Progress Details Report

Banswara Mandakani
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 61099000.0046089113.00
2 Env. Man & Moni Plan in (Job) 6.005.00
3 Other Allied Works & Finishing Work in (Job) 15.0011.00
4 Excavation in Foundation in (cum) 4119.002945.00
5 PCC in Foundation in (cum) 304.00240.15
6 Construction Embankments in (cum) 4921.003070.00
7 Launching Aprons in (cum) 836.00650.00
8 Excavation in soil in (cum) 11039.007900.00
9 CC in R/W and B/W in (cum) 3711.003410.00
10 RRM in R/W and B/W in (cum) 5534.004606.93
11 TMT Bar in R/W in (mt) 27.0021.16
12 H.P. Stone in (cum) 2470.002000.00
13 Quality in (%) 90