-09-20164+450Rolling over PMC SurfaceMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
15.18-09-20164+390Thickness of PMC found 29 mmMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
16.18-09-2016Ch-4+390PMC LayingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
17.04-09-2016Ch-0+850Slide during ApdaMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
18.04-09-2016Ch-0+930Slide during ApdaMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
19.24-08-201606+000 last point of RoadWork Bank Mission visit on Pkg 99,OALG motor road in Bageshwar Distirct.Rishi RamQCDSC5 R&B WB Bageshwar See Pic
20.24-08-201602+970FDD checking of RBI_81 layerRishi RamQCDSC5 R&B WB Bageshwar See Pic