Dhlam Khunoli Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1115 |
Sanction Cost: |
369.85 lakh |
Length:
|
8.000 KM. |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
Design and Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 45
Package Name: 
UDRP/PWD/08/06/RD/045
Tender Date: 19-04-2014
Current Status: Agreement signed
Achieved on Date: 13-11-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/045
Contractor Name: ESPAN Infrastructure Ltd
|
Start Date: 20-11-2014
Intended Completion Date: 31-08-2017
Original End Date: 19-02-2016 |
Total Bond Cost: 41607857.19 (416.08 lakh)
Variation Cost: 21048924.06 (210.49 lakh) Hence Total Bond Cost is 62656781.25 (626.57 lakh)
|
Sub Project Cost: 270.40 lakh
Variation Cost of Sub Project: 7788200.71 (77.88 lakh)
Total Sub Project Cost:
348.28 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 686532 for 33 days
LD Analysis for Milestone2: calculated LD is Rs 2829344 for 136 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.58 KM | 15.38 | 15-04-2015 | 31-01-2016 | 0.58 KM | 0.58 KM | 4.18 | 15.38 | 2. | R/Wall, B/ Wall Type Protection works | 830.00 m | 39.34 | 20-11-2014 | 10-05-2017 | 875.00 m | 875.00 m | 10.68 | 39.34 | 3. | GSB/RBI/G-1 | 5.00 KM | 32.80 | 01-04-2015 | 15-11-2016 | 5.00 KM | 5.00 KM | 8.91 | 32.80 | 4. | G-2 | 5.00 KM | 24.32 | 08-04-2015 | 25-11-2016 | 5.00 KM | 5.00 KM | 6.61 | 24.32 | 5. | G-3 | 5.00 KM | 27.36 | 12-04-2015 | 25-11-2016 | 5.00 KM | 5.00 KM | 7.43 | 27.36 | 6. | PC/CC i/c Prime Coat, Tack Coat | 5.00 KM | 91.87 | 15-05-2015 | 30-11-2016 | 5.00 KM | 5.00 KM | 24.95 | 91.87 | 7. | Cause Way | 4.00 No | 56.12 | 02-11-2016 | 10-05-2017 | 3.00 No | 3.00 No | 15.24 | 56.12 | 8. | Culverts/Scupper | 16.00 No | 49.07 | 01-01-2015 | 28-02-2016 | 16.00 No | 16.00 No | 13.33 | 49.07 | 9. | longitudinal Drain | 3580.00 m | 5.13 | 01-04-2015 | 10-05-2017 | 5000.00 m | 5000.00 m | 1.39 | 5.13 | 10. | Crash Barrier | 40.00 m | 1.54 | 25-11-2016 | 10-05-2017 | 1400.00 m | 1400.00 m | 0.42 | 1.54 | 11. | Parapet | 75.00 No | 11.22 | 15-11-2016 | 20-12-2016 | 56.00 No | 56.00 No | 3.05 | 11.22 | 12. | Road Furniture | 83.00 No | 2.59 | 20-01-2015 | 15-05-2017 | 40.00 No | 40.00 No | 0.7 | 2.59 | 13. | Other Allied Works & Finishing Work | 4.00 Job | 11.49 | 25-11-2014 | 15-05-2017 | 4.00 Job | 4.00 Job | 3.12 | 11.49 |
Total Amount: |
368.23 |
|
100 |
368.23 |
|
Remarks:
No Remarks
Work Program Made On:
24-02-2015 } ?>
Updation of work program on:
14-05-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-May-2015 | 30.42 lakh | 2. | 29-June-2015 | 14.02 lakh | 3. | 26-August-2015 | 38.81 lakh | 4. | 30-October-2015 | 33.67 lakh | 5. | 08-April-2016 | 0.05 lakh | 6. | 16-May-2016 | 13.16 lakh | 7. | 31-May-2016 | 28.49 lakh | 8. | 30-July-2016 | 68.85 lakh | 9. | 27-October-2016 | 10.63 lakh | 10. | 29-December-2016 | 45.55 lakh | 11. | 22-February-2017 | 0.29 lakh | 12. | 25-March-2017 | 19.72 lakh | 13. | 30-June-2017 | 60.78 lakh | 14. | 07-October-2017 | 7.56 lakh | 15. | 16-November-2018 | 0.37 lakh |
Total |
372.37 lakh |
% Payment | 106.92 % |
|
Advance Amount: 182.38 lakh
Recovered Amount: 182.39 lakh
Balance to be Recovered -0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Physical Progress Wrongly Reported. | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 615 No. of Test Done : 570 No. of Test Passed : 544 No. of Test Failed : 26 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 85.17 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 51 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 12-01-2017 | Ch 4.700 | Site inspection by EE sir PD PWD bageshwar.and SDM kanda . | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 12-01-2017 | Ch 4.700 | PC thickness checking and found 25 mm. By EE sir PD bageshwar. | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 12-01-2017 | Ch 2.280 | PC thickness checking by EE sir PWD PD bageshwar and EE pmgsy bageshwar. And found 22 mm. | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 02-12-2016 | At plant | Bitumen extraction test of PC material and found 3.76% | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 02-12-2016 | At plant | Bitumen extraction test of PC material | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 28-11-2016 | At plant | Binder content of PMC and found 3.75 % | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
7. | 22-11-2016 | Ch 5.200 | Rolling over seal coat . | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 16-11-2016 | Ch 5.450 | Spreading of stone dust over G3 layer | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 16-11-2016 | Ch 5.350 | Total crust thickness checking and found 25 cm. Hence as per specification. | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 16-11-2016 | Ch 5.200 | Total Crust thickness checking and found 26 cm. | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 16-11-2016 | Ch 5.200 | Rolling over G3 surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 16-11-2016 | Ch 5.200 | Stone dust over G3 surface. | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 16-11-2016 | Ch 8.00 | End point and project information board. | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 16-11-2016 | End point of the Road | Project information board | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
15. | 16-11-2016 | 4+055 | WBM GR 3 ready for PMC | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
16. | 17-10-2016 | Ch 8.00 | Site inspection E.E Sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
17. | 18-03-2016 | Ch 7.500 | Construction of R/Wall | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
18. | 16-03-2016 | Ch 6.210 | Collection of W.B.M (G2) | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
19. | 15-03-2016 | 03+960 | Site visit By TL sir | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
20. | 15-03-2016 | 02+400 | Site visit with TL sir on Dhalan Khunoli MR PKG 45 | Rishi Ram | QC | DSC5 R&B WB Bageshwar | See Pic |
|
|