Progress Details Report

Ladies Police Station, Srinagar
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 96262000.0097412345.00
2 Site Development in (Job) 15.8715.87
3 Foundation and Plinth Work in (Job) 14.5314.53
4 Structural Frame in (Job) 29.8729.87
5 Doors & Windows in (Job) 11.2611.26
6 Water Supply and Sanitary work in (Job) 3.403.40
7 Electrification Works in (Job) 10.3410.34
8 Other Allied Works & Finishing Work in (Job) 14.7314.73
9 Quality in (%) 87.63