Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Dhora-Ratankhan Motor Road Work Completed
Project: UDRP-RB UID: 1044 Sanction Cost: 351.24  lakh Length: 5.850 KM.
District: Almora Block: Lamgarha Constituency: Jageshwar Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision Type: VR
Procurement:
Package No.: 147        Package Name:  UDRP/PWD/09/01/RD/013(N)        Tender Date: 11-06-2018        Current Status: Agreement signed        Achieved on Date: 22-10-2018

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/01/RD/013(N)      Contractor Name: Technical Consultant and Construction Associates
Start Date:  30-10-2018      Intended Completion Date:  30-11-2019      Original End Date:  29-06-2019
Total Bond Cost: 40389569.89 (403.9 lakh)        Variation Cost: 546545.88 (5.47 lakh)    Hence Total Bond Cost is   40936115.77 (409.36 lakh) 
Sub Project Cost: 180.00  lakh        Variation Cost of Sub Project: -712346.49  (-7.12 lakh)       Total Sub Project Cost:   172.88 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.Hill side Cutting & Slip clearence0.38 KM2.7630-10-201825-06-20190.38 KM0.38 KM1.532.76
2.R/Wall, B/ Wall Type Protection works330.00 m18.6630-10-201831-01-2019330.00 m330.00 m10.318.66
3.G-20.50 KM5.8730-11-201830-12-20180.50 KM0.50 KM3.245.87
4.G-35.90 KM39.6505-11-201820-02-20195.90 KM5.90 KM21.939.65
5.PC/CC i/c Prime Coat, Tack Coat5.90 KM48.8715-03-201915-06-20195.90 KM5.90 KM26.9848.87
6.Cause Way3.00 No15.2028-11-201815-01-20193.00 No3.00 No8.3915.20
7.Culverts/Scupper 8.00 No14.7830-10-201830-01-20198.00 No8.00 No8.1614.78
8.longitudinal Drain4200.00 m6.2610-12-201830-01-20194200.00 m4200.00 m3.466.26
9.Crash Barrier250.00 m9.1301-05-201915-06-2019250.00 m250.00 m5.049.13
10.Parapet150.00 No4.1501-01-201930-03-2019150.00 No150.00 No2.294.15
11.Road Furniture285.00 No1.8015-05-201925-06-2019285.00 No285.00 No11.80
12.Env. Man & Moni Plan1.00 Job3.0515-12-201815-05-20191.00 Job1.00 Job1.683.05
13.Other Allied Works & Finishing Work 1.00 Job10.9115-12-201815-05-20191.00 Job1.00 Job6.0310.91
Total Amount: 181.09 100   181.09
Remarks: No Remarks       Work Program Made On: 17-11-2018        Updation of work program on: 26-05-2019       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.16-December-201510.89  lakh
2.27-January-201618.02  lakh
3.19-March-201614.39  lakh
4.08-April-20160.05  lakh
5.28-June-201616.09  lakh
6.27-October-20169.76  lakh
7.18-January-201711.43  lakh
Previous Package Expenditure Total 80.63  lakh
SNo. Date Payment
1.16-November-201833.66  lakh
2.13-December-201824.50  lakh
3.09-January-201927.48  lakh
4.15-February-201930.36  lakh
5.18-March-20192.03  lakh
6.17-May-201945.68  lakh
7.03-June-201915.35  lakh
8.20-September-20192.28  lakh
Total 181.34  lakh
% Payment104.89 %
Advance Amount:  0.00  lakh        Recovered Amount:  0.00  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 20   No. of Test Done : 20    No. of Test Passed : 20   No. of Test Failed : 0   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 88.01
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 115
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.13-05-20191+600Rolling over p.c..Azhar ShadJEUDRP R&B Bageshwar See Pic
2.13-05-20191+700Rolling over P.C..Azhar ShadJEUDRP R&B Bageshwar See Pic
3.13-05-20191+700Rolling over P.C..Azhar ShadJEUDRP R&B Bageshwar See Pic
4.09-05-20192+575PC laying in progress...Azhar ShadJEUDRP R&B Bageshwar See Pic
5.27-04-20195+900Rolling over p.c..Azhar ShadJEUDRP R&B Bageshwar See Pic
6.27-04-20192+100Surface cleaning is in progress..Azhar ShadJEUDRP R&B Bageshwar See Pic
7.25-04-2019Ch 4.200CE sir and SE sir and EE sir inspectionJagdish Narayan Meenaunknownunknown See Pic
8.28-02-20190+000Site visit by Rajesh pant sir C.M.E sir..Azhar ShadJEUDRP R&B Bageshwar See Pic
9.05-02-20195+290Excavation For K.C drain..Azhar ShadJEUDRP R&B Bageshwar See Pic
10.05-02-20195+300Excavation For K.C drain..Azhar ShadJEUDRP R&B Bageshwar See Pic
11.02-02-20193+300Fixing of crash barrier posts..Azhar ShadJEUDRP R&B Bageshwar See Pic
12.29-01-2019Ch 4.250CME and EE sir inspectionJagdish Narayan Meenaunknownunknown See Pic
13.19-01-20192+450Casting of half causeway.PQC..Azhar ShadJEUDRP R&B Bageshwar See Pic
14.19-01-20195+425Casting of half causeway PQC...Azhar ShadJEUDRP R&B Bageshwar See Pic
15.19-01-20195+425Casting of half causeway PQC..Azhar ShadJEUDRP R&B Bageshwar See Pic
16.18-01-20192+750Excavation of half causeway.Azhar ShadJEUDRP R&B Bageshwar See Pic
17.18-01-20192+750Excavation of half causeway.Azhar ShadJEUDRP R&B Bageshwar See Pic
18.17-01-20192+800Casting of bed block of half culvert..Azhar ShadJEUDRP R&B Bageshwar See Pic
19.17-01-20192+800Casting of bed block of half culvertAzhar ShadJEUDRP R&B Bageshwar See Pic
20.30-12-20183+900Compaction of G3.Azhar ShadJEUDRP R&B Bageshwar See Pic