Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dakghar Simghari MR Work Completed
Project: UDRP-RB UID: 1137 Sanction Cost: 221.95  lakh Length: 2.560 KM.
District: Bageshwar Block: Garud Constituency: Bageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 110        Package Name:  UDRP/PWD/08/05/RD/099        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 24-09-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/099      Contractor Name: Anil Malik Contractor
Start Date:  01-10-2015      Intended Completion Date:  10-10-2017      Original End Date:  30-12-2016
Total Bond Cost: 152575316.91 (1525.75 lakh)        Variation Cost: 4156629.06 (41.57 lakh)    Hence Total Bond Cost is   156731945.97 (1567.32 lakh) 
Sub Project Cost: 182.08  lakh        Variation Cost of Sub Project: 545152.80  (5.45 lakh)       Total Sub Project Cost:   187.53 lakh
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days        LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.49 KM12.7010-10-201530-04-20170.49 KM0.49 KM6.5412.70
2.R/Wall, B/ Wall Type Protection works408.00 m34.1401-11-201531-12-2016408.00 m408.00 m17.5934.14
3.GSB/RBI/G-12.45 KM32.9710-06-201630-07-20162.50 KM2.50 KM16.9932.97
4.G-32.45 KM16.8315-07-201630-09-20162.56 KM2.56 KM8.6716.83
5.PC/CC i/c Prime Coat, Tack Coat2.45 KM32.4415-10-201630-10-20162.56 KM2.56 KM16.7132.44
6.Cause Way4.00 No23.9215-03-201630-09-20163.00 No3.00 No12.3323.92
7.Culverts/Scupper 10.00 No18.8625-11-201530-04-201610.00 No10.00 No9.7218.86
8.longitudinal Drain2192.00 m9.3920-12-201530-06-20162276.00 m2276.00 m4.849.39
9.Crash Barrier84.00 m2.1916-06-201630-12-201684.00 m84.00 m1.132.19
10.Parapet80.00 No2.3116-06-201615-07-201780.00 No80.00 No1.192.31
11.Road Furniture136.00 No1.3901-10-201615-03-2017132.00 No132.00 No0.721.39
12.Other Allied Works & Finishing Work 1.00 Job6.9425-05-201610-08-20171.00 Job1.00 Job3.576.94
Total Amount: 194.08 100   194.08
Remarks: No Remarks       Work Program Made On: 21-11-2015        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.29-February-201642.03  lakh
2.29-March-201621.10  lakh
3.30-April-20168.32  lakh
4.28-June-201617.13  lakh
5.12-August-201617.52  lakh
6.22-October-201667.65  lakh
7.08-December-20160.16  lakh
8.13-January-201711.75  lakh
9.02-February-20170.09  lakh
10.27-April-20172.40  lakh
11.27-September-20172.98  lakh
12.16-October-20172.19  lakh
13.24-November-20172.45  lakh
14.16-November-20180.45  lakh
Total 196.22  lakh
% Payment104.63 %
Advance Amount:  625.98  lakh        Recovered Amount:  625.98  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 1601   No. of Test Done : 1519    No. of Test Passed : 1463   No. of Test Failed : 56   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.93
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 40
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.17-10-2016Ch 0.025Mixing of R.B.I 81Sanjeev BhattAEUDRP R&B Bageshwar See Pic
2.17-10-2016Ch 2.475Construction of R/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
3.15-10-20160+550PMC Laying and rollingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
4.15-10-20161+190Rolling over Seal coatMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
5.15-10-2016Ch-1+855Curing of B/WMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
6.13-08-2016Ch-1+150PQC for causewayMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
7.19-07-2016Ch 0.400Tree plantationJagdish Narayan Meenaunknownunknown See Pic
8.19-07-2016Ch 0.450RBI surface and G3 materialJagdish Narayan Meenaunknownunknown See Pic
9.19-07-2016Ch 0.550Stacking of WBM G3 materialJagdish Narayan Meenaunknownunknown See Pic
10.19-07-2016Ch 0.880R/Wall damaged due to settlementJagdish Narayan Meenaunknownunknown See Pic
11.19-07-2016Ch 2.490EE sir inspectionJagdish Narayan Meenaunknownunknown See Pic
12.19-07-2016Ch 0.990Slide due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
13.17-06-2016Change 0+015Field CBR TESTINGMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
14.13-06-2016Ch- 0+075Watering on RBI-81Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
15.09-06-2016Ch- 0+075RBI-81 mixingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
16.09-06-2016Ch- 0+075RBI-81 mixingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
17.13-04-2016Ch 0.982Construction of R WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
18.11-04-2016Ch 1.025Construction of R WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
19.05-03-2016Ch. 6.700Const of rcc culvertManoj SharmaJEUDRP R&B Bageshwar See Pic
20.12-02-2016Site Laboratory Pkg 99Silt content of Coarse sandRishi RamQCDSC5 R&B WB Bageshwar See Pic