Okadal Ana Loharchora Gairlaikh
Work Completed
|
Project: |
UDRP-RB |
UID: |
1138 |
Sanction Cost: |
451.88 lakh |
Length:
|
6.000 KM. |
District: |
Bageshwar |
Block: |
Garud |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 110
Package Name: 
UDRP/PWD/08/05/RD/099
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/099
Contractor Name: Anil Malik Contractor
|
Start Date: 01-10-2015
Intended Completion Date: 10-10-2017
Original End Date: 30-12-2016 |
Total Bond Cost: 152575316.91 (1525.75 lakh)
Variation Cost: 4156629.06 (41.57 lakh) Hence Total Bond Cost is 156731945.97 (1567.32 lakh)
|
Sub Project Cost: 437.22 lakh
Variation Cost of Sub Project: 1937424.32 (19.37 lakh)
Total Sub Project Cost:
456.59 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days
LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.45 KM | 46.46 | 10-10-2015 | 30-04-2017 | 1.33 KM | 1.33 KM | 9.89 | 46.46 | 2. | R/Wall, B/ Wall Type Protection works | 1009.00 m | 83.89 | 01-11-2015 | 30-05-2016 | 1009.00 m | 1009.00 m | 17.86 | 83.89 | 3. | GSB/RBI/G-1 | 5.96 KM | 90.34 | 01-02-2016 | 15-07-2016 | 5.96 KM | 5.96 KM | 19.24 | 90.34 | 4. | G-3 | 5.96 KM | 44.59 | 01-03-2016 | 30-07-2016 | 5.96 KM | 5.96 KM | 9.5 | 44.59 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.96 KM | 81.37 | 15-06-2016 | 15-10-2016 | 5.96 KM | 5.96 KM | 17.33 | 81.37 | 6. | Cause Way | 1.00 No | 7.98 | 27-05-2016 | 30-06-2016 | 1.00 No | 1.00 No | 1.7 | 7.98 | 7. | Culverts/Scupper | 19.00 No | 55.23 | 25-10-2015 | 30-05-2016 | 19.00 No | 19.00 No | 11.76 | 55.23 | 8. | longitudinal Drain | 5856.00 m | 17.26 | 01-12-2015 | 30-11-2016 | 5856.00 m | 5856.00 m | 3.67 | 17.26 | 9. | Crash Barrier | 696.00 m | 20.37 | 16-06-2016 | 30-12-2016 | 595.00 m | 595.00 m | 4.34 | 20.37 | 10. | Parapet | 186.00 No | 5.04 | 16-06-2016 | 30-09-2016 | 186.00 No | 186.00 No | 1.07 | 5.04 | 11. | Road Furniture | 270.00 No | 2.59 | 01-11-2016 | 15-03-2017 | 270.00 No | 270.00 No | 0.55 | 2.59 | 12. | Other Allied Works & Finishing Work | 2.00 Job | 14.53 | 01-11-2015 | 30-08-2017 | 5.00 Job | 5.00 Job | 3.1 | 14.53 |
Total Amount: |
469.65 |
|
100 |
469.65 |
|
Remarks:
No Remarks
Work Program Made On:
21-11-2015 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-February-2016 | 95.76 lakh | 2. | 30-April-2016 | 70.75 lakh | 3. | 28-June-2016 | 93.90 lakh | 4. | 12-August-2016 | 55.00 lakh | 5. | 29-September-2016 | 68.70 lakh | 6. | 22-October-2016 | 44.35 lakh | 7. | 08-December-2016 | 0.44 lakh | 8. | 21-December-2016 | 0.93 lakh | 9. | 13-January-2017 | 46.92 lakh | 10. | 02-February-2017 | 0.06 lakh | 11. | 27-April-2017 | 1.19 lakh | 12. | 16-October-2017 | 1.10 lakh | 13. | 24-November-2017 | 8.57 lakh | 14. | 16-November-2018 | 0.45 lakh |
Total |
488.12 lakh |
% Payment | 106.91 % |
|
Advance Amount: 625.98 lakh
Recovered Amount: 625.98 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1601 No. of Test Done : 1519 No. of Test Passed : 1463 No. of Test Failed : 56 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.03 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 110 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 17-12-2016 | Ch_0+700 | PC thickness checked by SE USRIP | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
2. | 17-12-2016 | Ch-0+080 | SE Sir USRIP Visit with EE & RE sir | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
3. | 17-10-2016 | Ch 4. 710 | Raft for 3.00 mtr span culvert | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
4. | 17-10-2016 | Ch 6.000 | Inspection by Mission world bank | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
5. | 17-10-2016 | Ch 6.000 | Site inspection by mission world bank | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
6. | 17-10-2016 | Ch 5. 200 | Inspection of labour camp | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
7. | 09-10-2016 | Hmp | Pc work in progress | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
8. | 06-10-2016 | Ch.4 190 | Checking undolation | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
9. | 06-10-2016 | Ch.0.00 | Pc work complete | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
10. | 06-10-2016 | Hmp | Pollution plant | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
11. | 06-10-2016 | Hmp | Checking temp of mix of pc | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
12. | 23-09-2016 | Ch.4.800 | Metal crash barrier work | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
13. | 23-09-2016 | Ch.4.750 | Preparation the surface for pc work. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
14. | 18-09-2016 | 4+450 | Rolling over PMC Surface | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
15. | 18-09-2016 | 4+390 | Thickness of PMC found 29 mm | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
16. | 18-09-2016 | Ch-4+390 | PMC Laying | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
17. | 04-09-2016 | Ch-0+850 | Slide during Apda | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 04-09-2016 | Ch-0+930 | Slide during Apda | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 24-08-2016 | 06+000 last point of Road | Work Bank Mission visit on Pkg 99,OALG motor road in Bageshwar Distirct. | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 24-08-2016 | 02+970 | FDD checking of RBI_81 layer | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|