Dhora-Ratankhan Motor Road
Work Completed
|
Project: |
UDRP-RB |
UID: |
1044 |
Sanction Cost: |
351.24 lakh |
Length:
|
5.850 KM. |
District: |
Almora |
Block: |
Lamgarha |
Constituency: |
Jageshwar |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
VR |
|
Procurement: |
Package No.: 147
Package Name: 
UDRP/PWD/09/01/RD/013(N)
Tender Date: 11-06-2018
Current Status: Agreement signed
Achieved on Date: 22-10-2018 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/01/RD/013(N)
Contractor Name: Technical Consultant and Construction Associates
|
Start Date: 30-10-2018
Intended Completion Date: 30-11-2019
Original End Date: 29-06-2019 |
Total Bond Cost: 40389569.89 (403.9 lakh)
Variation Cost: 546545.88 (5.47 lakh) Hence Total Bond Cost is 40936115.77 (409.36 lakh)
|
Sub Project Cost: 180.00 lakh
Variation Cost of Sub Project: -712346.49 (-7.12 lakh)
Total Sub Project Cost:
172.88 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 0.38 KM | 2.76 | 30-10-2018 | 25-06-2019 | 0.38 KM | 0.38 KM | 1.53 | 2.76 | 2. | R/Wall, B/ Wall Type Protection works | 330.00 m | 18.66 | 30-10-2018 | 31-01-2019 | 330.00 m | 330.00 m | 10.3 | 18.66 | 3. | G-2 | 0.50 KM | 5.87 | 30-11-2018 | 30-12-2018 | 0.50 KM | 0.50 KM | 3.24 | 5.87 | 4. | G-3 | 5.90 KM | 39.65 | 05-11-2018 | 20-02-2019 | 5.90 KM | 5.90 KM | 21.9 | 39.65 | 5. | PC/CC i/c Prime Coat, Tack Coat | 5.90 KM | 48.87 | 15-03-2019 | 15-06-2019 | 5.90 KM | 5.90 KM | 26.98 | 48.87 | 6. | Cause Way | 3.00 No | 15.20 | 28-11-2018 | 15-01-2019 | 3.00 No | 3.00 No | 8.39 | 15.20 | 7. | Culverts/Scupper | 8.00 No | 14.78 | 30-10-2018 | 30-01-2019 | 8.00 No | 8.00 No | 8.16 | 14.78 | 8. | longitudinal Drain | 4200.00 m | 6.26 | 10-12-2018 | 30-01-2019 | 4200.00 m | 4200.00 m | 3.46 | 6.26 | 9. | Crash Barrier | 250.00 m | 9.13 | 01-05-2019 | 15-06-2019 | 250.00 m | 250.00 m | 5.04 | 9.13 | 10. | Parapet | 150.00 No | 4.15 | 01-01-2019 | 30-03-2019 | 150.00 No | 150.00 No | 2.29 | 4.15 | 11. | Road Furniture | 285.00 No | 1.80 | 15-05-2019 | 25-06-2019 | 285.00 No | 285.00 No | 1 | 1.80 | 12. | Env. Man & Moni Plan | 1.00 Job | 3.05 | 15-12-2018 | 15-05-2019 | 1.00 Job | 1.00 Job | 1.68 | 3.05 | 13. | Other Allied Works & Finishing Work | 1.00 Job | 10.91 | 15-12-2018 | 15-05-2019 | 1.00 Job | 1.00 Job | 6.03 | 10.91 |
Total Amount: |
181.09 |
|
100 |
181.09 |
|
Remarks:
No Remarks
Work Program Made On:
17-11-2018 } ?>
Updation of work program on:
26-05-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 16-December-2015 | 10.89 lakh | 2. | 27-January-2016 | 18.02 lakh | 3. | 19-March-2016 | 14.39 lakh | 4. | 08-April-2016 | 0.05 lakh | 5. | 28-June-2016 | 16.09 lakh | 6. | 27-October-2016 | 9.76 lakh | 7. | 18-January-2017 | 11.43 lakh |
Previous Package Expenditure Total |
80.63 lakh |
SNo. |
Date |
Payment |
1. | 16-November-2018 | 33.66 lakh | 2. | 13-December-2018 | 24.50 lakh | 3. | 09-January-2019 | 27.48 lakh | 4. | 15-February-2019 | 30.36 lakh | 5. | 18-March-2019 | 2.03 lakh | 6. | 17-May-2019 | 45.68 lakh | 7. | 03-June-2019 | 15.35 lakh | 8. | 20-September-2019 | 2.28 lakh |
Total |
181.34 lakh |
% Payment | 104.89 % |
|
Advance Amount: 0.00 lakh
Recovered Amount: 0.00 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 20 No. of Test Done : 20 No. of Test Passed : 20 No. of Test Failed : 0 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 88.01 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 115 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 13-05-2019 | 1+600 | Rolling over p.c.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
2. | 13-05-2019 | 1+700 | Rolling over P.C.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
3. | 13-05-2019 | 1+700 | Rolling over P.C.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
4. | 09-05-2019 | 2+575 | PC laying in progress... | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
5. | 27-04-2019 | 5+900 | Rolling over p.c.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
6. | 27-04-2019 | 2+100 | Surface cleaning is in progress.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
7. | 25-04-2019 | Ch 4.200 | CE sir and SE sir and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
8. | 28-02-2019 | 0+000 | Site visit by Rajesh pant sir C.M.E sir.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
9. | 05-02-2019 | 5+290 | Excavation For K.C drain.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
10. | 05-02-2019 | 5+300 | Excavation For K.C drain.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
11. | 02-02-2019 | 3+300 | Fixing of crash barrier posts.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
12. | 29-01-2019 | Ch 4.250 | CME and EE sir inspection | Jagdish Narayan Meena | unknown | unknown | See Pic |
13. | 19-01-2019 | 2+450 | Casting of half causeway.PQC.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
14. | 19-01-2019 | 5+425 | Casting of half causeway PQC... | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
15. | 19-01-2019 | 5+425 | Casting of half causeway PQC.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
16. | 18-01-2019 | 2+750 | Excavation of half causeway. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
17. | 18-01-2019 | 2+750 | Excavation of half causeway. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
18. | 17-01-2019 | 2+800 | Casting of bed block of half culvert.. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
19. | 17-01-2019 | 2+800 | Casting of bed block of half culvert | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
20. | 30-12-2018 | 3+900 | Compaction of G3. | Azhar Shad | JE | UDRP R&B Bageshwar | See Pic |
|
|