Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Vijaypur Dhaptri Bastoli Motor Road Work Completed
Project: UDRP-RB UID: 1131 Sanction Cost: 300.55  lakh Length: 6.000 KM.
District: Bageshwar Block: Bageshwar Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 38        Package Name:  UDRP/PWD/08/05/RD/038        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 15-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/038      Contractor Name: Dwarika Projects Limited
Start Date:  22-09-2014      Intended Completion Date:  25-09-2017      Original End Date:  21-12-2015
Total Bond Cost: 60641927.25 (606.42 lakh)        Variation Cost: 6062931.19 (60.63 lakh)    Hence Total Bond Cost is   66704858.44 (667.05 lakh) 
Sub Project Cost: 233.21  lakh        Variation Cost of Sub Project: 2712290.53  (27.12 lakh)       Total Sub Project Cost:   260.33 lakh
LD Analysis for Milestone1: calculated LD is Rs 5245533 for 173 days        LD Analysis for Milestone2: calculated LD is Rs 14372154 for 474 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.02 KM13.2701-04-201505-05-20161.02 KM1.02 KM4.2313.27
2.R/Wall, B/ Wall Type Protection works735.00 m50.0822-09-201410-05-2017675.00 m675.00 m15.9650.08
3.GSB/RBI/G-14.00 KM60.3701-04-201512-05-20173.50 KM3.50 KM19.2460.37
4.G-20.00 KM0.0010-04-201502-08-20160.00 KM0.00 KM00.00
5.G-30.00 KM0.0015-04-201502-08-20163.60 KM3.60 KM00.00
6.PC/CC i/c Prime Coat, Tack Coat4.00 KM76.3802-09-201520-09-20163.50 KM3.50 KM24.3476.38
7.Cause Way5.00 No24.7101-04-201515-05-20174.00 No4.00 No7.8824.71
8.Culverts/Scupper 10.00 No37.8701-10-201410-05-201710.00 No10.00 No12.0737.87
9.longitudinal Drain3950.00 m5.1307-08-201515-05-20173950.00 m3950.00 m1.645.13
10.Crash Barrier425.00 m17.0601-08-201520-09-20161636.00 m1636.00 m5.4417.06
11.Parapet270.00 No8.8301-09-201510-05-201765.00 No65.00 No2.818.83
12.Road Furniture68.00 No2.6001-11-201515-05-201742.00 No42.00 No0.832.60
13.Other Allied Works & Finishing Work 3.00 Job17.4615-12-201415-05-20173.00 Job3.00 Job5.5717.46
Total Amount: 313.76 100   313.76
Remarks: No Remarks       Work Program Made On: 01-10-2014        Updation of work program on: 14-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-May-201535.07  lakh
2.29-June-20157.60  lakh
3.28-August-20159.60  lakh
4.03-November-201518.82  lakh
5.08-April-20160.10  lakh
6.27-October-20164.98  lakh
7.28-February-201739.91  lakh
8.12-April-201754.54  lakh
9.20-June-201769.46  lakh
10.08-September-20170.45  lakh
11.16-October-201782.85  lakh
12.16-November-20181.26  lakh
Total 324.64  lakh
% Payment124.7 %
Advance Amount:  131.35  lakh        Recovered Amount:  131.35  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 599   No. of Test Done : 607    No. of Test Passed : 580   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 86.30
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 73
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-06-2017Ch 2.950Crash barrier and sign boardJagdish Narayan Meenaunknownunknown See Pic
2.18-02-2017Ch 3.360RBI -81 crust checking by SE sir PWD champawatJagdish Narayan Meenaunknownunknown See Pic
3.18-02-2017Ch 5.900Causeway inspection by SE sir champawatJagdish Narayan Meenaunknownunknown See Pic
4.18-02-2017Ch 1.950SE sir PWD champawat inspectionJagdish Narayan Meenaunknownunknown See Pic
5.29-01-2017At HM plantSafety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38 & 45Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
6.28-01-2017At plantEnvironmental trainingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
7.28-01-2017At HM plantSafety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38,45 & 37Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
8.23-01-2017Ch-3+660Curing on RBI-81 surfaceMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
9.21-01-2017Ch-4+620Construction of R/Wall Regected because Base width of wall only 60 & 70 cmMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
10.28-12-2016Ch-0+300Subgrade preparationMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
11.25-12-2016Ch 3.560Subgrade preparationJagdish Narayan Meenaunknownunknown See Pic
12.17-09-20164+900DLC of causeway completedHarish ChandraJEUDRP R&B Bageshwar See Pic
13.15-09-2016Ch 4.425R/wall with stone fillingJagdish Narayan Meenaunknownunknown See Pic
14.01-09-2016Ch-1+500Slab castingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
15.01-09-2016Ch-1+375Preparing of sub gradeMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
16.03-06-20164+900C/way work in progressHarish ChandraJEUDRP R&B Bageshwar See Pic
17.13-04-2016Ch- 1+320Defect CuttingMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
18.18-03-2016Site laboratory bageshwarStone broken for AIV TestSanjeev BhattAEUDRP R&B Bageshwar See Pic
19.16-03-2016Ch 1.510Site inspection E.E.sirSanjeev BhattAEUDRP R&B Bageshwar See Pic
20.20-01-2016Ch 1.505Execavation of 1.00 mtr span R.C.C CulvertSanjeev BhattAEUDRP R&B Bageshwar See Pic