Vishnath-Jaskot Road
Agreement signed
|
Project: |
UDRP-RB |
UID: |
1059 |
Sanction Cost: |
432.60 lakh |
Length:
|
8.000 KM. |
District: |
Almora |
Block: |
Lamgarha |
Constituency: |
Jageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 147
Package Name: 
UDRP/PWD/09/01/RD/013(N)
Tender Date: 11-06-2018
Current Status: Agreement signed
Achieved on Date: 22-10-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/01/RD/013(N)
Contractor Name: Technical Consultant and Construction Associates
|
Start Date: 30-10-2018
Intended Completion Date: 30-11-2019
Original End Date: 29-06-2019 |
Total Bond Cost: 40389569.89 (403.9 lakh)
Variation Cost: 546545.88 (5.47 lakh) Hence Total Bond Cost is 40936115.77 (409.36 lakh)
|
Sub Project Cost: 222.80 lakh
Variation Cost of Sub Project: 1258892.37 (12.59 lakh)
Total Sub Project Cost:
235.39 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.31 KM | 5.10 | 01-12-2018 | 15-06-2019 | 0.31 KM | 0.31 KM | 2.42 | 5.10 | 2. | R/Wall, B/ Wall Type Protection works | 270.00 m | 20.77 | 01-12-2018 | 10-06-2019 | 270.00 m | 270.00 m | 9.85 | 20.77 | 3. | G-2 | 2.75 KM | 33.17 | 30-01-2019 | 15-06-2019 | 3.00 KM | 2.75 KM | 14.42 | 30.40 | 4. | G-3 | 6.00 KM | 37.31 | 01-12-2018 | 20-06-2019 | 6.00 KM | 5.75 KM | 16.96 | 35.76 | 5. | PC/CC i/c Prime Coat, Tack Coat | 7.85 KM | 60.86 | 27-05-2019 | 28-06-2019 | 7.85 KM | 7.00 KM | 25.74 | 54.27 | 6. | Cause Way | 0.00 No | 0.00 | 05-04-2019 | 10-06-2019 | 4.00 No | 0.00 No | 0 | 0.00 | 7. | Culverts/Scupper | 5.00 No | 16.44 | 01-12-2018 | 10-06-2019 | 5.00 No | 5.00 No | 7.8 | 16.44 | 8. | longitudinal Drain | 7250.00 m | 8.44 | 15-12-2018 | 15-06-2019 | 7250.00 m | 7250.00 m | 4 | 8.44 | 9. | Crash Barrier | 250.00 m | 9.13 | 01-05-2019 | 15-06-2019 | 250.00 m | 250.00 m | 4.33 | 9.13 | 10. | Parapet | 104.00 No | 2.42 | 01-04-2019 | 20-06-2019 | 104.00 No | 104.00 No | 1.15 | 2.42 | 11. | Road Furniture | 295.00 No | 1.88 | 15-05-2019 | 20-06-2019 | 295.00 No | 295.00 No | 0.89 | 1.88 | 12. | Env. Man & Moni Plan | 1.00 Job | 3.05 | 15-12-2018 | 20-06-2019 | 1.00 Job | 1.00 Job | 1.45 | 3.05 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 12.30 | 01-12-2018 | 20-06-2019 | 1.00 Job | 1.00 Job | 5.83 | 12.30 |
Total Amount: |
210.87 |
|
94.83 |
199.96 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2018 } ?>
Updation of work program on:
15-03-2021
|
|
Work Program Status:Program Expired. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 30-October-2015 | 17.41 lakh | 2. | 16-December-2015 | 23.45 lakh | 3. | 27-January-2016 | 23.35 lakh | 4. | 19-March-2016 | 2.72 lakh | 5. | 08-April-2016 | 0.10 lakh | 6. | 28-June-2016 | 4.51 lakh | 7. | 20-December-2016 | 0.47 lakh | 8. | 12-January-2017 | 15.68 lakh | 9. | 18-January-2017 | 1.66 lakh | 10. | 02-February-2017 | 19.83 lakh | 11. | 07-March-2017 | 12.27 lakh |
Previous Package Expenditure Total |
121.45 lakh |
SNo. |
Date |
Payment |
1. | 15-February-2019 | 19.81 lakh | 2. | 18-March-2019 | 16.78 lakh | 3. | 17-May-2019 | 9.86 lakh | 4. | 03-June-2019 | 15.57 lakh | 5. | 21-June-2019 | 20.71 lakh | 6. | 25-June-2019 | 13.22 lakh | 7. | 29-June-2019 | 15.62 lakh | 8. | 20-September-2019 | 38.69 lakh |
Total |
150.26 lakh |
% Payment | 63.83 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Analysis:Bill sh
ould be issued | Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
Environment & Social Compliances(Package level):
No Pending Issue
Environment & Social Compliances(Sub Project level):
EMP Land Owner Consent, Glove, water sprinkling, debris disposal |
Detailed report of this subproject
|
|
Quality
|
No. of Test Required : 20 No. of Test Done : 20 No. of Test Passed : 20 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 86.37 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 101 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 06-11-2019 | 7+600 | World bank mission visit.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
2. | 06-11-2019 | 7+500 | World Bank mission visit.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
3. | 25-04-2019 | Ch 5.600 | CE sir, SE sir and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
4. | 25-04-2019 | Ch 5.600 | CE sir, SE sir and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
5. | 28-02-2019 | 1+325 | Rolling over G-3.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
6. | 28-02-2019 | 1+300 | Rolling over G-3.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
7. | 14-07-2017 | 5+750 | SRMD
SLIP CLEARANCE | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
8. | 14-07-2017 | 5+700 | SRMD
Slip clearance...
Road blocked due to heavy Rainfall.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
9. | 06-06-2017 | 5+750 | SRMD
Slip Due to heavy Rainfall.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
10. | 06-06-2017 | 6+020 | Laying Of G3
The progress of work is too slow
Only 12 Labours Found Today.
Contractor doesn't increase the labour after too many instructions | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
11. | 29-05-2017 | 5.750 | Slip due to Rainfall.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
12. | 29-05-2017 | 4.5 | Damaged RBI-81 due to Rainfall
The contractor doesn't do work Rapidly to Cover RBI-81 with G-3
Only 12 Labours are present today on site.
And only 200 RBI-81 is covered with G-3 in last 20 days | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
13. | 27-05-2017 | 4.3 | Damaged RBI-81 Due to rain
The contractor doesn't do work properly to cover RBI-81 With G-3...
Only 12 Labours are here Today... | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
14. | 18-05-2017 | Contractors site Laboratory | AIV Test of WBM G3 Material | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
15. | 18-05-2017 | 6+040 | Sample collection for AIV Test of stocked WBM Gr-3 metal. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
16. | 18-05-2017 | 3+950 | Machine engaged for defect cutting is not competent. contractor is instructed to use chisel breaker arrangement for rock cutting. | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
17. | 14-05-2017 | 4.550 | Give instructions for hill side defect cutting. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
18. | 04-05-2017 | Ch 3.350 | Defect cutting balance. | Jagdish Narayan Meena | unknown | unknown | See Pic |
19. | 03-05-2017 | 3+400 | Defect cutting balance up to till date | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
20. | 03-05-2017 | Chainage 4+700 | Public consultation for work site regarding problems | Manoj Bhatt | RE | DSC2 R&B WB Pauri | See Pic |
|
|