Harinagri-Kulau-Gwaldam MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1118 |
Sanction Cost: |
956.10 lakh |
Length:
|
17.000 KM. |
District: |
Bageshwar |
Block: |
Garud |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 109
Package Name: 
UDRP/PWD/08/05/RD/98
Tender Date: 10-04-2015
Current Status: Agreement signed
Achieved on Date: 07-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/98
Contractor Name: Anil Malik Contractor
|
Start Date: 14-07-2015
Intended Completion Date: 31-12-2016
Original End Date: 13-10-2016 |
Total Bond Cost: 92930638.35 (929.31 lakh)
Variation Cost: 4331703.78 (43.32 lakh) Hence Total Bond Cost is 97262342.13 (972.62 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 1951530 for 42 days
LD Analysis for Milestone2: calculated LD is Rs 2044460 for 44 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.95 KM | 55.52 | 01-08-2015 | 31-12-2016 | 1.95 KM | 1.95 KM | 5.94 | 55.52 | 2. | R/Wall, B/ Wall Type Protection works | 1288.00 m | 171.56 | 01-08-2015 | 15-11-2016 | 1288.00 m | 1288.00 m | 18.36 | 171.56 | 3. | GSB/RBI/G-1 | 4.81 KM | 81.86 | 01-01-2016 | 30-10-2016 | 4.81 KM | 4.81 KM | 8.76 | 81.86 | 4. | G-3 | 13.40 KM | 94.76 | 01-03-2016 | 30-10-2016 | 13.40 KM | 13.40 KM | 10.14 | 94.76 | 5. | PC/CC i/c Prime Coat, Tack Coat | 15.10 KM | 214.25 | 15-03-2016 | 15-11-2016 | 15.10 KM | 15.10 KM | 22.93 | 214.25 | 6. | Cause Way | 1.00 No | 13.13 | 20-05-2015 | 15-06-2016 | 1.00 No | 1.00 No | 1.41 | 13.13 | 7. | Culverts/Scupper | 29.00 No | 108.47 | 01-08-2015 | 31-12-2016 | 29.00 No | 29.00 No | 11.61 | 108.47 | 8. | longitudinal Drain | 16930.00 m | 99.13 | 01-09-2015 | 30-11-2016 | 12468.00 m | 12468.00 m | 10.61 | 99.13 | 9. | Crash Barrier | 2230.00 m | 53.87 | 01-07-2016 | 31-12-2016 | 2230.00 m | 2230.00 m | 5.77 | 53.87 | 10. | Parapet | 390.00 No | 9.46 | 01-07-2016 | 30-09-2016 | 390.00 No | 390.00 No | 1.01 | 9.46 | 11. | Road Furniture | 3162.00 No | 20.46 | 01-08-2016 | 31-12-2016 | 3162.00 No | 3162.00 No | 2.19 | 20.46 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 11.97 | 15-02-2016 | 30-11-2016 | 1.00 Job | 1.00 Job | 1.28 | 11.97 |
Total Amount: |
934.44 |
|
100 |
934.44 |
|
Remarks:
No Remarks
Work Program Made On:
29-09-2015 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-October-2015 | 54.22 lakh | 2. | 23-December-2015 | 52.04 lakh | 3. | 06-January-2016 | 28.89 lakh | 4. | 01-February-2016 | 71.36 lakh | 5. | 28-March-2016 | 92.27 lakh | 6. | 31-May-2016 | 135.73 lakh | 7. | 09-August-2016 | 76.80 lakh | 8. | 29-September-2016 | 72.14 lakh | 9. | 22-October-2016 | 187.02 lakh | 10. | 08-December-2016 | 0.41 lakh | 11. | 21-December-2016 | 90.51 lakh | 12. | 02-February-2017 | 0.33 lakh | 13. | 09-February-2017 | 42.25 lakh | 14. | 08-September-2017 | 0.17 lakh | 15. | 18-September-2017 | 70.20 lakh | 16. | 16-November-2018 | 4.63 lakh |
Total |
978.97 lakh |
% Payment |
100.67 % |
|
Advance Amount: 402.76 lakh
Recovered Amount: 510.08 lakh
Balance to be Recovered -107.32 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 845 No. of Test Done : 830 No. of Test Passed : 806 No. of Test Failed : 24 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.16 |
Number of Notice(s) issued: 74 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 227 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-05-2017 | 12+760 | Slip clearance and drain Excavation required | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
2. | 09-01-2017 | Ch- 1+650 | Damaged exiting Culvert has been replaced by new Culvert. | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
3. | 19-11-2016 | Ch 5.800 | Causeway inspection by CE sir almora. | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 19-11-2016 | Ch 3.550 | Inspection of Lab by CE sir PWD (kumau)almora. | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 19-11-2016 | Ch 0.200 | PC thickness checking and found 20 mm. | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 19-11-2016 | Ch 0.00 | CE sir PWD almora inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 19-11-2016 | Ch-12+000 | PC completed and Seal coat being applied on last 300 m | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
8. | 16-11-2016 | Ch-17+075 | Seal coat laying over PC Surface | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
9. | 16-11-2016 | Ch-9+400 to 9+420 | B/ Wall including new road surface damaged by local in illegal way, | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
10. | 16-11-2016 | Ch-3+650 | Conducted Ambient Air quality test, Result awaited | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
11. | 16-11-2016 | At plant | Stock of Emulsion at HMP for use in prime coat & tack coat for Pkg 98 & 99 | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
12. | 03-11-2016 | Chainage 15+900 | Seal coat in progress during the site visit of DPM | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
13. | 03-11-2016 | Chainage 15+980 | PC thickness checked and found 33mm | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
14. | 03-11-2016 | Starting point | Road visited by DPM | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
15. | 03-11-2016 | HMP | DPM visited road | Manoj Bhatt | RE | DSC5 R&B WB Bageshwar | See Pic |
16. | 26-10-2016 | Ch-1+650 | Existing Culvert damage, repairing required. | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
17. | 19-10-2016 | Ch-2+935 | Loose Thickness of PMC 30mm | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
18. | 19-10-2016 | Ch-2+935 | PMC Laying and laying temperature found 103 °C | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
19. | 19-10-2016 | Ch- 2+925 | PMC Laying & quality is good | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 17-10-2016 | Ch 5.450 | Laying of P.Q.C on causeway | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
|
|