kanda- Mantoli MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1123 |
Sanction Cost: |
305.87 lakh |
Length:
|
5.000 KM. |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 38
Package Name: 
UDRP/PWD/08/05/RD/038
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/038
Contractor Name: Dwarika Projects Limited
|
Start Date: 22-09-2014
Intended Completion Date: 25-09-2017
Original End Date: 21-12-2015 |
Total Bond Cost: 60641927.25 (606.42 lakh)
Variation Cost: 6062931.19 (60.63 lakh) Hence Total Bond Cost is 66704858.44 (667.05 lakh)
|
Sub Project Cost: 292.28 lakh
Variation Cost of Sub Project: 3350640.66 (33.51 lakh)
Total Sub Project Cost:
325.79 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 5245533 for 173 days
LD Analysis for Milestone2: calculated LD is Rs 14372154 for 474 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.93 KM | 21.90 | 01-04-2015 | 10-05-2017 | 2.93 KM | 2.93 KM | 5.95 | 21.90 | 2. | R/Wall, B/ Wall Type Protection works | 574.00 m | 75.80 | 01-10-2014 | 10-05-2017 | 574.00 m | 574.00 m | 20.61 | 75.80 | 3. | GSB/RBI/G-1 | 5.00 KM | 77.50 | 15-05-2015 | 12-05-2017 | 5.00 KM | 5.00 KM | 21.07 | 77.50 | 4. | G-2 | 0.00 KM | 0.00 | 15-03-2015 | 04-05-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 0.00 KM | 0.00 | 03-01-2015 | 15-07-2015 | 5.00 KM | 5.00 KM | 0 | 0.00 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.00 KM | 85.64 | 16-04-2015 | 15-05-2017 | 5.00 KM | 5.00 KM | 23.28 | 85.64 | 7. | Cause Way | 6.00 No | 25.61 | 01-05-2015 | 15-05-2017 | 3.00 No | 3.00 No | 6.96 | 25.61 | 8. | Culverts/Scupper | 19.00 No | 46.80 | 01-10-2014 | 10-05-2017 | 14.00 No | 14.00 No | 12.72 | 46.80 | 9. | longitudinal Drain | 3950.00 m | 5.14 | 02-04-2015 | 25-08-2016 | 4550.00 m | 4550.00 m | 1.4 | 5.14 | 10. | Crash Barrier | 40.00 m | 1.74 | 16-07-2015 | 30-04-2017 | 1624.00 m | 1624.00 m | 0.47 | 1.74 | 11. | Parapet | 175.00 No | 7.07 | 14-04-2015 | 10-05-2017 | 10.00 No | 10.00 No | 1.92 | 7.07 | 12. | Road Furniture | 88.00 No | 3.17 | 01-11-2015 | 15-05-2017 | 273.00 No | 273.00 No | 0.86 | 3.17 | 13. | Other Allied Works & Finishing Work | 1510.00 Job | 17.44 | 01-11-2015 | 10-05-2017 | 1510.00 Job | 1510.00 Job | 4.74 | 17.44 |
Total Amount: |
367.81 |
|
100 |
367.81 |
|
Remarks:
No Remarks
Work Program Made On:
10-10-2014 } ?>
Updation of work program on:
14-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 12.98 lakh | 2. | 29-June-2015 | 14.14 lakh | 3. | 28-August-2015 | 19.21 lakh | 4. | 03-November-2015 | 20.24 lakh | 5. | 08-April-2016 | 0.10 lakh | 6. | 27-October-2016 | 44.32 lakh | 7. | 29-December-2016 | 100.33 lakh | 8. | 22-February-2017 | 0.11 lakh | 9. | 28-February-2017 | 50.71 lakh | 10. | 12-April-2017 | 14.63 lakh | 11. | 20-June-2017 | 16.75 lakh | 12. | 08-September-2017 | 0.43 lakh | 13. | 16-October-2017 | 65.74 lakh | 14. | 16-November-2018 | 2.50 lakh |
Total |
362.19 lakh |
% Payment | 111.17 % |
|
Advance Amount: 131.35 lakh
Recovered Amount: 131.35 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 599 No. of Test Done : 607 No. of Test Passed : 580 No. of Test Failed : 27 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.97 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 63 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 29-04-2017 | 1+500 | G3 work | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
2. | 29-04-2017 | 1+050 | Rolling work Rbi 81 | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
3. | 18-02-2017 | Ch 4.750 | Crust thickness checking by SE sir PWD champawat | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 18-02-2017 | Ch 2.362 | SE sir PWD champawat inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 12-01-2017 | Ch 1.005 | Checking of PC surface by EE sir PWD PD bageshwar. | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 12-01-2017 | Ch 1.200 | Site inspection by EE PWD bageshwar and EE pmgsy . | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 29-12-2016 | 1+075 | PMC Sample collecting from site for testing | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
8. | 28-12-2016 | Ch-5+550 | Dry rolling over WBM GR 3 . | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
9. | 25-12-2016 | Ch 5.880 | Surface after G3 , required compaction | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 25-12-2016 | Ch 5.900 | Water sprinkling over G3 surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 13-12-2016 | 3+930 | Compacting over WBM GR 3 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
12. | 13-12-2016 | Ch-3+930 | Water sprinkling on WBM GR 3 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
13. | 10-12-2016 | At plant | Exhaust temperature of PMC and found 150?C | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
14. | 10-12-2016 | At plant | Binder content of PMC material and found 3.43% | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
15. | 08-12-2016 | 3+600 | RBI-81 work in progress | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
16. | 07-12-2016 | Ch3+400 | Field density of RBI-81 & found 2.178 g/cc & compaction 101.78% | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
17. | 07-12-2016 | Ch-1+320 | Field CBR testing by cone penetrometer equipment | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 22-11-2016 | Ch 4.300 | HS cutting in progress | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 13-10-2016 | 1+200 | Rbi 81 work wet mixing | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
20. | 10-10-2016 | 1+200 | Rbi 81 work in progress | Harish Chandra | JE | UDRP R&B Bageshwar | See Pic |
|
|