Kameridevi Syakot Motor road Work Completed
Project: UDRP-RB UID: 1122 Sanction Cost: 256.75  lakh Length: 9.500 KM.
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 45        Package Name:  UDRP/PWD/08/06/RD/045        Tender Date: 19-04-2014        Current Status: Agreement signed        Achieved on Date: 13-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/045      Contractor Name: ESPAN Infrastructure Ltd
Start Date:  20-11-2014      Intended Completion Date:  31-08-2017      Original End Date:  19-02-2016
Total Bond Cost: 41607857.19 (416.08 lakh)        Variation Cost: 21048924.06 (210.49 lakh)    Hence Total Bond Cost is   62656781.25 (626.57 lakh) 
Sub Project Cost: 77.57  lakh        Variation Cost of Sub Project: 13260723.35  (132.61 lakh)       Total Sub Project Cost:   210.18 lakh
LD Analysis for Milestone1: calculated LD is Rs 686532 for 33 days        LD Analysis for Milestone2: calculated LD is Rs 2829344 for 136 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.20 KM9.6921-04-201505-04-20160.20 KM0.20 KM3.699.69
2.R/Wall, B/ Wall Type Protection works746.00 m28.4220-11-201410-05-2017746.00 m746.00 m10.8328.42
3.GSB/RBI/G-11.85 KM26.9020-10-201515-11-20161.85 KM1.85 KM10.2526.90
4.G-20.00 KM0.0004-04-201530-04-20150.00 KM0.00 KM00.00
5.G-31.85 KM14.4912-04-201505-05-20151.85 KM1.85 KM5.5214.49
6.PC/CC i/c Prime Coat, Tack Coat3.00 KM43.4905-06-201610-05-20171.85 KM1.85 KM16.5743.49
7.Cause Way3.00 No43.4901-03-201510-05-20173.00 No3.00 No16.5743.49
8.Culverts/Scupper 9.00 No49.4301-01-201528-02-20169.00 No9.00 No18.8449.43
9.longitudinal Drain2100.00 m4.1301-05-201510-05-20172100.00 m2100.00 m1.574.13
10.Crash Barrier40.00 m1.5401-11-201510-05-20172114.00 m2114.00 m0.591.54
11.Parapet75.00 No27.9615-11-201615-05-201710.00 No10.00 No10.6527.96
12.Road Furniture62.00 No2.3920-12-201515-05-201718.00 No18.00 No0.912.39
13.Other Allied Works & Finishing Work 3.00 Job10.5125-11-201415-05-20173.00 Job3.00 Job4.0110.51
Total Amount: 262.44 100   262.44
Remarks: No Remarks       Work Program Made On: 24-02-2015        Updation of work program on: 14-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-May-201526.25  lakh
2.29-June-20159.27  lakh
3.26-August-201516.87  lakh
4.30-October-201529.54  lakh
5.08-April-20160.05  lakh
6.16-May-201614.03  lakh
7.31-May-20164.78  lakh
8.27-October-201644.85  lakh
9.08-December-20160.09  lakh
10.29-December-20164.09  lakh
11.25-March-201727.27  lakh
12.30-June-20170.60  lakh
13.07-October-201793.43  lakh
14.16-November-20180.34  lakh
Total 271.46  lakh
% Payment129.16 %
Advance Amount:  182.38  lakh        Recovered Amount:  182.39  lakh        Balance to be Recovered  -0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 615   No. of Test Done : 570    No. of Test Passed : 544   No. of Test Failed : 26   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.30
Number of Notice(s) issued: 1

Mobile Pic Upload

Number of Pics Available on Web Repository: 49
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-12-20167+500Pc & seal coat completed, shoulder work yet to be done.Naresh MittalTLDSC5 R&B WB Bageshwar See Pic
2.16-11-2016Ch 9.500End point of roadJagdish Narayan Meenaunknownunknown See Pic
3.16-11-2016Ch 0.000Information board , correction required.Jagdish Narayan Meenaunknownunknown See Pic
4.16-11-20160+000Project information board, provision of work PC & seal coat not a BM & SDBCMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
5.26-10-2016Ch 8.200Dismantling of kharanja , and instruct to do again.Jagdish Narayan Meenaunknownunknown See Pic
6.26-10-2016Ch 8.200Dry kharanja rejected due to small size of stone and thickness not found OK.Jagdish Narayan Meenaunknownunknown See Pic
7.26-10-2016Ch 5.400Rolling over premix carpet surfaceJagdish Narayan Meenaunknownunknown See Pic
8.26-10-20165.450Compacted thickness of PC , found 26 mm.Jagdish Narayan Meenaunknownunknown See Pic
9.26-10-20165.450Laying temperature and found 119?.Jagdish Narayan Meenaunknownunknown See Pic
10.26-10-2016Ch 5.400ROLLING over PC surfaceJagdish Narayan Meenaunknownunknown See Pic
11.17-10-2016Ch 7. 250Laying of screening material over G3 layerSanjeev BhattAEUDRP R&B Bageshwar See Pic
12.15-03-201607+550Site Inspection of TL on PKG 45Rishi RamQCDSC5 R&B WB Bageshwar See Pic
13.15-03-201607+700Site visit with TL SirRishi RamQCDSC5 R&B WB Bageshwar See Pic
14.13-01-2016Site Laboratory Bageshwar for Pkg 45Liquid limit test procedure of Soil use for SubgradeRishi RamQCDSC5 R&B WB Bageshwar See Pic
15.13-01-2016Site Laboratory Bageshwar& sample collected from CH 07+755Liquid limit test of Soil use for SubgradeRishi RamQCDSC5 R&B WB Bageshwar See Pic
16.12-01-201605+300forSite visit with TL,RE AE & RBI team (MR.Sanjay Kumar) discussion for RBI 81Rishi RamQCDSC5 R&B WB Bageshwar See Pic
17.07-01-201605+500Site Instructions By EE world Bank at SiteRishi RamQCDSC5 R&B WB Bageshwar See Pic
18.07-01-201607+700RBI 81 work in progressRishi RamQCDSC5 R&B WB Bageshwar See Pic
19.07-01-201607+500Road Surface after Laying RBI 81Rishi RamQCDSC5 R&B WB Bageshwar See Pic
20.07-01-201607+670RBI 81 in progressRishi RamQCDSC5 R&B WB Bageshwar See Pic