Chaufala Mate Tilsari MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1136 |
Sanction Cost: |
476.19 lakh |
Length:
|
6.000 KM. |
District: |
Bageshwar |
Block: |
Garud |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 110
Package Name: 
UDRP/PWD/08/05/RD/099
Tender Date: 27-06-2015
Current Status: Agreement signed
Achieved on Date: 24-09-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/099
Contractor Name: Anil Malik Contractor
|
Start Date: 01-10-2015
Intended Completion Date: 10-10-2017
Original End Date: 30-12-2016 |
Total Bond Cost: 152575316.91 (1525.75 lakh)
Variation Cost: 4156629.06 (41.57 lakh) Hence Total Bond Cost is 156731945.97 (1567.32 lakh)
|
Sub Project Cost: 439.49 lakh
Variation Cost of Sub Project: 8292451.26 (82.92 lakh)
Total Sub Project Cost:
522.41 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 2746368 for 36 days
LD Analysis for Milestone2: calculated LD is Rs 3661824 for 48 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.97 KM | 34.54 | 20-10-2015 | 10-05-2017 | 0.85 KM | 0.85 KM | 6.57 | 34.54 | 2. | R/Wall, B/ Wall Type Protection works | 892.00 m | 91.93 | 01-11-2015 | 30-05-2016 | 769.00 m | 769.00 m | 17.49 | 91.93 | 3. | GSB/RBI/G-1 | 6.03 KM | 77.39 | 01-01-2017 | 30-06-2017 | 6.00 KM | 6.00 KM | 14.73 | 77.39 | 4. | G-3 | 6.03 KM | 45.69 | 01-02-2017 | 30-07-2017 | 6.00 KM | 6.00 KM | 8.7 | 45.69 | 5. | PC/CC i/c Prime Coat, Tack Coat | 6.03 KM | 84.30 | 05-05-2017 | 30-09-2017 | 6.03 KM | 6.03 KM | 16.04 | 84.30 | 6. | Cause Way | 2.00 No | 20.81 | 10-02-2017 | 10-10-2017 | 2.00 No | 2.00 No | 3.96 | 20.81 | 7. | Culverts/Scupper | 40.00 No | 82.44 | 20-10-2015 | 30-09-2016 | 24.00 No | 24.00 No | 15.69 | 82.44 | 8. | longitudinal Drain | 5805.00 m | 52.24 | 01-12-2015 | 10-10-2017 | 5805.00 m | 5805.00 m | 9.94 | 52.24 | 9. | Crash Barrier | 350.00 m | 9.12 | 15-03-2017 | 10-10-2017 | 650.00 m | 650.00 m | 1.74 | 9.12 | 10. | Parapet | 120.00 No | 3.42 | 15-04-2017 | 10-10-2017 | 20.00 No | 20.00 No | 0.65 | 3.42 | 11. | Road Furniture | 113.00 No | 1.41 | 01-10-2016 | 10-10-2017 | 196.00 No | 196.00 No | 0.27 | 1.41 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 22.20 | 02-04-2017 | 10-10-2017 | 1.00 Job | 1.00 Job | 4.23 | 22.20 |
Total Amount: |
525.49 |
|
100 |
525.49 |
|
Remarks:
No Remarks
Work Program Made On:
21-11-2015 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 29-February-2016 | 14.25 lakh | 2. | 29-March-2016 | 36.65 lakh | 3. | 30-April-2016 | 9.77 lakh | 4. | 28-June-2016 | 22.61 lakh | 5. | 22-October-2016 | 60.05 lakh | 6. | 21-December-2016 | 1.18 lakh | 7. | 13-January-2017 | 27.57 lakh | 8. | 02-February-2017 | 0.06 lakh | 9. | 27-April-2017 | 56.14 lakh | 10. | 21-June-2017 | 99.98 lakh | 11. | 21-August-2017 | 54.78 lakh | 12. | 08-September-2017 | 0.37 lakh | 13. | 27-September-2017 | 93.31 lakh | 14. | 16-October-2017 | 20.58 lakh | 15. | 24-November-2017 | 49.57 lakh | 16. | 16-November-2018 | 8.50 lakh |
Total |
555.37 lakh |
% Payment | 106.31 % |
|
Advance Amount: 625.98 lakh
Recovered Amount: 625.98 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 1601 No. of Test Done : 1519 No. of Test Passed : 1463 No. of Test Failed : 56 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 84.93 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 65 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 14-06-2017 | 1+700 | Seal coat over pc surface in progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
2. | 14-06-2017 | 1+800 | Seal coat on pc surface in progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
3. | 08-06-2017 | 3+550 | G3 Rolling, Work in progress | Mohd Irfan Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
4. | 12-05-2017 | Anil malik contractor lab | WBM G 3 gradation test report | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 12-05-2017 | Ch 0.700 | Sample collection for WBM G3 greadation test and AIV test . | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 05-05-2017 | Anil malik lab | WBM G3 Gradation report | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
7. | 05-05-2017 | Anil malik lab | Gradation of WBM G3 | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
8. | 05-05-2017 | 0+700 | Super elevation check and found 7%. | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
9. | 05-05-2017 | 0+750 | Providing screening on G3 | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
10. | 05-05-2017 | 0+730 | G3 laying | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
11. | 04-05-2017 | 0+825 | Social Experts Discuss with workering labours working at site | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
12. | 04-05-2017 | 0+750 | Social Experts discussions with road users. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
13. | 04-05-2017 | 0+750 | Discuss with Villagers Mr. CS Pandey (mob. No. 9967270096) social experts Dr. S ROY & Mr. CS Tyagi. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
14. | 04-05-2017 | 0+750 | WBM gr-3, Spreading in Progress | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
15. | 04-05-2017 | 0+875 | Social Experts verifing social compliances | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
16. | 04-05-2017 | 0+000 | Social experts visit to verify the compliances | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
17. | 04-05-2017 | Piu office in bageshwar, Environment expert Dr. Sameer Ray discussions EE, RE, JE | Environment expert discuss with EE and RE, JE | Mohd. Ifran Qureshi | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 16-02-2017 | Ch 0.570 | Culvert abutment work in progress and HPS filling | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 16-02-2017 | Ch 2.140 | Culvert abutment work in progress | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 29-12-2016 | Ch-3+610 | Sample collection for CBR testing by third party. | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|