Progress Details Report

Alakapuri Kathiyal Sain Alaknanda
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 109959000.0045838228.00
2 R/Wall, B/ Wall Type Protection works in (m) 0.000.00
3 Env. Man & Moni Plan in (Job) 2.002.00
4 Other Allied Works & Finishing Work in (Job) 15.003.00
5 Excavation in Foundation in (cum) 7301.005114.00
6 PCC in Foundation in (cum) 467.00200.00
7 Construction Embankments in (cum) 8974.001784.70
8 Launching Aprons in (cum) 2180.000.00
9 Excavation in soil in (cum) 33849.0010054.00
10 CC in R/W and B/W in (cum) 7711.003489.32
11 RRM in R/W and B/W in (cum) 11971.692508.00
12 TMT Bar in R/W in (mt) 11.007.77
13 H.P. Stone in (cum) 3850.00561.45
14 Quality in (%) 87.56