Progress Details Report

Govt Inter College Ghimtoli
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 40679000.0037944033.00
2 Site Development in (Job) 3.183.18
3 Foundation and Plinth Work in (Job) 17.6217.62
4 Structural Frame in (Job) 39.7039.70
5 Doors & Windows in (Job) 10.1210.12
6 Water Supply and Sanitary work in (Job) 2.422.42
7 Electrification Works in (Job) 6.476.47
8 Other Allied Works & Finishing Work in (Job) 20.4920.49
9 Quality in (%) 91.71