Vijaypur Dhaptri Bastoli Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1131 |
Sanction Cost: |
300.55 lakh |
Length:
|
6.000 KM. |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 38
Package Name: 
UDRP/PWD/08/05/RD/038
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/038
Contractor Name: Dwarika Projects Limited
|
Start Date: 22-09-2014
Intended Completion Date: 25-09-2017
Original End Date: 21-12-2015 |
Total Bond Cost: 60641927.25 (606.42 lakh)
Variation Cost: 6062931.19 (60.63 lakh) Hence Total Bond Cost is 66704858.44 (667.05 lakh)
|
Sub Project Cost: 233.21 lakh
Variation Cost of Sub Project: 2712290.53 (27.12 lakh)
Total Sub Project Cost:
260.33 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 5245533 for 173 days
LD Analysis for Milestone2: calculated LD is Rs 14372154 for 474 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.02 KM | 13.27 | 01-04-2015 | 05-05-2016 | 1.02 KM | 1.02 KM | 4.23 | 13.27 | 2. | R/Wall, B/ Wall Type Protection works | 735.00 m | 50.08 | 22-09-2014 | 10-05-2017 | 675.00 m | 675.00 m | 15.96 | 50.08 | 3. | GSB/RBI/G-1 | 4.00 KM | 60.37 | 01-04-2015 | 12-05-2017 | 3.50 KM | 3.50 KM | 19.24 | 60.37 | 4. | G-2 | 0.00 KM | 0.00 | 10-04-2015 | 02-08-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 0.00 KM | 0.00 | 15-04-2015 | 02-08-2016 | 3.60 KM | 3.60 KM | 0 | 0.00 | 6. | PC/CC i/c Prime Coat, Tack Coat | 4.00 KM | 76.38 | 02-09-2015 | 20-09-2016 | 3.50 KM | 3.50 KM | 24.34 | 76.38 | 7. | Cause Way | 5.00 No | 24.71 | 01-04-2015 | 15-05-2017 | 4.00 No | 4.00 No | 7.88 | 24.71 | 8. | Culverts/Scupper | 10.00 No | 37.87 | 01-10-2014 | 10-05-2017 | 10.00 No | 10.00 No | 12.07 | 37.87 | 9. | longitudinal Drain | 3950.00 m | 5.13 | 07-08-2015 | 15-05-2017 | 3950.00 m | 3950.00 m | 1.64 | 5.13 | 10. | Crash Barrier | 425.00 m | 17.06 | 01-08-2015 | 20-09-2016 | 1636.00 m | 1636.00 m | 5.44 | 17.06 | 11. | Parapet | 270.00 No | 8.83 | 01-09-2015 | 10-05-2017 | 65.00 No | 65.00 No | 2.81 | 8.83 | 12. | Road Furniture | 68.00 No | 2.60 | 01-11-2015 | 15-05-2017 | 42.00 No | 42.00 No | 0.83 | 2.60 | 13. | Other Allied Works & Finishing Work | 3.00 Job | 17.46 | 15-12-2014 | 15-05-2017 | 3.00 Job | 3.00 Job | 5.57 | 17.46 |
Total Amount: |
313.76 |
|
100 |
313.76 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2014 } ?>
Updation of work program on:
14-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 35.07 lakh | 2. | 29-June-2015 | 7.60 lakh | 3. | 28-August-2015 | 9.60 lakh | 4. | 03-November-2015 | 18.82 lakh | 5. | 08-April-2016 | 0.10 lakh | 6. | 27-October-2016 | 4.98 lakh | 7. | 28-February-2017 | 39.91 lakh | 8. | 12-April-2017 | 54.54 lakh | 9. | 20-June-2017 | 69.46 lakh | 10. | 08-September-2017 | 0.45 lakh | 11. | 16-October-2017 | 82.85 lakh | 12. | 16-November-2018 | 1.26 lakh |
Total |
324.64 lakh |
% Payment | 124.7 % |
|
Advance Amount: 131.35 lakh
Recovered Amount: 131.35 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 599 No. of Test Done : 607 No. of Test Passed : 580 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.30 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 73 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-06-2017 | Ch 2.950 | Crash barrier and sign board | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 18-02-2017 | Ch 3.360 | RBI -81 crust checking by SE sir PWD champawat | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 18-02-2017 | Ch 5.900 | Causeway inspection by SE sir champawat | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 18-02-2017 | Ch 1.950 | SE sir PWD champawat inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 29-01-2017 | At HM plant | Safety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38 & 45 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
6. | 28-01-2017 | At plant | Environmental training | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
7. | 28-01-2017 | At HM plant | Safety tips by Expert to worker's , supervisors & Engineers of PKG 10, 38,45 & 37 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
8. | 23-01-2017 | Ch-3+660 | Curing on RBI-81 surface | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
9. | 21-01-2017 | Ch-4+620 | Construction of R/Wall Regected because Base width of wall only 60 & 70 cm | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
10. | 28-12-2016 | Ch-0+300 | Subgrade preparation | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
11. | 25-12-2016 | Ch 3.560 | Subgrade preparation | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 17-09-2016 | 4+900 | DLC of causeway completed | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
13. | 15-09-2016 | Ch 4.425 | R/wall with stone filling | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 01-09-2016 | Ch-1+500 | Slab casting | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
15. | 01-09-2016 | Ch-1+375 | Preparing of sub grade | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
16. | 03-06-2016 | 4+900 | C/way work in progress | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
17. | 13-04-2016 | Ch- 1+320 | Defect Cutting | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 18-03-2016 | Site laboratory bageshwar | Stone broken for AIV Test | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
19. | 16-03-2016 | Ch 1.510 | Site inspection E.E.sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
20. | 20-01-2016 | Ch 1.505 | Execavation of 1.00 mtr span R.C.C Culvert | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
|
|