Pasiya-Pipna MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1028 |
Sanction Cost: |
451.26 lakh |
Length:
|
15.000 KM. |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 23
Package Name: 
UDRP/PWD/09/03/RD/023
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 09-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/03/RD/023
Contractor Name: Trilok Singh Ram Singh Jamnal
|
Start Date: 16-09-2014
Intended Completion Date: 15-04-2016
Original End Date: 15-12-2015 |
Total Bond Cost: 75091114.5 (750.91 lakh)
Variation Cost: -2124403.62 (-21.24 lakh) Hence Total Bond Cost is 72966710.88 (729.67 lakh)
|
Sub Project Cost: 429.68 lakh
Variation Cost of Sub Project: -401456.85 (-4.01 lakh)
Total Sub Project Cost:
425.67 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | R/Wall, B/ Wall Type Protection works | 1200.00 m | 93.95 | 16-09-2014 | 30-12-2016 | 1200.00 m | 1200.00 m | 22.07 | 93.95 | 2. | G-2 | 0.03 KM | 0.22 | 03-10-2015 | 11-10-2015 | 0.03 KM | 0.03 KM | 0.05 | 0.22 | 3. | G-3 | 2.88 KM | 4.40 | 01-02-2015 | 30-10-2015 | 2.88 KM | 2.88 KM | 1.04 | 4.40 | 4. | PC/CC i/c Prime Coat, Tack Coat | 15.00 KM | 179.27 | 01-03-2015 | 15-06-2015 | 15.00 KM | 15.00 KM | 42.12 | 179.27 | 5. | Cause Way | 4.00 No | 15.13 | 01-10-2014 | 15-11-2016 | 4.00 No | 4.00 No | 3.55 | 15.13 | 6. | Culverts/Scupper | 22.00 No | 54.86 | 01-10-2014 | 31-12-2016 | 22.00 No | 22.00 No | 12.89 | 54.86 | 7. | longitudinal Drain | 16000.00 m | 18.58 | 16-12-2014 | 30-11-2016 | 12900.00 m | 12900.00 m | 4.37 | 18.58 | 8. | Crash Barrier | 4006.00 m | 4.10 | 01-07-2015 | 30-12-2016 | 4006.00 m | 4006.00 m | 0.96 | 4.10 | 9. | Parapet | 99.00 No | 34.11 | 16-08-2015 | 30-09-2016 | 660.00 No | 660.00 No | 8.01 | 34.11 | 10. | Road Furniture | 551.00 No | 7.74 | 16-11-2015 | 31-12-2016 | 2073.00 No | 2073.00 No | 1.82 | 7.74 | 11. | Other Allied Works & Finishing Work | 1.00 Job | 13.29 | 15-02-2016 | 30-11-2016 | 1.00 Job | 1.00 Job | 3.12 | 13.29 |
Total Amount: |
425.65 |
|
100 |
425.65 |
|
Remarks:
No Remarks
Work Program Made On:
04-10-2014 } ?>
Updation of work program on:
27-11-2017
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 03-December-2014 | 38.02 lakh | 2. | 02-February-2015 | 54.79 lakh | 3. | 31-March-2015 | 49.59 lakh | 4. | 12-June-2015 | 160.34 lakh | 5. | 04-May-2016 | 92.55 lakh | 6. | 30-July-2016 | 30.37 lakh |
Total |
425.66 lakh |
% Payment | 100 % |
|
Advance Amount: 241.28 lakh
Recovered Amount: 241.28 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 158 No. of Test Done : 143 No. of Test Passed : 129 No. of Test Failed : 14 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.82 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 89 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 15-03-2016 | Ch 8.250 | Letter writting on culvert | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
2. | 15-03-2016 | Ch 6.325 | Patch Repair work | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
3. | 12-03-2016 | Ch 13.350 | Crash Barrier Work | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
4. | 10-03-2016 | Ch.6.750 | Patch repairing | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
5. | 10-03-2016 | Ch. 13.150 | Patch repairing | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
6. | 05-02-2016 | Ch 4.300 | Inspection by chief engineer sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
7. | 05-02-2016 | Ch 14.650 | Inspection by C.E Sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
8. | 09-01-2016 | Ch 33.750 | Damage dry supper. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
9. | 09-01-2016 | Ch.14.2000 | Protection work. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
10. | 09-01-2016 | Ch.10.750 | Fixing of edge stone and const of b wall. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
11. | 09-01-2016 | Ch.10.050 | Const of b.wall | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
12. | 09-01-2016 | | Fixing of edge stone | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
13. | 08-01-2016 | Ch 8.250 | Construction of parapets | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
14. | 08-01-2016 | Ch 8.175 | Fixing of edge stone | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
15. | 08-01-2016 | Ch 3.110 | Construction of R / Wall | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
16. | 08-01-2016 | Ch 2.650 | Construction of R/Wall | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
17. | 08-01-2016 | Ch 0.800 | Construction of B/Wall | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
18. | 29-12-2015 | Ch. 0.020 | Pucca drain | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
19. | 21-10-2015 | Ch 0.825 | Constt of B/Wall | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
20. | 19-10-2015 | 1.00 | SE VISIT | Prateek Gupta | Site Engineer | DSC5 R&B WB Almora | See Pic |
|
|