Birahi Village RB Alaknanda
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 179566000.00179565715.00
2 R/Wall, B/ Wall Type Protection works in (m) 0.000.00
3 Env. Man & Moni Plan in (Job) 2.002.00
4 Other Allied Works & Finishing Work in (Job) 15.0015.00
5 Excavation in Foundation in (cum) 10174.3410174.34
6 PCC in Foundation in (cum) 546.41546.41
7 Construction Embankments in (cum) 10019.8110019.81
8 Launching Aprons in (cum) 2375.772375.77
9 Excavation in soil in (cum) 34291.8634291.86
10 CC in R/W and B/W in (cum) 18771.4418771.44
11 RRM in R/W and B/W in (cum) 3891.243891.24
12 TMT Bar in R/W in (mt) 33.5433.54
13 H.P. Stone in (cum) 3461.863461.86
14 Quality in (%) 90.47