Progress Details Report

Maithana Alaknanda
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 107897000.00104536647.00
2 Env. Man & Moni Plan in (Job) 6.005.50
3 Other Allied Works & Finishing Work in (Job) 15.0014.00
4 Excavation in Foundation in (cum) 4738.004738.00
5 PCC in Foundation in (cum) 380.00378.70
6 Construction Embankments in (cum) 19401.0018500.00
7 Launching Aprons in (cum) 931.50921.60
8 Excavation in soil in (cum) 18457.0013889.00
9 CC in R/W and B/W in (cum) 10679.5010628.49
10 RRM in R/W and B/W in (cum) 4860.004860.00
11 TMT Bar in R/W in (mt) 25.5025.50
12 H.P. Stone in (cum) 3823.002869.00
13 Quality in (%) 90