Progress Details Report

Food Godown, srinagar
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 34456000.0034553064.00
2 Site Development in (Job) 34.9034.90
3 Foundation and Plinth Work in (Job) 21.4421.44
4 Structural Frame in (Job) 24.3424.34
5 Doors & Windows in (Job) 1.621.62
6 Water Supply and Sanitary work in (Job) 7.317.31
7 Electrification Works in (Job) 2.222.22
8 Other Allied Works & Finishing Work in (Job) 32.5632.56
9 Quality in (%) 89.42