Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Bhyun- Gadera Motor Road Work Completed
Project: UDRP-RB UID: 1113 Sanction Cost: 514.16  lakh Length: 7.000 KM.
District: Bageshwar Block: Kapkot Constituency: Kapkote Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 37        Package Name:  UDRP/PWD/08/06/RD/037        Tender Date: 27-03-2014        Current Status: Agreement signed        Achieved on Date: 15-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/06/RD/037      Contractor Name: Dwarika Projects Limited
Start Date:  22-09-2014      Intended Completion Date:  31-07-2016      Original End Date:  22-12-2015
Total Bond Cost: 82967179.7 (829.67 lakh)        Variation Cost: 3700237.83 (37 lakh)    Hence Total Bond Cost is   86667417.53 (866.67 lakh) 
Sub Project Cost: 400.28  lakh        Variation Cost of Sub Project: 13356181.05  (133.56 lakh)       Total Sub Project Cost:   533.84 lakh
LD Analysis for Milestone1: calculated LD is Rs 5558856 for 134 days        LD Analysis for Milestone2: calculated LD is Rs 1866780 for 45 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence1.88 KM25.3801-12-201430-03-20161.88 KM1.88 KM4.7625.38
2.R/Wall, B/ Wall Type Protection works1720.00 m161.5822-09-201428-02-20161720.00 m1720.00 m30.27161.58
3.GSB/RBI/G-14.40 KM25.0715-04-201530-05-20164.40 KM4.40 KM4.725.07
4.G-24.40 KM44.1922-04-201530-05-20164.40 KM4.40 KM8.2844.19
5.G-34.40 KM25.9910-05-201530-05-20164.40 KM4.40 KM4.8725.99
6.PC/CC i/c Prime Coat, Tack Coat4.30 KM65.7601-06-201531-07-20164.30 KM4.30 KM12.3265.76
7.Cause Way4.00 No35.9701-09-201530-05-20164.00 No4.00 No6.7435.97
8.Culverts/Scupper 15.00 No62.1910-01-201531-01-201615.00 No15.00 No11.6562.19
9.longitudinal Drain3200.00 m19.3130-04-201530-06-20163200.00 m3200.00 m3.6219.31
10.Crash Barrier300.00 m31.1001-07-201515-05-2016300.00 m300.00 m5.8331.10
11.Parapet55.00 No7.1601-08-201515-05-201655.00 No55.00 No1.347.16
12.Road Furniture78.00 No5.6301-11-201531-07-201678.00 No78.00 No1.055.63
13.Other Allied Works & Finishing Work 5.00 Job24.5115-02-201630-11-20165.00 Job5.00 Job4.5924.51
Total Amount: 533.84 100   533.84
Remarks: No Remarks       Work Program Made On: 01-10-2014        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.28-February-201519.89  lakh
2.28-May-201514.26  lakh
3.29-June-20157.40  lakh
4.28-August-201547.84  lakh
5.30-October-201591.80  lakh
6.29-February-201678.58  lakh
7.08-April-20160.10  lakh
8.31-May-201628.01  lakh
9.30-July-2016100.74  lakh
10.31-March-201742.64  lakh
Total 431.26  lakh
% Payment80.78 %
Advance Amount:  379.76  lakh        Recovered Amount:  379.76  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 730   No. of Test Done : 724    No. of Test Passed : 691   No. of Test Failed : 33   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 87.60
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 71
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.30-04-2017Ch 3.950Plum protecting work completedJagdish Narayan Meenaunknownunknown See Pic
2.30-04-2017Ch 3.650Plum protecting work and crash barrierJagdish Narayan Meenaunknownunknown See Pic
3.30-04-2017Ch 3.600Crash barrierJagdish Narayan Meenaunknownunknown See Pic
4.30-04-2017Ch 3.200B/wall with kc type drainJagdish Narayan Meenaunknownunknown See Pic
5.30-04-2017Ch 2.700Delinator, parapet on R/wallJagdish Narayan Meenaunknownunknown See Pic
6.30-04-2017Ch 2.400Delinator and parapet work completedJagdish Narayan Meenaunknownunknown See Pic
7.30-04-2017Ch 2.130Hair pin bendsJagdish Narayan Meenaunknownunknown See Pic
8.30-04-2017Ch 2.100Road surface after installing Delinator and sign boardJagdish Narayan Meenaunknownunknown See Pic
9.30-04-2017Ch 6.450Crash barrierJagdish Narayan Meenaunknownunknown See Pic
10.30-04-2017Ch 6.500End point information board, required correctionJagdish Narayan Meenaunknownunknown See Pic
11.30-04-2017Ch 6.200Causeway and B/wall with kc type drainJagdish Narayan Meenaunknownunknown See Pic
12.30-04-2017Ch 5.475Road surfaceJagdish Narayan Meenaunknownunknown See Pic
13.30-04-2017Ch 5.400Plum protecting work and R/wallJagdish Narayan Meenaunknownunknown See Pic
14.30-04-2017Ch 3.950B/wallJagdish Narayan Meenaunknownunknown See Pic
15.30-04-2017Ch 3.900Road surface with kc type drainJagdish Narayan Meenaunknownunknown See Pic
16.30-04-2017Ch 3.800Crash barrierJagdish Narayan Meenaunknownunknown See Pic
17.30-04-2017Ch 2.090Sign board and DelinatorJagdish Narayan Meenaunknownunknown See Pic
18.30-04-2017Ch 2.030DelinatorJagdish Narayan Meenaunknownunknown See Pic
19.30-04-2017Ch 2.000B/wall with kc type drainJagdish Narayan Meenaunknownunknown See Pic
20.30-04-2017Ch 2.000Information board, required correctionJagdish Narayan Meenaunknownunknown See Pic