Kameridevi Syakot Motor road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1122 |
Sanction Cost: |
256.75 lakh |
Length:
|
9.500 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 45
Package Name: 
UDRP/PWD/08/06/RD/045
Tender Date: 19-04-2014
Current Status: Agreement signed
Achieved on Date: 13-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/045
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 20-11-2014
Intended Completion Date: 31-08-2017
Original End Date: 19-02-2016 |
Total Bond Cost: 41607857.19 (416.08 lakh)
Variation Cost: 21048924.06 (210.49 lakh) Hence Total Bond Cost is 62656781.25 (626.57 lakh)
|
Sub Project Cost: 77.57 lakh
Variation Cost of Sub Project: 13260723.35 (132.61 lakh)
Total Sub Project Cost:
210.18 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 686532 for 33 days
LD Analysis for Milestone2: calculated LD is Rs 2829344 for 136 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.20 KM | 9.69 | 21-04-2015 | 05-04-2016 | 0.20 KM | 0.20 KM | 3.69 | 9.69 | 2. | R/Wall, B/ Wall Type Protection works | 746.00 m | 28.42 | 20-11-2014 | 10-05-2017 | 746.00 m | 746.00 m | 10.83 | 28.42 | 3. | GSB/RBI/G-1 | 1.85 KM | 26.90 | 20-10-2015 | 15-11-2016 | 1.85 KM | 1.85 KM | 10.25 | 26.90 | 4. | G-2 | 0.00 KM | 0.00 | 04-04-2015 | 30-04-2015 | 0.00 KM | 0.00 KM | 0 | 0.00 | 5. | G-3 | 1.85 KM | 14.49 | 12-04-2015 | 05-05-2015 | 1.85 KM | 1.85 KM | 5.52 | 14.49 | 6. | PC/CC i/c Prime Coat, Tack Coat | 3.00 KM | 43.49 | 05-06-2016 | 10-05-2017 | 1.85 KM | 1.85 KM | 16.57 | 43.49 | 7. | Cause Way | 3.00 No | 43.49 | 01-03-2015 | 10-05-2017 | 3.00 No | 3.00 No | 16.57 | 43.49 | 8. | Culverts/Scupper | 9.00 No | 49.43 | 01-01-2015 | 28-02-2016 | 9.00 No | 9.00 No | 18.84 | 49.43 | 9. | longitudinal Drain | 2100.00 m | 4.13 | 01-05-2015 | 10-05-2017 | 2100.00 m | 2100.00 m | 1.57 | 4.13 | 10. | Crash Barrier | 40.00 m | 1.54 | 01-11-2015 | 10-05-2017 | 2114.00 m | 2114.00 m | 0.59 | 1.54 | 11. | Parapet | 75.00 No | 27.96 | 15-11-2016 | 15-05-2017 | 10.00 No | 10.00 No | 10.65 | 27.96 | 12. | Road Furniture | 62.00 No | 2.39 | 20-12-2015 | 15-05-2017 | 18.00 No | 18.00 No | 0.91 | 2.39 | 13. | Other Allied Works & Finishing Work | 3.00 Job | 10.51 | 25-11-2014 | 15-05-2017 | 3.00 Job | 3.00 Job | 4.01 | 10.51 |
Total Amount: |
262.44 |
|
100 |
262.44 |
|
Remarks:
No Remarks
Work Program Made On:
24-02-2015 } ?>
Updation of work program on:
14-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 26.25 lakh | 2. | 29-June-2015 | 9.27 lakh | 3. | 26-August-2015 | 16.87 lakh | 4. | 30-October-2015 | 29.54 lakh | 5. | 08-April-2016 | 0.05 lakh | 6. | 16-May-2016 | 14.03 lakh | 7. | 31-May-2016 | 4.78 lakh | 8. | 27-October-2016 | 44.85 lakh | 9. | 08-December-2016 | 0.09 lakh | 10. | 29-December-2016 | 4.09 lakh | 11. | 25-March-2017 | 27.27 lakh | 12. | 30-June-2017 | 0.60 lakh | 13. | 07-October-2017 | 93.43 lakh | 14. | 16-November-2018 | 0.34 lakh |
Total |
271.46 lakh |
% Payment | 129.16 % |
|
Advance Amount: 182.38 lakh
Recovered Amount: 182.39 lakh
Balance to be Recovered -0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 615 No. of Test Done : 570 No. of Test Passed : 544 No. of Test Failed : 26 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.30 |
Number of Notice(s) issued: 1 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 49 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 08-12-2016 | 7+500 | Pc & seal coat completed, shoulder work yet to be done. | Naresh Mittal | TL | DSC5 R&B WB Bageshwar | See Pic |
2. | 16-11-2016 | Ch 9.500 | End point of road | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 16-11-2016 | Ch 0.000 | Information board , correction required. | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 16-11-2016 | 0+000 | Project information board, provision of work PC & seal coat not a BM & SDBC | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
5. | 26-10-2016 | Ch 8.200 | Dismantling of kharanja , and instruct to do again. | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 26-10-2016 | Ch 8.200 | Dry kharanja rejected due to small size of stone and thickness not found OK. | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 26-10-2016 | Ch 5.400 | Rolling over premix carpet surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 26-10-2016 | 5.450 | Compacted thickness of PC , found 26 mm. | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 26-10-2016 | 5.450 | Laying temperature and found 119?. | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 26-10-2016 | Ch 5.400 | ROLLING over PC surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 17-10-2016 | Ch 7. 250 | Laying of screening material over G3 layer | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
12. | 15-03-2016 | 07+550 | Site Inspection of TL on PKG 45 | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
13. | 15-03-2016 | 07+700 | Site visit with TL Sir | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
14. | 13-01-2016 | Site Laboratory Bageshwar for Pkg 45 | Liquid limit test procedure of Soil use for Subgrade | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
15. | 13-01-2016 | Site Laboratory Bageshwar& sample collected from CH 07+755 | Liquid limit test of Soil use for Subgrade | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
16. | 12-01-2016 | 05+300 | forSite visit with TL,RE AE & RBI team (MR.Sanjay Kumar) discussion for RBI 81 | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
17. | 07-01-2016 | 05+500 | Site Instructions By EE world Bank at Site | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 07-01-2016 | 07+700 | RBI 81 work in progress | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 07-01-2016 | 07+500 | Road Surface after Laying RBI 81 | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 07-01-2016 | 07+670 | RBI 81 in progress | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|