Menu

Sub Project Profile Report

Project:  District: Package: Sub Project: 

Sub Project Profile Report

Pasiya-Pipna MR Work Completed
Project: UDRP-RB UID: 1028 Sanction Cost: 451.26  lakh Length: 15.000 KM.
District: Almora Block: Sult Constituency: Salt Circle: Pithoragarh WB Circle
DEA: DEA Bageshwar DSC: Royal Haskoning DHV DSC Scope: only Supervision Type: ODR
Procurement:
Package No.: 23        Package Name:  UDRP/PWD/09/03/RD/023        Tender Date: 22-02-2014        Current Status: Agreement signed        Achieved on Date: 09-09-2014

Construction Phase

Agreement Details
Bond/Agreement Name: UDRP/PWD/09/03/RD/023      Contractor Name: Trilok Singh Ram Singh Jamnal
Start Date:  16-09-2014      Intended Completion Date:  15-04-2016      Original End Date:  15-12-2015
Total Bond Cost: 75091114.5 (750.91 lakh)        Variation Cost: -2124403.62 (-21.24 lakh)    Hence Total Bond Cost is   72966710.88 (729.67 lakh) 
Sub Project Cost: 429.68  lakh        Variation Cost of Sub Project: -401456.85  (-4.01 lakh)       Total Sub Project Cost:   425.67 lakh
LD Analysis for Milestone1: Ld Not applicable        LD Analysis for Milestone2: Ld Not applicable       
Component Wise Progress
SNo. Progress Name As per Work Programme As per Actual
Quantity Amount
(in lakh)
Start Date End Date Target Quantity Achieved Quantity Progress(in %) Cost of completed work
(in lakh)
1.R/Wall, B/ Wall Type Protection works1200.00 m93.9516-09-201430-12-20161200.00 m1200.00 m22.0793.95
2.G-20.03 KM0.2203-10-201511-10-20150.03 KM0.03 KM0.050.22
3.G-32.88 KM4.4001-02-201530-10-20152.88 KM2.88 KM1.044.40
4.PC/CC i/c Prime Coat, Tack Coat15.00 KM179.2701-03-201515-06-201515.00 KM15.00 KM42.12179.27
5.Cause Way4.00 No15.1301-10-201415-11-20164.00 No4.00 No3.5515.13
6.Culverts/Scupper 22.00 No54.8601-10-201431-12-201622.00 No22.00 No12.8954.86
7.longitudinal Drain16000.00 m18.5816-12-201430-11-201612900.00 m12900.00 m4.3718.58
8.Crash Barrier4006.00 m4.1001-07-201530-12-20164006.00 m4006.00 m0.964.10
9.Parapet99.00 No34.1116-08-201530-09-2016660.00 No660.00 No8.0134.11
10.Road Furniture551.00 No7.7416-11-201531-12-20162073.00 No2073.00 No1.827.74
11.Other Allied Works & Finishing Work 1.00 Job13.2915-02-201630-11-20161.00 Job1.00 Job3.1213.29
Total Amount: 425.65 100   425.65
Remarks: No Remarks       Work Program Made On: 04-10-2014        Updation of work program on: 27-11-2017       
Work Program Status:Task Finish.
Financial Progress
SNo. Date Payment
1.03-December-201438.02  lakh
2.02-February-201554.79  lakh
3.31-March-201549.59  lakh
4.12-June-2015160.34  lakh
5.04-May-201692.55  lakh
6.30-July-201630.37  lakh
Total 425.66  lakh
% Payment100 %
Advance Amount:  241.28  lakh        Recovered Amount:  241.28  lakh        Balance to be Recovered  0.00  lakh        * Advances are at package level not sub project level
Tracking Signal of Subproject.
Pending Environmental & Social issues
Environment & Social Compliances(Package level):
Environment & Social Compliances(Sub Project level):
Detailed report of this subproject
Quality
No. of Test Required : 158   No. of Test Done : 143    No. of Test Passed : 129   No. of Test Failed : 14   Test report of this package      * Tests Information is at package level not sub project level
Quality Ranking in %: 89.82
No Notice issued.

Mobile Pic Upload

Number of Pics Available on Web Repository: 89
( last 20 Pics)
SNo. Creation date Landmark Remark Data Collector Designation Orgnization Pic
1.15-03-2016Ch 8.250Letter writting on culvertSanjeev BhattAEUDRP R&B Bageshwar See Pic
2.15-03-2016Ch 6.325Patch Repair workSanjeev BhattAEUDRP R&B Bageshwar See Pic
3.12-03-2016Ch 13.350Crash Barrier WorkSanjeev BhattAEUDRP R&B Bageshwar See Pic
4.10-03-2016Ch.6.750Patch repairingManoj SharmaJEUDRP R&B Bageshwar See Pic
5.10-03-2016Ch. 13.150Patch repairingManoj SharmaJEUDRP R&B Bageshwar See Pic
6.05-02-2016Ch 4.300Inspection by chief engineer sirSanjeev BhattAEUDRP R&B Bageshwar See Pic
7.05-02-2016Ch 14.650Inspection by C.E SirSanjeev BhattAEUDRP R&B Bageshwar See Pic
8.09-01-2016Ch 33.750Damage dry supper.Manoj SharmaJEUDRP R&B Bageshwar See Pic
9.09-01-2016Ch.14.2000Protection work.Manoj SharmaJEUDRP R&B Bageshwar See Pic
10.09-01-2016Ch.10.750Fixing of edge stone and const of b wall.Manoj SharmaJEUDRP R&B Bageshwar See Pic
11.09-01-2016Ch.10.050Const of b.wallManoj SharmaJEUDRP R&B Bageshwar See Pic
12.09-01-2016Fixing of edge stoneManoj SharmaJEUDRP R&B Bageshwar See Pic
13.08-01-2016Ch 8.250Construction of parapetsSanjeev BhattAEUDRP R&B Bageshwar See Pic
14.08-01-2016Ch 8.175Fixing of edge stoneSanjeev BhattAEUDRP R&B Bageshwar See Pic
15.08-01-2016Ch 3.110Construction of R / WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
16.08-01-2016Ch 2.650Construction of R/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
17.08-01-2016Ch 0.800Construction of B/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
18.29-12-2015Ch. 0.020Pucca drainManoj SharmaJEUDRP R&B Bageshwar See Pic
19.21-10-2015Ch 0.825Constt of B/WallSanjeev BhattAEUDRP R&B Bageshwar See Pic
20.19-10-20151.00SE VISITPrateek GuptaSite EngineerDSC5 R&B WB Almora See Pic