Khunt -Almora Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1055 |
Sanction Cost: |
124.63 lakh |
Length:
|
11.500 KM. |
District: |
Almora |
Block: |
Hawal Bagh |
Constituency: |
Someshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 62
Package Name: 
UDRP/PWD/09/01/RD/013 (a)
Tender Date: 20-11-2014
Current Status: Agreement signed
Achieved on Date: 18-06-2015 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/01/RD/013 (a)
Contractor Name: Jagat Singh Kanwal
|
Start Date: 24-06-2015
Intended Completion Date: 23-09-2016
|
Total Bond Cost: 12463320.3 (124.63 lakh)
Variation Cost: -5028335.44 (-50.28 lakh) Hence Total Bond Cost is 7434984.86 (74.35 lakh)
|
LD Analysis for Milestone1: calculated LD is Rs 280440 for 45 days
LD Analysis for Milestone2: calculated LD is Rs 523488 for 84 days
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 273.00 m | 26.20 | 27-07-2015 | 30-07-2016 | 273.00 m | 273.00 m | 35.34 | 26.20 | 2. | G-3 | 0.10 KM | 0.79 | 01-09-2016 | 20-09-2016 | 0.10 KM | 0.10 KM | 1.07 | 0.79 | 3. | PC/CC i/c Prime Coat, Tack Coat | 0.10 KM | 1.24 | 10-09-2016 | 23-09-2016 | 0.10 KM | 0.10 KM | 1.67 | 1.24 | 4. | Cause Way | 1.00 No | 0.98 | 01-07-2016 | 30-07-2016 | 1.00 No | 1.00 No | 1.32 | 0.98 | 5. | Culverts/Scupper | 9.00 No | 18.84 | 02-08-2015 | 30-07-2016 | 9.00 No | 9.00 No | 25.42 | 18.84 | 6. | longitudinal Drain | 5455.00 m | 5.35 | 01-11-2015 | 15-08-2016 | 5455.00 m | 5455.00 m | 7.21 | 5.35 | 7. | Crash Barrier | 544.00 m | 13.52 | 25-06-2016 | 02-09-2016 | 544.00 m | 544.00 m | 18.24 | 13.52 | 8. | Parapet | 94.00 No | 3.48 | 15-07-2016 | 20-08-2016 | 94.00 No | 94.00 No | 4.7 | 3.48 | 9. | Road Furniture | 64.00 No | 2.45 | 19-08-2016 | 15-09-2016 | 64.00 No | 64.00 No | 3.31 | 2.45 | 10. | Other Allied Works & Finishing Work | 1.00 Job | 1.28 | 19-08-2016 | 15-09-2016 | 1.00 Job | 1.00 Job | 1.73 | 1.28 |
Total Amount: |
74.13 |
|
100 |
74.13 |
|
Remarks:
No Remarks
Work Program Made On:
03-10-2015 } ?>
Updation of work program on:
27-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-December-2015 | 19.99 lakh | 2. | 19-March-2016 | 21.33 lakh | 3. | 22-July-2016 | 21.89 lakh | 4. | 18-November-2016 | 4.40 lakh | 5. | 13-April-2017 | 6.73 lakh |
Total |
74.34 lakh |
% Payment |
99.99 % |
|
Advance Amount: 10.00 lakh
Recovered Amount: 10.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 171 No. of Test Done : 170 No. of Test Passed : 159 No. of Test Failed : 11 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.29 |
Number of Notice(s) issued: 72 |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 41 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 22-11-2016 | Ch-8+010 | Culvert inspection by SE NH haldwani | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
2. | 22-11-2016 | Ch-7+725 | Culvert inspection by SE NH haldwani | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
3. | 28-09-2016 | Ch-8+450 | PMC Laying ragected Because only 10 mm aggregate are used | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
4. | 04-09-2016 | Ch-1+350 | Existing Causeway inspection by AE & RE Sir | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
5. | 02-09-2016 | Ch-5+075 | Site inspection by Re | Mukesh Kumar Yadav 2 | QC | DSC5 R&B WB Bageshwar | See Pic |
6. | 09-07-2016 | Ch 8.950 | Parapat complete | Jagdish Narayan Meena | unknown | unknown | See Pic |
7. | 09-07-2016 | Ch 8.290 | Parapat construction | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 14-06-2016 | Ch 8.450 | Y p joshi sir visit | Jagdish Narayan Meena | unknown | unknown | See Pic |
9. | 27-04-2016 | Ch 4.900 | Inspection by YP joshi sir ,EE sir & TL sir | Jagdish Narayan Meena | unknown | unknown | See Pic |
10. | 04-01-2016 | Ch 8.000 | Excavation for scupper | Jagdish Narayan Meena | unknown | unknown | See Pic |
11. | 04-01-2016 | Ch 8.950 | Kuchha drain | Jagdish Narayan Meena | unknown | unknown | See Pic |
12. | 04-01-2016 | Ch 8.025 | Dressing of stone for r/wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 04-01-2016 | Ch 4.900 | R/wall banded completed | Jagdish Narayan Meena | unknown | unknown | See Pic |
14. | 04-01-2016 | Ch 4.900 | Bed block curing | Jagdish Narayan Meena | unknown | unknown | See Pic |
15. | 07-11-2015 | Ch 6.225 | Dry R/wall | Jagdish Narayan Meena | unknown | unknown | See Pic |
16. | 03-10-2015 | 9.00 | Meeting | Subhash Kumar | Site Engineer | DSC5 R&B WB Almora | See Pic |
17. | 03-10-2015 | 8.925 | R/w | Subhash Kumar | Site Engineer | DSC5 R&B WB Almora | See Pic |
18. | 03-10-2015 | 8.950 | Social expert visit and r/w | Narendra Singh | JE | UDRP R&B Bageshwar | See Pic |
19. | 22-09-2015 | 8.925 | Scrupper work | Narendra Singh | JE | UDRP R&B Bageshwar | See Pic |
20. | 16-09-2015 | 8.950 | Retaining wall | Prateek Gupta | Site Engineer | DSC5 R&B WB Almora | See Pic |
|
|