Dyangar-Kathyatbara-Aare bypass MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1106 |
Sanction Cost: |
585.88 lakh |
Length:
|
5.400 KM. |
District: |
Bageshwar |
Block: |
Bageshwar |
Constituency: |
Bageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 103
Package Name: 
UDRP/PWD/08/05/RD/092
Tender Date: 10-04-2015
Current Status: Agreement signed
Achieved on Date: 24-07-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/08/05/RD/092
Contractor Name: Neeraj Mishra
|
Start Date: 31-07-2015
Intended Completion Date: 15-12-2017
Original End Date: 30-10-2016 |
Total Bond Cost: 28989377.69 (289.89 lakh)
Variation Cost: 28659469.87 (286.59 lakh) Hence Total Bond Cost is 57648847.56 (576.49 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 101465 for 7 days
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 1.02 KM | 8.09 | 01-08-2015 | 30-04-2017 | 1.02 KM | 1.02 KM | 1.64 | 8.09 | 2. | R/Wall, B/ Wall Type Protection works | 945.00 m | 95.53 | 01-09-2015 | 15-10-2017 | 945.00 m | 945.00 m | 19.33 | 95.53 | 3. | GSB/RBI/G-1 | 1.16 KM | 13.11 | 01-12-2015 | 25-06-2017 | 1.16 KM | 1.16 KM | 2.65 | 13.11 | 4. | G-2 | 5.40 KM | 37.13 | 01-12-2015 | 25-06-2017 | 5.25 KM | 5.25 KM | 7.51 | 37.13 | 5. | G-3 | 5.40 KM | 38.63 | 01-09-2016 | 25-06-2017 | 5.25 KM | 5.25 KM | 7.82 | 38.63 | 6. | PC/CC i/c Prime Coat, Tack Coat | 0.00 KM | 0.00 | 15-09-2016 | 20-10-2016 | 0.00 KM | 0.00 KM | 0 | 0.00 | 7. | BM i/c Prime Coat, Tack Coat | 5.40 KM | 112.20 | 15-03-2017 | 30-06-2017 | 5.10 KM | 5.10 KM | 22.7 | 112.20 | 8. | SDBC i/c Tackcoat | 5.40 KM | 56.69 | 20-03-2017 | 30-06-2017 | 5.13 KM | 5.13 KM | 11.47 | 56.69 | 9. | Cause Way | 5.00 No | 23.21 | 01-08-2015 | 15-05-2017 | 3.00 No | 3.00 No | 4.7 | 23.21 | 10. | Culverts/Scupper | 10.00 No | 33.52 | 01-08-2015 | 31-05-2017 | 10.00 No | 10.00 No | 6.78 | 33.52 | 11. | longitudinal Drain | 5034.00 m | 8.06 | 01-08-2015 | 30-06-2017 | 5210.00 m | 5210.00 m | 1.63 | 8.06 | 12. | Crash Barrier | 0.00 m | 0.00 | 01-08-2016 | 01-08-2016 | 1000.00 m | 1000.00 m | 0 | 0.00 | 13. | Parapet | 100.00 No | 46.42 | 01-08-2016 | 25-06-2017 | 86.00 No | 86.00 No | 9.39 | 46.42 | 14. | Road Furniture | 220.00 No | 2.43 | 01-06-2016 | 15-10-2017 | 192.00 No | 192.00 No | 0.49 | 2.43 | 15. | Other Allied Works & Finishing Work | 5.00 Job | 19.26 | 01-08-2015 | 15-10-2017 | 5.00 Job | 5.00 Job | 3.9 | 19.26 |
Total Amount: |
494.28 |
|
100 |
494.28 |
|
Remarks:
No Remarks
Work Program Made On:
30-09-2015 } ?>
Updation of work program on:
09-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-October-2015 | 17.91 lakh | 2. | 30-November-2015 | 14.95 lakh | 3. | 11-January-2016 | 28.48 lakh | 4. | 01-February-2016 | 22.05 lakh | 5. | 28-March-2016 | 31.78 lakh | 6. | 31-May-2016 | 33.71 lakh | 7. | 30-July-2016 | 18.05 lakh | 8. | 29-September-2016 | 30.81 lakh | 9. | 24-October-2016 | 78.47 lakh | 10. | 16-December-2016 | 89.09 lakh | 11. | 23-December-2016 | 1.40 lakh | 12. | 02-February-2017 | 0.72 lakh | 13. | 08-March-2017 | 29.07 lakh | 14. | 27-April-2017 | 16.51 lakh | 15. | 07-June-2017 | 22.49 lakh | 16. | 25-August-2017 | 0.10 lakh | 17. | 11-October-2017 | 32.51 lakh | 18. | 24-November-2017 | 25.41 lakh | 19. | 15-December-2017 | 26.21 lakh | 20. | 21-March-2018 | 35.63 lakh | 21. | 20-April-2018 | 19.16 lakh | 22. | 16-November-2018 | 7.31 lakh |
Total |
581.82 lakh |
% Payment |
100.9 % |
|
Advance Amount: 136.21 lakh
Recovered Amount: 136.21 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 627 No. of Test Done : 602 No. of Test Passed : 581 No. of Test Failed : 21 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 84.26 |
Number of Notice(s) issued: 77 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 385 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 25-01-2018 | 0+001 | Grievance no.is changed | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
2. | 25-01-2018 | 1+010 | Crash barrier | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
3. | 25-01-2018 | 3+250 | Parapet white washing | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
4. | 25-01-2018 | 4+965 | R/w work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
5. | 25-01-2018 | 4+480 | Patch repair | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
6. | 25-01-2018 | 5+025 | Plum protection work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
7. | 25-01-2018 | 5+125 | Site visit by C.M.E sir & E.E sir | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
8. | 25-01-2018 | 5+225 | Plum protection work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
9. | 25-01-2018 | 5+230 | Pipe laying /shifting work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
10. | 24-01-2018 | 5+225 | Pipe laying/shifting work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
11. | 24-01-2018 | 4+200 | Pipe shifting | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
12. | 24-01-2018 | 4+900 | Subgrade filling | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
13. | 24-01-2018 | 5+200 | Toe wall construction work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
14. | 24-01-2018 | 5+200 | Toe wall construction work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
15. | 24-01-2018 | 4+950 | Pipe laying/shifting | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
16. | 24-01-2018 | 5+225 | Toe wall base construction for R/W | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
17. | 24-01-2018 | 5+100 | 150 mm.dia pipe for pipe shifting | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
18. | 10-10-2017 | 5+200 | Plum concrete work in progress for R/w base | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
19. | 10-10-2017 | 5+250 | R/W construction work in progress | Mukesh Kumar | JE | UDRP R&B Bageshwar | See Pic |
20. | 04-09-2017 | Ch 5.404 | Warning sign board | Jagdish Narayan Meena | unknown | unknown | See Pic |
|
|