Progress Details Report

Sub- Center Baluwakot
* click on component name for more details
S.No. Progress Component Total Target Total Achievement
1 Expenditure in (Rs.) 16090000.0016258011.00
2 Site Development in (Job) 1.541.54
3 Foundation and Plinth Work in (Job) 18.2118.21
4 Structural Frame in (Job) 42.7842.78
5 Doors & Windows in (Job) 4.654.65
6 Water Supply and Sanitary work in (Job) 5.885.88
7 Electrification Works in (Job) 12.7312.73
8 Other Allied Works & Finishing Work in (Job) 14.2014.20
9 Quality in (%) 90.95