Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Khunt -Almora Road Work Completed
Project: UDRP-RB UID: 1055 Sanction Cost: 124.63  lakh Length: 11.500 KM.
District: Almora Block: Hawal Bagh Constituency: Someshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 62        Package Name:  UDRP/PWD/09/01/RD/013 (a)        Tender Date: 20-11-2014        Current Status: Agreement signed        Achieved on Date: 18-06-2015

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/01/RD/013 (a)      Contractor Name: Jagat Singh Kanwal
Start Date:  24-06-2015      Intended Completion Date:  23-09-2016     
Total Bond Cost: 12463320.3 (124.63 lakh)        Variation Cost: -5028335.44 (-50.28 lakh)    Hence Total Bond Cost is   7434984.86 (74.35 lakh) 
LD Analysis for Milestone1: calculated LD is Rs 280440 for 45 days        LD Analysis for Milestone2: calculated LD is Rs 523488 for 84 days       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works273.00 m26.2027-07-201530-07-2016273.00 m273.00 m35.3426.20
2.G-30.10 KM0.7901-09-201620-09-20160.10 KM0.10 KM1.070.79
3.PC/CC i/c Prime Coat, Tack Coat0.10 KM1.2410-09-201623-09-20160.10 KM0.10 KM1.671.24
4.Cause Way1.00 No0.9801-07-201630-07-20161.00 No1.00 No1.320.98
5.Culverts/Scupper 9.00 No18.8402-08-201530-07-20169.00 No9.00 No25.4218.84
6.longitudinal Drain5455.00 m5.3501-11-201515-08-20165455.00 m5455.00 m7.215.35
7.Crash Barrier544.00 m13.5225-06-201602-09-2016544.00 m544.00 m18.2413.52
8.Parapet94.00 No3.4815-07-201620-08-201694.00 No94.00 No4.73.48
9.Road Furniture64.00 No2.4519-08-201615-09-201664.00 No64.00 No3.312.45
10.Other Allied Works & Finishing Work 1.00 Job1.2819-08-201615-09-20161.00 Job1.00 Job1.731.28
Total Amount: 74.13 100   74.13
Remarks: No Remarks       Work Program Made On: 03-10-2015        Updation of work program on: 27-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-December-201519.99  lakh
2.19-March-201621.33  lakh
3.22-July-201621.89  lakh
4.18-November-20164.40  lakh
5.13-April-20176.73  lakh
Total 74.34  lakh
% Payment 99.99 %
Advance Amount:  10.00  lakh        Recovered Amount:  10.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 171   No. of Test Done : 170    No. of Test Passed : 159   No. of Test Failed : 11   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.29
Number of Notice(s) issued: 72

Mobile Pic Upload

Number of Pics Available on Web Repository: 41
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.22-11-2016Ch-8+010Culvert inspection by SE NH haldwaniMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
2.22-11-2016Ch-7+725Culvert inspection by SE NH haldwaniMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
3.28-09-2016Ch-8+450PMC Laying ragected Because only 10 mm aggregate are usedMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
4.04-09-2016Ch-1+350Existing Causeway inspection by AE & RE SirMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
5.02-09-2016Ch-5+075Site inspection by ReMukesh Kumar Yadav 2QCDSC5 R&B WB Bageshwar See Pic
6.09-07-2016Ch 8.950Parapat completeJagdish Narayan Meenaunknownunknown See Pic
7.09-07-2016Ch 8.290Parapat constructionJagdish Narayan Meenaunknownunknown See Pic
8.14-06-2016Ch 8.450Y p joshi sir visitJagdish Narayan Meenaunknownunknown See Pic
9.27-04-2016Ch 4.900Inspection by YP joshi sir ,EE sir & TL sirJagdish Narayan Meenaunknownunknown See Pic
10.04-01-2016Ch 8.000Excavation for scupperJagdish Narayan Meenaunknownunknown See Pic
11.04-01-2016Ch 8.950Kuchha drainJagdish Narayan Meenaunknownunknown See Pic
12.04-01-2016Ch 8.025Dressing of stone for r/wallJagdish Narayan Meenaunknownunknown See Pic
13.04-01-2016Ch 4.900R/wall banded completedJagdish Narayan Meenaunknownunknown See Pic
14.04-01-2016Ch 4.900Bed block curingJagdish Narayan Meenaunknownunknown See Pic
15.07-11-2015Ch 6.225Dry R/wallJagdish Narayan Meenaunknownunknown See Pic
16.03-10-20159.00MeetingSubhash KumarSite EngineerDSC5 R&B WB Almora See Pic
17.03-10-20158.925R/wSubhash KumarSite EngineerDSC5 R&B WB Almora See Pic
18.03-10-20158.950Social expert visit and r/wNarendra SinghJEUDRP R&B Bageshwar See Pic
19.22-09-20158.925Scrupper workNarendra SinghJEUDRP R&B Bageshwar See Pic
20.16-09-20158.950Retaining wallPrateek GuptaSite EngineerDSC5 R&B WB Almora See Pic