Bageshwar-Girichhina MR Work Completed
Project: UDRP-RB UID: 1102 Sanction Cost: 1014.60  lakh Length: 13.400 KM.
District: Bageshwar Block: Bageshwar Constituency: Bageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 102        Package Name:  UDRP/PWD/08/05/RD/091        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 13-01-2016

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/08/05/RD/091      Contractor Name: Parihar Construction
Start Date:  20-01-2016      Intended Completion Date:  31-08-2017      Original End Date:  19-01-2017
Total Bond Cost: 46841261.26 (468.41 lakh)        Variation Cost: -2801363.78 (-28.01 lakh)    Hence Total Bond Cost is   44039897.48 (440.4 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 1147629 for 49 days        LD Analysis for Milestone2: calculated LD is Rs 3864465 for 165 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence5.00 KM75.2130-01-201630-05-20174.50 KM4.50 KM17.0875.21
2.R/Wall, B/ Wall Type Protection works1535.00 m143.9901-02-201630-08-20171535.00 m1535.00 m32.69143.99
3.GSB/RBI/G-15.00 KM27.2225-03-201620-06-20174.50 KM4.50 KM6.1827.22
4.G-25.00 KM27.6130-11-201630-06-20174.50 KM4.50 KM6.2727.61
5.G-35.00 KM35.0716-01-201730-06-20174.50 KM4.50 KM7.9635.07
6.PC/CC i/c Prime Coat, Tack Coat5.00 KM64.5615-03-201730-06-20174.50 KM4.50 KM14.6664.56
7.Cause Way1.00 No3.6925-10-201630-08-20172.00 No2.00 No0.843.69
8.Culverts/Scupper 10.00 No24.1301-02-201630-08-201714.00 No14.00 No5.4824.13
9.longitudinal Drain4844.00 m6.0501-01-201730-08-20174500.00 m4500.00 m1.376.05
10.Crash Barrier150.00 m4.1215-03-201730-08-20171000.00 m1000.00 m0.944.12
11.Parapet255.00 No7.8411-11-201630-08-201790.00 No90.00 No1.787.84
12.Road Furniture113.00 No1.7401-04-201730-08-201793.00 No93.00 No0.41.74
13.Other Allied Works & Finishing Work 3.00 Job19.1820-01-201630-08-20173.00 Job3.00 Job4.3619.18
Total Amount: 440.41 100   440.41
Remarks: No Remarks       Work Program Made On: 15-02-2016        Updation of work program on: 28-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.04-May-201664.12  lakh
2.28-June-201625.39  lakh
3.30-August-201623.97  lakh
4.24-October-201622.25  lakh
5.16-December-20162.64  lakh
6.06-February-201757.02  lakh
7.28-March-201779.15  lakh
8.29-June-2017109.71  lakh
9.28-March-201853.03  lakh
Total 437.28  lakh
% Payment 99.29 %
Advance Amount:  54.94  lakh        Recovered Amount:  54.94  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 332   No. of Test Done : 336    No. of Test Passed : 331   No. of Test Failed : 5   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 84.27
Number of Notice(s) issued: 55

Mobile Pic Upload

Number of Pics Available on Web Repository: 112
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.21-08-2017Ch 13.900B/wall constructionJagdish Narayan Meenaunknownunknown See Pic
2.21-08-2017Ch 14.060B/wallJagdish Narayan Meenaunknownunknown See Pic
3.21-08-2017Ch 14.200SRMD, heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
4.21-08-2017Ch 14.560SRMD, heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
5.01-08-2017Ch 14.200SRMD, road block due to heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
6.01-08-2017Ch 14.500SRMD, road damaged due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
7.01-08-2017Ch 14.500SRMD, road surface damaged due to heavy rainJagdish Narayan Meenaunknownunknown See Pic
8.01-08-2017Ch 14.240SRMD, road block due to heavy bouldersJagdish Narayan Meenaunknownunknown See Pic
9.12-06-2017Ch 12.750Tack coat for PCJagdish Narayan Meenaunknownunknown See Pic
10.11-06-2017Ch 12.700Rolling over seal coatJagdish Narayan Meenaunknownunknown See Pic
11.11-06-2017Ch 12.670Rolling over seal coatJagdish Narayan Meenaunknownunknown See Pic
12.11-06-2017Ch 12+770PC surfaceJagdish Narayan Meenaunknownunknown See Pic
13.11-06-2017Ch 12.720PC surfaceJagdish Narayan Meenaunknownunknown See Pic
14.11-06-2017Ch 12.700Rolling over PCJagdish Narayan Meenaunknownunknown See Pic
15.11-06-2017Ch 12.630Tack coat for PCJagdish Narayan Meenaunknownunknown See Pic
16.11-06-2017Ch 12.800PC surface after seal coatJagdish Narayan Meenaunknownunknown See Pic
17.08-06-201713+960Seal coat work in progressMohd Irfan QureshiQCDSC5 R&B WB Bageshwar See Pic
18.08-06-201713+960Seal coat work in progressMohd Irfan QureshiQCDSC5 R&B WB Bageshwar See Pic
19.08-06-2017Ch 13.200Laying of PCJagdish Narayan Meenaunknownunknown See Pic
20.08-06-2017Ch 13.270PC surface after seal coatJagdish Narayan Meenaunknownunknown See Pic