Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Mornaula-Jainti Motor Raod Work Completed
Project: UDRP-RB UID: 1057 Sanction Cost: 915.78  lakh Length: 13.000 KM.
District: Almora Block: Lamgarha Constituency: Jageshwar Circle: Pithoragarh WB Circle
DEA: DEA Nanital DSC: Royal Haskoning DHV DSC Scope: Design and Supervision Type: VR
Procurement:
Package No.: 127        Package Name:  UDRP/PWD/09/01/RD/116        Tender Date: 27-06-2015        Current Status: Agreement signed        Achieved on Date: 02-12-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/01/RD/116      Contractor Name: M/S.Dalip Singh Adhikari
Start Date:  09-12-2015      Intended Completion Date:  08-03-2017     
Total Bond Cost: 88936492.01 (889.36 lakh)        Variation Cost: 70382.40 (0.7 lakh)    Hence Total Bond Cost is   89006874.41 (890.07 lakh) 
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence2.10 KM18.9409-12-201510-12-20162.10 KM2.10 KM2.1318.94
2.R/Wall, B/ Wall Type Protection works2176.00 m246.8209-12-201515-11-20162176.00 m2176.00 m27.73246.82
3.GSB/RBI/G-10.81 KM7.9501-08-201615-08-20160.81 KM0.81 KM0.897.95
4.G-20.62 KM4.4105-08-201615-08-20160.62 KM0.62 KM0.54.41
5.G-32.36 KM14.1501-06-201631-12-20162.36 KM2.36 KM1.5914.15
6.PC/CC i/c Prime Coat, Tack Coat13.02 KM245.9405-06-201630-11-201613.02 KM13.02 KM27.63245.94
7.Cause Way0.00 No0.0001-03-201631-07-20160.00 No0.00 No00.00
8.Culverts/Scupper 33.00 No229.0125-02-201601-09-201633.00 No33.00 No25.73229.01
9.longitudinal Drain12705.00 m46.2701-06-201615-11-201612705.00 m12705.00 m5.246.27
10.Crash Barrier0.00 m0.0015-01-201631-10-20160.00 m0.00 m00.00
11.Parapet2200.00 No51.6901-08-201630-10-20162200.00 No2200.00 No5.8151.69
12.Road Furniture2676.00 No15.5001-12-201628-02-20172676.00 No2676.00 No1.7415.50
13.Other Allied Works & Finishing Work 2.00 Job9.3815-10-201631-01-20172.00 Job2.00 Job1.059.38
Total Amount: 890.06 100   890.06
Remarks:        Work Program Made On: 26-12-2015        Updation of work program on: 13-08-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.07-January-201621.91  lakh
2.30-January-201656.98  lakh
3.29-February-201670.48  lakh
4.31-March-201662.68  lakh
5.11-May-201682.63  lakh
6.31-May-201659.91  lakh
7.30-June-201639.97  lakh
8.30-July-201614.16  lakh
9.04-October-201633.82  lakh
10.20-October-2016108.51  lakh
11.26-October-201666.42  lakh
12.08-December-201686.17  lakh
13.11-January-201789.50  lakh
14.29-March-201795.98  lakh
Total 889.12  lakh
% Payment 99.88 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 641   No. of Test Done : 655    No. of Test Passed : 628   No. of Test Failed : 27   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 90.00
Number of Notice(s) issued: 76

Mobile Pic Upload

Number of Pics Available on Web Repository: 55
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.08-12-201711+900Inspection of CEAshvani KumarJEUDRP R&B Nainital See Pic
2.02-08-201710+100PlantationAshvani KumarJEUDRP R&B Nainital See Pic
3.02-08-201710+ 000PlantationAshvani KumarJEUDRP R&B Nainital See Pic
4.02-08-201710+150PlantationAshvani KumarJEUDRP R&B Nainital See Pic
5.15-05-20170+050Site visit of world bankDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
6.21-11-201610+200Laying of sdbcDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
7.21-11-20161+600While washing Of parapetDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
8.11-11-20164+360Sdbc work , satisfactoryNaresh MittalTLDSC5 R&B WB Bageshwar See Pic
9.11-11-2016Plant siteChucking sdbc material at plant siteDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
10.10-11-2016At PlantBitumen extraction test for sdbc Results satisfactory found 5.11%Naveen ShuklaQCDSC5 R&B WB Almora See Pic
11.10-11-20163+900Laying of SDBC work satisfactoryNaveen ShuklaQCDSC5 R&B WB Almora See Pic
12.09-11-2016At plantBitumen extraction test for BM Results satisfactory found 3.5%Naveen ShuklaQCDSC5 R&B WB Almora See Pic
13.09-11-2016At PlantBitumen extraction test for sdbc Results satisfactory found 5.12%Naveen ShuklaQCDSC5 R&B WB Almora See Pic
14.25-10-2016Ch.7+100Laying of SDBC (Quality satisfactory )Naveen ShuklaQCDSC5 R&B WB Almora See Pic
15.23-10-2016CH.7+950Laying of SDBC (Quality good)Naveen ShuklaQCDSC5 R&B WB Almora See Pic
16.22-10-20160+350Laying of sdbcDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
17.22-10-20160+000Laying of sdbcDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic
18.21-10-2016Completed sdbc work at junction in pkg- 116Completed sdbc work at junction of Mornula _jainti m/r and SH.Naresh MittalTLDSC5 R&B WB Bageshwar See Pic
19.16-10-20160+000 of Mornula - jainti M/RJunction of SH and Mornula - jainti M/RNaresh MittalTLDSC5 R&B WB Bageshwar See Pic
20.02-06-20165+940Construction of coolie wallDharmendra Kumar SinghREDSC5 R&B WB Nainital See Pic