Progress Details Report

Primary School Barsu (Rudrapryag)
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 6696000.005968802.00
2 Site Development in (Job) 22.9322.93
3 Foundation and Plinth Work in (Job) 22.6622.66
4 Structural Frame in (Job) 24.5924.59
5 Doors & Windows in (Job) 5.925.92
6 Electrification Works in (Job) 2.672.67
7 Other Allied Works & Finishing Work in (Job) 21.2321.23
8 Quality in (%) 95