Dhlam Khunoli Motor Road Work Completed
Project: UDRP-RB UID: 1115 Sanction Cost: 369.85  lakh Length: 8.000 KM.
District: Bageshwar Block: Bageshwar Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 45        Package Name:  UDRP/PWD/08/06/RD/045        Tender Date: 19-04-2014        Current Status: Agreement signed        Achieved on Date: 13-11-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/045      Contractor Name: ESPAN Infrastructure Ltd
Start Date:  20-11-2014      Intended Completion Date:  31-08-2017      Original End Date:  19-02-2016
Total Bond Cost: 41607857.19 (416.08 lakh)        Variation Cost: 21048924.06 (210.49 lakh)    Hence Total Bond Cost is   62656781.25 (626.57 lakh) 
Sub Project Cost: 270.40  lakh        Variation Cost of Sub Project: 7788200.71  (77.88 lakh)       Total Sub Project Cost:   348.28 lakh
LD Analysis for Milestone1: calculated LD is Rs 686532 for 33 days        LD Analysis for Milestone2: calculated LD is Rs 2829344 for 136 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.58 KM15.3815-04-201531-01-20160.58 KM0.58 KM4.1815.38
2.R/Wall, B/ Wall Type Protection works830.00 m39.3420-11-201410-05-2017875.00 m875.00 m10.6839.34
3.GSB/RBI/G-15.00 KM32.8001-04-201515-11-20165.00 KM5.00 KM8.9132.80
4.G-25.00 KM24.3208-04-201525-11-20165.00 KM5.00 KM6.6124.32
5.G-35.00 KM27.3612-04-201525-11-20165.00 KM5.00 KM7.4327.36
6.PC/CC i/c Prime Coat, Tack Coat5.00 KM91.8715-05-201530-11-20165.00 KM5.00 KM24.9591.87
7.Cause Way4.00 No56.1202-11-201610-05-20173.00 No3.00 No15.2456.12
8.Culverts/Scupper 16.00 No49.0701-01-201528-02-201616.00 No16.00 No13.3349.07
9.longitudinal Drain3580.00 m5.1301-04-201510-05-20175000.00 m5000.00 m1.395.13
10.Crash Barrier40.00 m1.5425-11-201610-05-20171400.00 m1400.00 m0.421.54
11.Parapet75.00 No11.2215-11-201620-12-201656.00 No56.00 No3.0511.22
12.Road Furniture83.00 No2.5920-01-201515-05-201740.00 No40.00 No0.72.59
13.Other Allied Works & Finishing Work 4.00 Job11.4925-11-201415-05-20174.00 Job4.00 Job3.1211.49
Total Amount: 368.23 100   368.23
Remarks: No Remarks       Work Program Made On: 24-02-2015        Updation of work program on: 14-05-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-May-201530.42  lakh
2.29-June-201514.02  lakh
3.26-August-201538.81  lakh
4.30-October-201533.67  lakh
5.08-April-20160.05  lakh
6.16-May-201613.16  lakh
7.31-May-201628.49  lakh
8.30-July-201668.85  lakh
9.27-October-201610.63  lakh
10.29-December-201645.55  lakh
11.22-February-20170.29  lakh
12.25-March-201719.72  lakh
13.30-June-201760.78  lakh
14.07-October-20177.56  lakh
15.16-November-20180.37  lakh
Total 372.37  lakh
% Payment106.92 %
Advance Amount:  182.38  lakh        Recovered Amount:  182.39  lakh        Balance to be Recovered  -0.00  lakh        * Advances are at package level not sub project level
Analysis:Physical Progress Wrongly Reported.
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 615   No. of Test Done : 570    No. of Test Passed : 544   No. of Test Failed : 26   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 85.17
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 51
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.12-01-2017Ch 4.700Site inspection by EE sir PD PWD bageshwar.and SDM kanda .Jagdish Narayan Meenaunknownunknown See Pic
2.12-01-2017Ch 4.700PC thickness checking and found 25 mm. By EE sir PD bageshwar.Jagdish Narayan Meenaunknownunknown See Pic
3.12-01-2017Ch 2.280PC thickness checking by EE sir PWD PD bageshwar and EE pmgsy bageshwar. And found 22 mm.Jagdish Narayan Meenaunknownunknown See Pic
4.02-12-2016At plantBitumen extraction test of PC material and found 3.76%Jagdish Narayan Meenaunknownunknown See Pic
5.02-12-2016At plantBitumen extraction test of PC materialJagdish Narayan Meenaunknownunknown See Pic
6.28-11-2016At plantBinder content of PMC and found 3.75 %Mukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
7.22-11-2016Ch 5.200Rolling over seal coat .Jagdish Narayan Meenaunknownunknown See Pic
8.16-11-2016Ch 5.450Spreading of stone dust over G3 layerJagdish Narayan Meenaunknownunknown See Pic
9.16-11-2016Ch 5.350Total crust thickness checking and found 25 cm. Hence as per specification.Jagdish Narayan Meenaunknownunknown See Pic
10.16-11-2016Ch 5.200Total Crust thickness checking and found 26 cm.Jagdish Narayan Meenaunknownunknown See Pic
11.16-11-2016Ch 5.200Rolling over G3 surfaceJagdish Narayan Meenaunknownunknown See Pic
12.16-11-2016Ch 5.200Stone dust over G3 surface.Jagdish Narayan Meenaunknownunknown See Pic
13.16-11-2016Ch 8.00End point and project information board.Jagdish Narayan Meenaunknownunknown See Pic
14.16-11-2016End point of the RoadProject information boardMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
15.16-11-20164+055WBM GR 3 ready for PMCMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
16.17-10-2016Ch 8.00Site inspection E.E SirSanjeev BhattAEUDRP R&B Bageshwar See Pic
17.18-03-2016Ch 7.500Construction of R/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
18.16-03-2016Ch 6.210Collection of W.B.M (G2)Sanjeev BhattAEUDRP R&B Bageshwar See Pic
19.15-03-201603+960Site visit By TL sirRishi RamQCDSC5 R&B WB Bageshwar See Pic
20.15-03-201602+400Site visit with TL sir on Dhalan Khunoli MR PKG 45Rishi RamQCDSC5 R&B WB Bageshwar See Pic