Chamkhala-Querala-Dabhra MR
Work Completed
|
Project: |
UDRP-RB |
UID: |
1007 |
Sanction Cost: |
329.59 lakh |
Length:
|
6.000 KM. |
District: |
Almora |
Block: |
Sult |
Constituency: |
Salt |
Circle: |
Pithoragarh WB Circle |
DEA: |
DEA Bageshwar |
DSC: |
Royal Haskoning DHV |
DSC Scope: |
only Supervision |
Type: |
ODR |
|
Procurement: |
Package No.: 23
Package Name: 
UDRP/PWD/09/03/RD/023
Tender Date: 22-02-2014
Current Status: Agreement signed
Achieved on Date: 09-09-2014 |
|
Construction Phase |
Agreement Details |
Bond/Agreement Name: UDRP/PWD/09/03/RD/023
Contractor Name: Trilok Singh Ram Singh Jamnal
|
Start Date: 16-09-2014
Intended Completion Date: 15-04-2016
Original End Date: 15-12-2015 |
Total Bond Cost: 75091114.5 (750.91 lakh)
Variation Cost: -2124403.62 (-21.24 lakh) Hence Total Bond Cost is 72966710.88 (729.67 lakh)
|
Sub Project Cost: 321.22 lakh
Variation Cost of Sub Project: -1722946.77 (-17.23 lakh)
Total Sub Project Cost:
303.99 lakh
|
LD Analysis for Milestone1: Ld Not applicable
LD Analysis for Milestone2: Ld Not applicable
|
|
Component Wise Progress
|
SNo. |
Progress Name |
As per Work Programme |
As per Actual |
Quantity |
Amount(in lakh) |
Start Date |
End Date |
Target Quantity |
Achieved Quantity |
Progress(in %) |
Cost of completed work(in lakh) |
1. | Hill side Cutting & Slip clearence | 2.00 KM | 28.00 | 16-09-2014 | 28-02-2015 | 2.00 KM | 2.00 KM | 9.21 | 28.00 | 2. | R/Wall, B/ Wall Type Protection works | 1316.00 m | 84.01 | 16-09-2014 | 30-12-2015 | 1316.00 m | 1316.00 m | 27.63 | 84.01 | 3. | GSB/RBI/G-1 | 2.00 KM | 10.95 | 16-10-2014 | 30-12-2015 | 2.00 KM | 2.00 KM | 3.6 | 10.95 | 4. | G-2 | 2.00 KM | 8.26 | 01-11-2014 | 30-12-2015 | 2.00 KM | 2.00 KM | 2.72 | 8.26 | 5. | G-3 | 2.20 KM | 8.64 | 01-02-2015 | 30-12-2015 | 2.20 KM | 2.20 KM | 2.84 | 8.64 | 6. | PC/CC i/c Prime Coat, Tack Coat | 6.00 KM | 70.18 | 16-04-2015 | 30-06-2015 | 6.00 KM | 6.00 KM | 23.09 | 70.18 | 7. | Culverts/Scupper | 13.00 No | 44.51 | 16-09-2014 | 31-01-2015 | 13.00 No | 13.00 No | 14.64 | 44.51 | 8. | longitudinal Drain | 5000.00 m | 9.25 | 01-12-2014 | 31-12-2015 | 5000.00 m | 5000.00 m | 3.04 | 9.25 | 9. | Crash Barrier | 464.00 m | 11.39 | 16-06-2015 | 15-04-2016 | 464.00 m | 464.00 m | 3.75 | 11.39 | 10. | Parapet | 248.00 No | 9.30 | 16-08-2015 | 30-11-2015 | 248.00 No | 248.00 No | 3.06 | 9.30 | 11. | Road Furniture | 2057.00 No | 2.63 | 16-11-2015 | 15-04-2016 | 2057.00 No | 2057.00 No | 0.87 | 2.63 | 12. | Other Allied Works & Finishing Work | 1.00 Job | 16.88 | 16-09-2014 | 15-04-2016 | 1.00 Job | 1.00 Job | 5.55 | 16.88 |
Total Amount: |
304 |
|
100 |
304 |
|
Remarks:
No Remarks
Work Program Made On:
04-10-2014 } ?>
Updation of work program on:
13-09-2019
|
|
Work Program Status:Task Finish. |
|
Financial Progress
|
SNo. |
Date |
Payment |
1. | 22-October-2014 | 54.57 lakh | 2. | 03-December-2014 | 23.84 lakh | 3. | 02-February-2015 | 28.11 lakh | 4. | 31-March-2015 | 50.90 lakh | 5. | 12-June-2015 | 118.62 lakh | 6. | 04-May-2016 | 16.14 lakh | 7. | 30-July-2016 | 11.81 lakh |
Total |
303.99 lakh |
% Payment | 100 % |
|
Advance Amount: 241.28 lakh
Recovered Amount: 241.28 lakh
Balance to be Recovered 0.00 lakh
* Advances are at package level not sub project level
|
Tracking Signal of Subproject. |
|
Pending Environmental & Social issues
|
|
Quality
|
No. of Test Required : 158 No. of Test Done : 143 No. of Test Passed : 129 No. of Test Failed : 14 Test report of this package
* Tests Information is at package level not sub project level |
|
Quality Ranking in %: 89.88 |
No Notice issued. |
Mobile Pic Upload |
Number of Pics Available on Web Repository: 68 |
( last 20 Pics) |
SNo. |
Creation date |
Landmark |
Remark |
Data Collector |
Designation |
Orgnization |
Pic |
1. | 05-04-2016 | 1+100 | Road visit | Ajay Kumar Pandey | QC | DSC5 R&B WB Almora | See Pic |
2. | 05-04-2016 | Ch 0.300 | Site visit Mr Deepak Malik Sir and T.L Sir | Sanjeev Bhatt | AE | UDRP R&B Bageshwar | See Pic |
3. | 10-03-2016 | Ch.7.900 | Patch repairing (due to slip zone ) | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
4. | 07-02-2016 | Km 8 | Excavation for vertical post of crash barrier. | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
5. | 09-01-2016 | Ch.2.140 | Const of parapet and kc drain | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
6. | 29-12-2015 | Ch. 8.950 | Inspection of work by SE sir shri G.K. Pangti | Manoj Sharma | JE | UDRP R&B Bageshwar | See Pic |
7. | 19-10-2015 | 8.00 | End point | Prateek Gupta | Site Engineer | DSC5 R&B WB Almora | See Pic |
8. | 07-05-2015 | Ch.0.00 | Mr. Mark visit at site | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
9. | 09-04-2015 | Ch. 8.140 | Pc surface of road and mts it. | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
10. | 09-04-2015 | Ch.1.250 | Spreading of tack coat | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
11. | 09-04-2015 | Ch. 1.500 | Pc work in progress | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
12. | 09-04-2015 | Ch. 7.090 | Checking mts of pc work. | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
13. | 08-04-2015 | Km 8 hm 0-2 | Premix surface of Road. | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
14. | 07-04-2015 | Km 1 HM 2-4 | Const of RCC culvert | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
15. | 07-04-2015 | Ch. 8.450 | Road surface after pc. | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
16. | 19-03-2015 | Ch.0.800 | CE visit at site | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
17. | 19-03-2015 | Ch.8.450 | Const of parapet and collection of grit for pc work. | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
18. | 19-03-2015 | Ch.7.555 | Storage of emulsion for prime and tack coat | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
19. | 19-03-2015 | Ch 7.750 | Road surface after WBM | Manoj Sharma | AE | DEA WB Bageshwar | See Pic |
20. | 19-03-2015 | Chg 8.45 | R. Wall with culvert | Santram | CE | PIU UDRP R&B | See Pic |
|
|