Bhyun- Gadera Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1113 |
Sanction Cost: |
514.16 lakh |
Length:
|
7.000 KM. |
District: |
Bageshwar |
Block: |
Kapkot |
Constituency: |
Kapkote |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 37
Package Name: 
UDRP/PWD/08/06/RD/037
Tender Date: 27-03-2014
Current Status: Agreement signed
Achieved on Date: 15-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/06/RD/037
Contractor Name: Dwarika Projects Limited
|
Start Date: 22-09-2014
Intended Completion Date: 31-07-2016
Original End Date: 22-12-2015 |
Total Bond Cost: 82967179.7 (829.67 lakh)
Variation Cost: 3700237.83 (37 lakh) Hence Total Bond Cost is 86667417.53 (866.67 lakh)
|
Sub Project Cost: 400.28 lakh
Variation Cost of Sub Project: 13356181.05 (133.56 lakh)
Total Sub Project Cost:
533.84 lakh
|
LD Analysis for Milestone1: calculated LD is Rs 5558856 for 134 days
LD Analysis for Milestone2: calculated LD is Rs 1866780 for 45 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.88 KM | 25.38 | 01-12-2014 | 30-03-2016 | 1.88 KM | 1.88 KM | 4.76 | 25.38 | 2. | R/Wall, B/ Wall Type Protection works | 1720.00 m | 161.58 | 22-09-2014 | 28-02-2016 | 1720.00 m | 1720.00 m | 30.27 | 161.58 | 3. | GSB/RBI/G-1 | 4.40 KM | 25.07 | 15-04-2015 | 30-05-2016 | 4.40 KM | 4.40 KM | 4.7 | 25.07 | 4. | G-2 | 4.40 KM | 44.19 | 22-04-2015 | 30-05-2016 | 4.40 KM | 4.40 KM | 8.28 | 44.19 | 5. | G-3 | 4.40 KM | 25.99 | 10-05-2015 | 30-05-2016 | 4.40 KM | 4.40 KM | 4.87 | 25.99 | 6. | PC/CC i/c Prime Coat, Tack Coat | 4.30 KM | 65.76 | 01-06-2015 | 31-07-2016 | 4.30 KM | 4.30 KM | 12.32 | 65.76 | 7. | Cause Way | 4.00 No | 35.97 | 01-09-2015 | 30-05-2016 | 4.00 No | 4.00 No | 6.74 | 35.97 | 8. | Culverts/Scupper | 15.00 No | 62.19 | 10-01-2015 | 31-01-2016 | 15.00 No | 15.00 No | 11.65 | 62.19 | 9. | longitudinal Drain | 3200.00 m | 19.31 | 30-04-2015 | 30-06-2016 | 3200.00 m | 3200.00 m | 3.62 | 19.31 | 10. | Crash Barrier | 300.00 m | 31.10 | 01-07-2015 | 15-05-2016 | 300.00 m | 300.00 m | 5.83 | 31.10 | 11. | Parapet | 55.00 No | 7.16 | 01-08-2015 | 15-05-2016 | 55.00 No | 55.00 No | 1.34 | 7.16 | 12. | Road Furniture | 78.00 No | 5.63 | 01-11-2015 | 31-07-2016 | 78.00 No | 78.00 No | 1.05 | 5.63 | 13. | Other Allied Works & Finishing Work | 5.00 Job | 24.51 | 15-02-2016 | 30-11-2016 | 5.00 Job | 5.00 Job | 4.59 | 24.51 |
Total Amount: |
533.84 |
|
100 |
533.84 |
|
Remarks:
No Remarks
Work Program Made On:
01-10-2014 } ?>
Updation of work program on:
28-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 28-February-2015 | 19.89 lakh | 2. | 28-May-2015 | 14.26 lakh | 3. | 29-June-2015 | 7.40 lakh | 4. | 28-August-2015 | 47.84 lakh | 5. | 30-October-2015 | 91.80 lakh | 6. | 29-February-2016 | 78.58 lakh | 7. | 08-April-2016 | 0.10 lakh | 8. | 31-May-2016 | 28.01 lakh | 9. | 30-July-2016 | 100.74 lakh | 10. | 31-March-2017 | 42.64 lakh |
Total |
431.26 lakh |
% Payment | 80.78 % |
|
Advance Amount: 379.76 lakh
Recovered Amount: 379.76 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 730 No. of Test Done : 724 No. of Test Passed : 691 No. of Test Failed : 33 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 87.60 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 71 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 30-04-2017 | Ch 3.950 | Plum protecting work completed | Jagdish Narayan Meena | unknown | unknown | See Pic |
2. | 30-04-2017 | Ch 3.650 | Plum protecting work and crash barrier | Jagdish Narayan Meena | unknown | unknown | See Pic |
3. | 30-04-2017 | Ch 3.600 | Crash barrier | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 30-04-2017 | Ch 3.200 | B/wall with kc type drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 30-04-2017 | Ch 2.700 | Delinator, parapet on R/wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
6. | 30-04-2017 | Ch 2.400 | Delinator and parapet work completed | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 30-04-2017 | Ch 2.130 | Hair pin bends | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 30-04-2017 | Ch 2.100 | Road surface after installing Delinator and sign board | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 30-04-2017 | Ch 6.450 | Crash barrier | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 30-04-2017 | Ch 6.500 | End point information board, required correction | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 30-04-2017 | Ch 6.200 | Causeway and B/wall with kc type drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 30-04-2017 | Ch 5.475 | Road surface | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 30-04-2017 | Ch 5.400 | Plum protecting work and R/wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 30-04-2017 | Ch 3.950 | B/wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 30-04-2017 | Ch 3.900 | Road surface with kc type drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 30-04-2017 | Ch 3.800 | Crash barrier | Jagdish Narayan Meena | unknown | unknown | See Pic |
17. | 30-04-2017 | Ch 2.090 | Sign board and Delinator | Jagdish Narayan Meena | unknown | unknown | See Pic |
18. | 30-04-2017 | Ch 2.030 | Delinator | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 30-04-2017 | Ch 2.000 | B/wall with kc type drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
20. | 30-04-2017 | Ch 2.000 | Information board, required correction | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|